SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
KMC Construction Ltd. - Appellant
Versus
National Highway Authority of India - Respondent
O.M.P. (COMM.) 458 of 2020, I.A. Nos. 257 of 2021 and 2649 of 2021
Decided On : 23-12-2021




The court emphasized that arbitration awards must adhere strictly to contract terms regarding payment and interest, rejecting arbitrary reductions of entitlement.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - Petition filed regarding claims under the contract for construction work - Key issues involved entitlement to payment adjustments for variations and entitlements upon contract completion. (Paras 1, 3.1, 10, 22, 28, 59)

(B) Contractual interpretation - The tribunal found that any rebates on contract prices applied to all Bill of Quantities (BOQ) items, affecting escalation claims. (Paras 12, 19, 20)

(C) Award of interest - Court set aside the reduction of interest from contractual terms, emphasizing entitlement as per the agreement. (Paras 51-58)

Facts of the case:
The contractor completed a highway project earlier than expected but faced payment disputes and the invocation of a performance bank guarantee. The disputes led to arbitration where multiple claims were raised. (Paras 3.1, 3.4)

Findings of Court:
The tribunal's decision to reject KMC's claims for escalation, excess payment adjustments, and bonus for early completion was maintained. The tribunal ruled that the contractor was entitled to certain interests and commission payments, but reduced awarded interest. (Paras 32, 35, 51)

Issues: Whether the adjustments in payment and interest awarded by the tribunal were appropriate under the contract's terms. (Paras 40, 56)

Ratio Decidendi: The court affirmed that the award must adhere to the contract stipulations on interest and payment adjustments and cannot arbitrarily reduce them based on perceived burdens. (Paras 56-58)

Result: Petition allowed in part by setting aside the interest reduction imposed by the tribunal.

Table of Content
1. factual background of the arbitration case. (Para 1 , 2 , 3)
2. overview of claims and counter-claims. (Para 4 , 5)
3. modification application filed by kmc. (Para 6)
4. arguments presented by kmc in arbitration. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13)
5. court's analysis and observations on claims. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58)
6. final ruling and order of the court. (Para 59 , 60)

JUDGMENT

Vibhu Bakhru, J.

1. The petitioner (hereafter `KMC') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an Arbitral Award dated 24.09.2019 (hereafter `the impugned award') rendered by an Arbitral Tribunal constituted by three members (hereafter `the Arbitral Tribunal'). KMC also impugns an order dated 21.11.2019 (hereafter the `revised order'), whereby its application under Section 33 of the A&C Act was rejected.

2. KMC challenges the impugned award in respect of its Claims Nos. 3, 5, 13, 19 and 22.

3. Briefly stated, the facts that are necessary to address the controversy are stated hereunder.

3.1. NHAI, by a Letter of Acceptance (LoA) dated 22.08.2001, awarded a contract for the work of `Widening to four lanes and strengthening of the existing two lane carriageway between Km 278/000 to Km 340/000 of Udaipur-Ratanpur-Gandhinagar Section of NH-8 in Rajasthan, package no. UG-1' (hereafter the `Project') to KMC. Subsequently, the parties entered into an agreement dated 05.10.2001 (hereafter `the Agreement'). In terms of the Agreement, KMC agreed to execute the works at a Contract Price of Rs.164,75,76,353/-. The works for the Project were to commence on 30.10.2001 and completed by 30.04.2004.

3.2. It is KMC's case that NHAI had failed to handover the site to it and had provided an incorrect Detailed Project Report (DPR). Despite this, KMC completed the project two months prior to the stipulated date of completion. The works were completed on 28.02.2004 at a Contract Price of Rs.248,00,00,000/- against the original Contract Price of Rs.164,75,76,353/-. KMC submitted its completion statement on 08.05.2004. It is KMC's case that the Engineer did not process the payments due to it and extended the defect liability period. Finally, the Engineer issued the Defect Liability Certificate on 24.05.2006. The Engineer issued a Statement at Completion proposing a recovery of Rs.18,16,34,122/- against the Final Bill of Rs.70,51,84,650/-. Further, the Engineer did not give its decision on the other sums payable to KMC.

3.3. NHAI invoked the Performance Bank Guarantee furnished by KMC in the sum of Rs.16,47,57,636/-.

3.4. In view of the disputes, KMC invoked the Arbitration Agreement by a letter dated 16.09.2006 and nominated Sh PV Rama Raju as an Arbitrator. NHAI nominated Sh VS Dixit as its nominee Arbitrator. Both nominated Arbitrators appointed Sh Prafulla Kumar as the Presiding Arbitrator and the Arbitral Tribunal was constituted on 12.11.2006.

3.5. In the meanwhile, KMC also filed a Writ Petition (bearing W.P. No. 18269/2006) before the High Court of Andhra Pradesh seeking interdiction of the invocation of the Bank Guarantee. By an order dated 29.11.2006, that High Court restrained NHAI from encashing the aforesaid Bank Guarantee. NHAI appealed against the aforesaid order before the Division Bench of the High Court of Andhra Pradesh and the Court ordered KMC to keep the Bank Guarantee alive during the course of the arbitration proceedings.

3.6. Before the Arbitral Tribunal, KMC raised twenty-two claims aggregating to Rs.135,96,28,549/-. NHAI filed its Statement of Defence and also raised counter-claims.

3.7. By a letter dated 11.10.2013 addressed to the Arbitral Tribunal, both parties requested the Arbitral Tribunal to keep the arbitral proceedings in abe





















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top