SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Dadheech Infrastructures Private Limited - Appellant
Versus
DTE Gen MD Accn Project - Respondent
O.M.P.(I) (COMM.) 3 of 2021 & I.A. 195 of 2021 and I.A. 196 of 2021
Decided On : 07-01-2021




The court ruled that bank guarantees must be honored regardless of existing disputes, affirming their unconditional nature and limiting judicial intervention to cases involving fraud or irretrievable injustice.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 9 - Invocation of Bank Guarantees - Petitioner seeks to restrain invocation of Performance and Retention Bank Guarantees amidst disputes regarding contract execution and termination. Court upheld that guarantees must be honored irrespective of disputes. (Paras 9, 12, 18)

(B) Contracts - Nature of Bank Guarantees - Unconditionality of bank guarantees affirmed; invocation does not require proof of loss or damage nor concern over contract performance. (Paras 10, 19)

Facts of the case:
The petitioner entered into a contract for construction work and submitted multiple bank guarantees. Disputes arose regarding delays attributed to the respondent's obligations, leading to the termination of the contract, and subsequent invocation of bank guarantees.

Findings of Court:
The invocation of bank guarantees is valid and must be honored, as contract termination does not prevent enforcement.

Issues: The primary issues involved the legality of contract termination and the conditions under which bank guarantees can be invoked.

Ratio Decidendi: The court established that the terms of the bank guarantees are unconditional, and disputes between parties do not impede invocation, emphasizing the importance of honoring bank guarantees without judicial interference unless cases of egregious fraud arise.

Result: Petition dismissed.

Table of Content
1. introduction of contract and guarantees involved. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7)
2. petitioner's argument against invocation of bank guarantees. (Para 8)
3. court's reasoning on bank guarantees and conditions of invocation. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19)
4. legal stance on the contract's termination and specific relief. (Para 20)
5. final decision to dismiss the petition. (Para 21)

JUDGMENT

[Hearing held through video conferencing]

Vibhu Bakhru, J. (Oral)--The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter `the Act'), inter alia, praying that the respondent may be restrained from invoking and encashing the Performance Bank Guarantees - Bank Guarantee No.0770171GPER0040 for an amount of Rs.11,00,00,000/- and Bank Guarantee No. 0770171GPER0042 for an amount of Rs.2,91,00,000/- (hereafter referred to as the `Performance Bank Guarantees'). The petitioner further prays that the respondent may be injuncted from encashing the Retention Guarantees being the Bank Guarantees furnished by the petitioner against disbursal of Retention Money, being Bank Guarantee No. 0770171GPER0037 for a sum of Rs.20,76,000/-; Bank Guarantee No. 0770171GPER0039 for a sum of Rs.2,07,50,000/-; and Bank Guarantee No. 0770171GPER0041 for a sum of Rs.1,80,00,000/- (hereafter referred to as `Retention Bank Guarantees'). In addition, the petitioner also prays that respondent no.1 be restrained from giving effect to letter bearing no. 84828/MAP/PHASE-II/PKG-25/R&C/1656/E8 dated 04.01.2021 unlawfully cancelling the Contract Agreement No.DG MAP/PHASEII/PKG-25 (R&C) 01 of 2013-14 (hereafter `the Contract').

2. The petitioner was awarded the Contract for construction of dwelling units including allied services at Ahmedabad, Gandhinagar and Chiloda ("DGMAP/PHASE-II/PKG-25(R&C)/01 OF 2013-2014: COMPLETION OF BALANCE WORKS OF CONSTRUCTION OF DWELLING UNITS INCLUDING ALLIED SERVICES FOR OFFICERS & JCOS/OR AT AHMEDABAD, GANDHINAGAR AND CHILODA" as detailed in Tender Enquiry vide letter no. 84828/MAP/PH-11/PKG-25/R&C/27/EB DT 12.07.2012 as amended by letters dated 02.08.2013, 12.08.2013, 19.08.2013 and 22.08.2013)

3. The petitioner had tendered for the aforesaid works pursuant to notices inviting tenders issued by respondent no.1. The petitioner's tender was accepted and by a letter dated 11.10.2013, respondent no.1 informed the petitioner that it had accepted the petitioner's offer for completing the works for a sum of Rs.2,78,16,52,390.08/-. The said parties also signed a formal Contract.

4. In terms of the said Contract, the petitioner furnished the two Performance Bank Guarantees, as mentioned above. Certain interim payments were made to the petitioner after retaining a specified proportion in terms of the Contract. The said retention money was also disbursed against Retention Bank Guarantees.

5. The works were to be executed within a period of twenty-four months. Admittedly, the execution of the works has been delayed and according to the petitioner, about 62% of the works are complete. The petitioner claims that the delay in completion of the Contract is not on account of any reason attributable to the petitioner but mainly on account of delay on the part of respondent no.1 in performing its obligations. The petitioner states that there was a considerable delay in handing over of the Site and the period of twenty-four months would not commence only when the complete Site was handed over to the petitioner. In addition, respondent no. 1 had also delayed handing over drawings. The petitioner states that it had sent letters setting out the reasons for the delay and seeking extension of time for completion of the Contract. However, instead of addressing the issues and extending the term of the Contract, respondent no.1 had blamed the petitioner for not maintaining adequate progress.

6. It is apparent that disputes arisen between the parties in relation

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top