IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Union of India - Appellant
Versus
NCC Limited - Respondent
O.M.P. (COMM) 112 of 2021
Decided On : 12-03-2021
| Table of Content |
|---|
| 1. delay applications (Para 1 , 2 , 3) |
| 2. background of contract (Para 4 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15) |
| 3. grounds for impugning award (Para 5 , 17 , 22 , 23) |
| 4. tribunal's discretion in claims (Para 16 , 18 , 20 , 21 , 28 , 29) |
| 5. no demand certificate fulfillment (Para 24 , 25 , 26 , 27) |
| 6. outcome of the petition (Para 31 , 32) |
JUDGMENT
Vibhu Bakhru, J. (Oral)
I.A. 3836/2021 & I.A. 3840/2021
1. For the reasons stated in the application, the delay in filing as well as re-filing is condoned.
2. The application is disposed of.
I.A. 3837/2021 & I.A. 3838/2021
3. Allowed, subject to all just exceptions.
O.M.P. (COMM) 112/2021 & I.A. 3839/2021
4. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter the `A&C Act'), impugning the interim award (hereafter `the impugned award') passed by the Arbitral Tribunal comprising of a Sole Arbitrator. By the impugned award, the Arbitral Tribunal had directed that the Performance Bank Guarantee (Bank Guarantee No. 130391 BG 0000505) for a sum of Rs.15,06,31,160/-, furnished by the respondent (hereafter `NCC') be returned to NCC, with the attendant direction to replace the same by a Bank Guarantee in the sum of Rs.1.5 crores.
5. The petitioner contends that the impugned award is patently illegal as it effectively dilutes the security available with the petitioner, to recover its counter-claims. According to the petitioner, the performance of the contract was delayed inordinately and it is entitled to recover damages, which have been articulated as counter-claims. The petitioner contends that such an interim award, without adjudication of its counter claims, is patently illegal and is liable to be set aside.
6. The controversy in the present case arises in the following context:
7. On 21.12.2009, the petitioner issued a Notice Inviting Tenders (NIT) for "Construction of Dwelling Units including allied services for officers, Senior Sailors & Junior Sailors at Naval Station (Dolphin Hill, DGNP site), Bheemunipatnam (Navy), Vizag". NCC submitted its bid pursuant to the said NIT.
8. On 05.03.2010, the petitioner issued the Letter of Award (LoA), awarding the contract for the construction of dwelling units including allied services for officers, senior sailors and junior sailors at three sites - Dolphin Hill, DGNP Site and Bheemunipatnam (Navy site) - at Vizag. In terms of the LoA, NCC was required to construct 1,369 Dwelling Units (hereafter DUs). The construction was planned in three Pockets and one hundred and seven blocks as under:
| Srl No | Pockets | No of DUs |
| 1 | Bheemunipatnam | 70 |
| 2 | Dolphin Hill | 470 |
| 3 | DGNP Site | 829 |
9. The period of completion of the works was stipulated as twenty-five months. The construction was to be completed in five phases and separate dates for commencement and completion of construction for each phase were stipulated in the Work Order - Work Order No.1 was issued on 18.03.2010.
10. In terms of the contract between the parties, the original date for completion of the last phase of the contract (Phase-V) was stipulated as 17.04.2012. The work in respect of the other phases was to be completed earlier. However, the dates of completion in respect of the five phases were extended from time to time.
11. The work commenced as per Work Order-I on 18.03.2010 and was completed on 13.08.2015.
12. The contract between the parties stipulated the defect liability period as two years. This period expired on 12.08.2017.
13. The respondent submitted its Final Bill on 09.11.2016, which included an undisputed amount as well as the disputed amount. Though the undisputed portion of the Final Bill was for a sum of Rs.1,31,02,606.50, however, a sum of Rs.1,07,91,165/- was released to the respondent.
14. The disputes between the parties have been referred to arbitration. The same also includes NCC's claim regarding return of the Bank Gurantee (Bank Guarantee No. 130391 BG 0000505) for a sum of
The court upheld the arbitral award directing the release of the performance bank guarantee, finding all contractual requirements were satisfied and counter claims were untimely.
The main legal point established in the judgment is the limited scope of interference in Arbitral Awards and the importance of complying with contractual conditions, such as the submission of a No De....
The court affirmed that a performance security cannot be withheld post-acknowledgment of contract performance, and interim relief must balance equities in arbitration under Section 17 of the Act.
Statutory limitation under Section 34 of the Arbitration Act is strict and cannot be relaxed without sufficient justification; defective petitions lead to being treated as non-est.
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Point of Law : Arbitral Tribunal had erred in concluding that the petitioner had abandoned the works, is also unpersuasive. The finding that the petitioner had abandoned the works is a finding of fac....
The Arbitral Tribunal's decision falls within its jurisdiction and does not amount to patent illegality, as it was based on a plausible interpretation of the exclusionary clause in the contracts and ....
The Arbitral Tribunal has considerable discretion in evaluating evidence and interpreting contract clauses, and its decision cannot be interfered with unless found to be patently illegal or in confli....
An interim order can restrain the encashment of bank guarantees pending arbitration if there is a risk of irreparable harm to the aggrieved party.
The court emphasizes the right to arbitration under the contractual agreement when disputes arise, affirming the appointment of arbitrators for effective resolution.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.