IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Dadheech Infrastructures Private Limited - Appellant
Versus
DTE Gen MD Accn Project - Respondent
O.M.P.(I) (COMM.) 3 of 2021 & I.A. 195 of 2021 and I.A. 196 of 2021
Decided On : 07-01-2021
| Table of Content |
|---|
| 1. introduction of contract and guarantees involved. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7) |
| 2. petitioner's argument against invocation of bank guarantees. (Para 8) |
| 3. court's reasoning on bank guarantees and conditions of invocation. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19) |
| 4. legal stance on the contract's termination and specific relief. (Para 20) |
| 5. final decision to dismiss the petition. (Para 21) |
JUDGMENT
[Hearing held through video conferencing]
Vibhu Bakhru, J. (Oral)--The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter `the Act'), inter alia, praying that the respondent may be restrained from invoking and encashing the Performance Bank Guarantees - Bank Guarantee No.0770171GPER0040 for an amount of Rs.11,00,00,000/- and Bank Guarantee No. 0770171GPER0042 for an amount of Rs.2,91,00,000/- (hereafter referred to as the `Performance Bank Guarantees'). The petitioner further prays that the respondent may be injuncted from encashing the Retention Guarantees being the Bank Guarantees furnished by the petitioner against disbursal of Retention Money, being Bank Guarantee No. 0770171GPER0037 for a sum of Rs.20,76,000/-; Bank Guarantee No. 0770171GPER0039 for a sum of Rs.2,07,50,000/-; and Bank Guarantee No. 0770171GPER0041 for a sum of Rs.1,80,00,000/- (hereafter referred to as `Retention Bank Guarantees'). In addition, the petitioner also prays that respondent no.1 be restrained from giving effect to letter bearing no. 84828/MAP/PHASE-II/PKG-25/R&C/1656/E8 dated 04.01.2021 unlawfully cancelling the Contract Agreement No.DG MAP/PHASEII/PKG-25 (R&C) 01 of 2013-14 (hereafter `the Contract').
2. The petitioner was awarded the Contract for construction of dwelling units including allied services at Ahmedabad, Gandhinagar and Chiloda ("DGMAP/PHASE-II/PKG-25(R&C)/01 OF 2013-2014: COMPLETION OF BALANCE WORKS OF CONSTRUCTION OF DWELLING UNITS INCLUDING ALLIED SERVICES FOR OFFICERS & JCOS/OR AT AHMEDABAD, GANDHINAGAR AND CHILODA" as detailed in Tender Enquiry vide letter no. 84828/MAP/PH-11/PKG-25/R&C/27/EB DT 12.07.2012 as amended by letters dated 02.08.2013, 12.08.2013, 19.08.2013 and 22.08.2013)
3. The petitioner had tendered for the aforesaid works pursuant to notices inviting tenders issued by respondent no.1. The petitioner's tender was accepted and by a letter dated 11.10.2013, respondent no.1 informed the petitioner that it had accepted the petitioner's offer for completing the works for a sum of Rs.2,78,16,52,390.08/-. The said parties also signed a formal Contract.
4. In terms of the said Contract, the petitioner furnished the two Performance Bank Guarantees, as mentioned above. Certain interim payments were made to the petitioner after retaining a specified proportion in terms of the Contract. The said retention money was also disbursed against Retention Bank Guarantees.
5. The works were to be executed within a period of twenty-four months. Admittedly, the execution of the works has been delayed and according to the petitioner, about 62% of the works are complete. The petitioner claims that the delay in completion of the Contract is not on account of any reason attributable to the petitioner but mainly on account of delay on the part of respondent no.1 in performing its obligations. The petitioner states that there was a considerable delay in handing over of the Site and the period of twenty-four months would not commence only when the complete Site was handed over to the petitioner. In addition, respondent no. 1 had also delayed handing over drawings. The petitioner states that it had sent letters setting out the reasons for the delay and seeking extension of time for completion of the Contract. However, instead of addressing the issues and extending the term of the Contract, respondent no.1 had blamed the petitioner for not maintaining adequate progress.
6. It is apparent that disputes arisen between the parties in relation
The court ruled that bank guarantees must be honored regardless of existing disputes, affirming their unconditional nature and limiting judicial intervention to cases involving fraud or irretrievable....
The unconditional nature of bank guarantees requires them to be honored despite disputes between the parties, and specific enforcement of a contract is impermissible under the Specific Relief Act, 19....
Bank guarantees cannot be interdicted on account of contractual disputes between the parties, and exceptions for interdicting bank guarantees include cases of egregious fraud and irretrievable injust....
The court reinforced that unconditional bank guarantees cannot be restrained unless egregious fraud or irretrievable injustice is established, which was not proven by the petitioner.
A party seeking to restrain the invocation of a bank guarantee must demonstrate either clear fraud or irretrievable injustice; mere contractual disputes do not suffice for injunctions.
Unconditional bank guarantees can only be interdicted on grounds of egregious fraud and special equities.
Bank - Bank guarantee cannot invoke - Bank guarantees cannot be interdicted on account of disputes between parties and any allegation that respondent has been reluctant to join proceedings for an ami....
Bank guarantees can only be interdicted in exceptional circumstances such as fraud or irretrievable injustice. Mere contractual disputes do not give rise to special equities for interdicting a bank g....
Bank guarantees cannot be interdicted due to contractual disputes unless fraud or irretrievable injustice is established.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.