SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
C. Hari Shankar, J.
Tantia Construction Limited - Appellant
Versus
Ircon International Ltd. - Respondent
O.M.P. (COMM) 593 of 2020 & I.A. 12328 of 2020
Decided On : 13-04-2021




The court held that the failure to adhere to the audi alteram partem principle and rectify errors under Section 33 without the appellant's hearing invalidated the supplementary arbitration award.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 33 - Arbitration award - Supplementary award reduced previously decided amounts without proper application of mind and failing to uphold principles of natural justice - Delay in application for correction under Section 33 cannot be condoned - Impugned award set aside due to violation of procedural fairness (Paras 11-21).

(B) Natural justice - Audi alteram partem principle must be adhered to; substantial decisions affecting parties require hearing before making changes to awards (Paras 16-19).

(C) Limitation period - 30-day limitation under Section 33(1) is strict and cannot be evaded unless mutually agreed by parties; mechanical condonation without cogent reasons is impermissible (Paras 12-15).

Facts of the case:
The appellant filed a Section 34 petition against a supplementary arbitration award reducing prior amounts awarded following claims resulting from an alleged wrongful termination of contract due to a force majeure event. The respondent's request for delay in filing the application under Section 33 was acknowledged but deemed unjustifiable.

Findings of Court:
The supplementary award was set aside as it contravened statutory limitations and natural justice norms.

Issues: Whether the delay in filing the Section 33 application could be condoned and if the supplementary award process adhered to natural justice.

Ratio Decidendi: The court clarified that the learned arbitrator failed to provide the appellant a chance to contest the respondent's application, rendering the supplementary award unsustainable in law.

Result: Petition allowed; supplementary award set aside.

JUDGMENT (Oral)

(Video-Conferencing)

1. This petition, under Section 34 of the Arbitration and Conciliation Act, 1996 ("the 1996 Act"), is directed against a supplementary award dated 20th August, 2020, passed by the learned arbitrator. By the supplementary award, the amounts awarded in favour of the petitioner in the original award dated 23rd January, 2020, against Claims No. 6 and 12, were reduced. The amount of Rs.1,90,86,595/-, awarded in respect of claim no. 6, was reduced to Rs.97,85,184/- and the amount of Rs.58,08,475/-, awarded in respect of claim no. 12, was reduced to Rs.54,01,882/-. Side by side, the learned arbitrator also modified the reasons for awarding the aforesaid amounts. The changes effected by the impugned supplementary award stand captured, in the impugned award itself, in a tabular form, thus:

"Claim no. 6 Claim for illegal encashment of performance bank guaranteeAmount claimed (Rs.)Amount awarded in Original award (Rs.)Award modified (Rs.)
1,90,86,5951,90,86,59597,85,184
Original reasons of awardModified reasons of award
As deliberated in above paras, the termination of the contract was wrongful, illegal and arbitrary due to the occurrence of earthquake in Nepal which also led to declaration of National Emergency, severely affected the citizens. Tender categorically stipulates that in the event of occurrence of a force majeure event, neither party shall be entitled to terminate contract in respect of non-performance or delay in performance. Hence claim amount of Rs.1,90,86,595/-, is reasonable and payable.As deliberated in above paras, the termination of the contract was wrongful, illegal and arbitrary due to the occurrence of earthquake in Nepal which also led to declaration of National Emergency, severely affected the citizens. Tender categorically stipulates that in the event of occurrence of a force majeure event, neither party shall be entitled to terminate contract in respect of non-performance or delay in performance.
As against claim amount of Rs.1,90,86,595/-, respondent has mentioned they have adjusted the recoveries other than mobilization advance in the final bill for Rs.93,01,410 in the encashed amount of PBB. Hence balance PBG amount of Rs.97,85,184 is reasonable and payable.
"Claim no.12 Claim for unbilled quantity of blanketing materials layedAmount claimed (Rs.)Amount awarded in Original award (Rs.)Award modified (Rs.)
66,90,00058,08,47554,01,882
Original reasons of awardModified reasons of award
As per 17th & final bill total quantity paid up to 16th running bill was 47485.880 cum of granular blanketing material but in the aforesaid 17th & final bill it has been reduced to 39411.264 cum. Since the 47485.880 cum is a measured and paid quantity, payment of balance quantity 8074.616 cum recovered from the final bill for amounting to amounting to Rs.58,08,475.00 to be refunded to claimant.As per 17th & final bill total quantity paid up to 16th running bill was 47485.880 cum of granular blanketing material but in the aforesaid 17th & final bill it has been reduced to 39411.264 cum. Since the 47485.880 cum is a measured and paid quantity, payment of balance quantity 8074.616 cum recovered from the final bill for amounting to amounting to Rs.54,01,882.00, after adjusting the rate quoted by the claimant, to be refunded to claimant.
Original concluding parasModified concluding paras
In conclusion, the respondent, IRCON INTERNATIONAL LIMITED shall pay to claimant, M/s Tantia Construction Limited. DD-30, 7th floor, Sector-1, Salt lake city Kolkata a sum of Rs.4,80,37,967.00 (Rs. four crores eighty lacs thirty seven thousand nine-hundred sixty seven only) in full and final settlement of all the claims/counter claims of both the parties arising out of dispute as referred vide IRCON International Limited, Saket's letter No. IRON/CO/ARBN/Tantai Con/JOG-Biratnagar/129/2601/74 dated 12.11.2015.In conclusion, the respondent, IRCON INTERNATIONAL LIMITED shall pay to claimant, M/s Tantia Construction Limited

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top