IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
National Highways Authority of India - Appellant
Versus
KMC Construction Ltd. - Respondent
O.M.P. (COMM.) 461 of 2020, I.A. Nos. 7760 of 2020 and 2327 of 2021
Decided On : 23-12-2021
| Table of Content |
|---|
| 1. overview of arbitral tribunal's award. (Para 4 , 5) |
| 2. parties' arguments against the arbitral award. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13) |
| 3. evaluation of claim no. 1 and engineer's role. (Para 14 , 15 , 16 , 17 , 18 , 19) |
| 4. interpretation of clause 52.3 and entitlement for additional overheads. (Para 23 , 24 , 25 , 26 , 27) |
| 5. assessment of kmc's claim regarding idling charges. (Para 31 , 32 , 34 , 35 , 36 , 39) |
| 6. conclusion regarding the reasonableness of interest rates. (Para 44) |
JUDGMENT
Vibhu Bakhru, J.
1. The petitioner (hereafter `NHAI') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an Arbitral Award dated 24.09.2019 (hereafter `the impugned award') rendered by an Arbitral Tribunal constituted by three members (hereafter `the Arbitral Tribunal').
2. NHAI challenges the impugned award to the limited extent that it allows KMC's claims for certain extra items (E-2, E-4, E-12, E-16, R2-05, CD-02 & 03) forming part of Claim No. 1 and to the extent that it allows KMC's Claim Nos. 12, 14 and 22.
3. Briefly stated the facts that are necessary to address the controversy are stated hereunder.
3.1. NHAI, by a Letter of Acceptance (LoA) dated 22.08.2001, awarded a contract for the work of `Widening to four lanes and strengthening of the existing two lane carriageway between Km 278/000 to Km 340/000 of Udaipur-Ratanpur-Gandhinagar Section of NH-8 in Rajasthan, package no. UG-1' (hereafter `the Project') to KMC. Subsequently, the parties entered into an agreement dated 05.10.2001 (hereafter `the Agreement'). In terms of the Agreement, KMC agreed to execute the works at a Contract Price of Rs.164,75,76,353/-. The works for the Project were to commence on 30.10.2001 and completed by 30.04.2004.
3.2. It is KMC's case that NHAI had failed to handover the site to it and had provided an incorrect Detailed Project Report (DPR). Despite this, KMC completed the project two months prior to the stipulated date of completion. The works were completed on 28.02.2004 at a Contract Price of Rs.248,00,00,000/- against the original Contract Price of Rs.164,75,76,353/-. KMC submitted its completion statement on 08.05.2004. It is KMC's case that the Engineer did not process the payments due to it and extended the defect liability period. Finally, the Engineer issued the Defect Liability Certificate on 24.05.2006. The Engineer issued a Statement at Completion proposing a recovery of Rs.18,16,34,122/- against the Final Bill of Rs.70,51,84,650/-. Further, the Engineer did not give its decision on the other sums payable to KMC.
3.3. NHAI invoked the Performance Bank Guarantee furnished by KMC in the sum of Rs.16,47,57,636/-.
3.4. In view of the disputes, KMC invoked the Arbitration Agreement by a letter dated 16.09.2006 and nominated Sh. P.V. Rama Raju as an Arbitrator. NHAI nominated Sh. V.S. Dixit as its nominee Arbitrator. Both nominated Arbitrators appointed Sh. Prafulla Kumar as the Presiding Arbitrator and the Arbitral Tribunal was constituted on 12.11.2006.
3.5. In the meanwhile, KMC also filed a Writ Petition (bearing W.P. No. 18269/2006) before the High Court of Andhra Pradesh seeking interdiction of the invocation of the Bank Guarantee. By an order dated 29.11.2006, that High Court restrained NHAI from encashing the aforesaid Bank Guarantee. NHAI appealed against the aforesaid order before the Division Bench of the High Court of Andhra Pradesh and the Court ordered KMC to keep the Bank Guarantee alive during the course of the arbitration proceedings.
3.6. Before the Arbitral Tribunal, KMC raised twenty-two claims aggregating to Rs.135,96,28,549/-. NHAI filed its Statement of Defence and also raised counter-claims.
3.7. By a letter dated 11.10.2013 addressed to the Arbitral Tribunal, both parties requested the Arbitral Tribunal to keep the arbitral proceedings in abeyance, to enable them to amicably resolve the disputes by Conciliation b
The court affirmed that arbitral awards are upheld unless blatant illegality is shown, emphasizing the tribunal's final authority under Section 34 of the Arbitration and Conciliation Act.
Patent illegality should be illegality which goes to the root of the matter. In other words, every error of law committed by the Arbitral Tribunal would not fall within the expression ‘patent illegal....
The court emphasized that arbitration awards must adhere strictly to contract terms regarding payment and interest, rejecting arbitrary reductions of entitlement.
The court held that the rejection of KMC's claims for escalation, additional payment, early completion bonus, and loss due to non-release of Performance Bank Guarantee was not illegal. However, the c....
The court upheld the learned Single Judge's ruling that claims not disclosed under the contract clauses and issues related to 'No Claim' certificates are non-recoverable, emphasizing the importance o....
The main legal point established is that an arbitral award must be based on relevant material and evidence, and claims for loss of profit must be substantiated with evidence of missed opportunities.
The inapplicability of the ground of patent illegality to international commercial arbitration and the importance of interpreting specific contractual clauses in determining the validity of claims an....
The entitlement to compensation for overheads incurred during the extended period of the agreement and the calculation of rates for extra items were central legal points established in the judgment.
The main legal point established in the judgment is the correct interpretation and application of contractual provisions in arbitration disputes.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.