IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
National Highways Authority of India - Appellant
Versus
Afcons Infrastructure Ltd. - Respondent
O.M.P. (COMM) 96 of 2016
Decided On : 23-03-2021
| Table of Content |
|---|
| 1. overview of contractual obligations (Para 1 , 2 , 3 , 4 , 5) |
| 2. dispute escalation and arbitration process (Para 6 , 7 , 8 , 9 , 10) |
| 3. tribunal's assessment of claims (Para 11 , 12 , 13) |
| 4. arguments presented by nhai and afcons (Para 14 , 15 , 16 , 17) |
| 5. details on clause 52.2 of copa (Para 19 , 20 , 21 , 22) |
| 6. determination of the new rate (Para 23 , 24 , 25) |
| 7. tribunal’s rationale and findings (Para 26 , 27 , 28 , 29) |
| 8. prior case law supporting tribunal's view (Para 30 , 31 , 32 , 33) |
| 9. judicial review of arbitral decision (Para 34 , 35) |
| 10. final ruling and dismissal of the petition (Para 36 , 37 , 38) |
JUDGMENT
Vibhu Bakhru, J. The petitioner (hereinafter `NHAI') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act'), inter alia, impugning the Arbitral Award dated 30.08.2012 (hereinafter `the impugned award') passed by the Arbitral Tribunal comprising of Mr. SK Jain (Presiding Arbitrator), Mr. Amar Singh Chauhan and Mr. P Sridharan.
2. The impugned award was rendered in respect of disputes that had arisen between the parties in relation to a contract dated 22.05.2001 (hereinafter `the agreement') entered into between the parties for execution of the project involving "Widening to 4-lanes and Rehabilitation of Existing 2 lane Carriageway of Poonamalle- Kanchipuram Road (NH-4), Package 1, from km 13.80 to km 70.20." (hereinafter `the Project")
3. The respondent (hereinafter `Afcons') submitted its bid on 22.02.2001, which was accepted by NHAI vide Letter of Acceptance dated 09.04.2001 and subsequently, an agreement dated 22.05.2001 was executed between the parties.
4. The parties had entered into the agreement for execution of the Project at a contract price of Rs.164,37,67,899/-. The Project was to be executed within a period of thirty months from 02.07.2001 with a completion date of 31.12.2003.
5. Disputes arose between NHAI and Afcons due to a disagreement on the rate of Item No. 3.02, Wet Mix Macadam (WMM) mentioned in the Bill of Quantity (BOQ). The BOQ indicated an estimated quantity of 1,91,212 cum. Afcons had quoted a rate of Rs.545 per cum for execution of WMM and the quoted amount for executing 1,91,212 cum was Rs.10,42,10,540/-. The total bid submitted by Afcons for executing the works was Rs.169,29,67,899/-. However, Afcons also gave a lumpsum rebate of Rs.4,92,00,000/- and revised its bid to Rs.164,37,67,899, which was accepted by NHAI. In view of the above rebate, the unit item of Rs.545 per cum for BOQ Item No. 3.02 - WMM stood reduced to Rs.529.16 per cum and the total amount accepted for executing 1,91,212 cum of the said works amounted to Rs.10,11,81,742. This constituted 6.15% of the Contract value after applying the necessary rebate.
6. Admittedly, the quantity of the said BOQ item No. 3.02 - WMM exceeded the estimated quantity beyond the limits as envisaged under Clause 52.2 of the Conditions of Particular Application (hereinafter `COPA'). In the circumstances, Afcons sent a letter dated 08.10.2007 to the Engineer submitting its analysis of the rates for determining a new rate for WMM. Afcons claimed a rate of Rs.831/- per cum which was based on the Ministry of Road Transport and Highways (MoRTH) norms.
7. The Engineer accepted that there was a change in the quantity that had triggered Clause 52.2 of COPA. However, it did not accept the rate of Rs.831/- per cum as submitted by Afcons and fixed a price of Rs.591/- per cum. The same was not acceptable to NHAI. The disputes were escalated and the parties were referred to Arbitration.
8. In terms of Clause 67.1 of COPA, the disputes between NHAI and Afcons were required to be referred to the Engineer. If the decision of the Engineer was not accepted, the disputes were required to be settled by arbitration.
9. In terms of Clause 67.1 of COPA, Afcons sent a letter dated 22.04.2008 and referred the disputes to the Engineer. The Engineer rendered his decision on
AI
An arbitrator may revise contract rates if the original rates become inappropriate due to variations in the quantity of work executed, as per applicable contractual clauses.
Project – Fixation of rate - Once a rate has been found to be inappropriate or inapplicable on account of variation in the quantity beyond the stipulated limit, then the new rate would be applicable ....
(1) Appeal against arbitral award – Arbitral award may not be interfered with if view taken by Arbitrator is a possible view based on facts – Court cannot undertake independent assessment of merits o....
The court affirmed that arbitral awards are upheld unless blatant illegality is shown, emphasizing the tribunal's final authority under Section 34 of the Arbitration and Conciliation Act.
The court upheld the Tribunal's award, emphasizing limited grounds for interference under Section 19, confirming the Tribunal's jurisdiction and decision-making process regarding construction claims.
Patent illegality should be illegality which goes to the root of the matter. In other words, every error of law committed by the Arbitral Tribunal would not fall within the expression ‘patent illegal....
The court upheld the Arbitrator's award, emphasizing that unilateral alterations to agreed contract rates without mutual consent are impermissible under the Arbitration and Conciliation Act, 1996.
The court emphasized that arbitration awards must adhere strictly to contract terms regarding payment and interest, rejecting arbitrary reductions of entitlement.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.