SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
Vasavi Power Services Pvt. Ltd. - Appellant
Versus
Bharat Heavy Electricals Ltd. - Respondent
Arb.P. 544 of 2021
Decided On : 16-07-2021




The court affirmed the necessity of arbitration per the Arbitration Agreement to resolve disputes, allowing the appointment of an Arbitrator despite opposition from the parties.

Headnote:(A) Arbitration & Conciliation Act, 1996 - Section 11 - Appointment of Arbitrator - Petition preferred for the appointment of an Arbitrator to adjudicate disputes arising from a contract executed on 26.11.2009 between the parties regarding construction projects - Respondent denied claims but acknowledged necessity for dispute resolution through arbitration. (Paras 1, 2, 5, 9)

(B) Jurisdiction - The court emphasized the importance of prompt resolution through arbitration as per the Arbitration Agreement, allowing the appointment of an Arbitrator despite disagreement from the Respondent. (Paras 7, 9)

Facts of the case:
The petitioner, a MSME, sought arbitration over disputes related to an agreement for work valued at USO15,500,000 for a power plant in Sudan, alleging delays caused by the respondent. (Paras 3, 4)

Findings of Court:
The court allowed the petition and appointed a sole Arbitrator to adjudicate the disputes while stating that issues remain open for decision as per law. (Paras 9, 12)

Issues: Whether the disputes between the parties could be adjudicated through the arbitration agreement contained in the contract and whether an Arbitrator should be appointed. (Paras 6, 7)

Ratio Decidendi: The court ruled that the appointment of an Arbitrator is necessary to resolve disputes fairly as per the earlier agreement, emphasizing the need for arbitration in commercial matters. (Paras 9)

Result: Petition allowed; Arbitrator appointed.

Table of Content
1. dispute initiation and contract details. (Para 1 , 2 , 3 , 4)
2. arguments regarding arbitration initiation. (Para 5 , 7 , 8)
3. appointment of arbitrator and procedural directives. (Para 9 , 10 , 11)
4. conclusion of the petition. (Para 12)

JUDGMENT

Suresh Kumar Kait, J. (Oral)

The hearing has been conducted through video conferencing.

1. The present petition is preferred by the petitioner under Section 11 of the Arbitration & Conciliation Act, 1996 seeking appointment of an Arbitrator in the present case for adjudicating the disputes between the parties.

2. The Petitioner is a MSME Company, who is said to have executed MEI (Mechanical, Electrical & Instrumentation) Erection Testing & Commissioning Projects for over 30 years across India, Middle East and Africa.

3. The crux of the case, as spelt out in the petition, is that on 26.11.2009, petitioner and respondent executed an Agreement for "erection, testing, commissioning, and trial operation of TG sets, ELECTRICAL, C & I and BOP packages for 4x125 MW Power Plant in Kosti, Sudan (Package-2/Contract Document No.646/2OO9)" and the total value of the work awarded was USO15,500,000 with the schedule commencement date as 24.11.2009 and the stipulated time period of completion was 21 months.

4. According to petitioner, it deployed/engaged all resources like Engineers, Supervisors, etc. and also procured Tools & Plants, Shuttering Material, etc. which was required to execute and complete the work within the scheduled time. However, despite petitioner's diligent efforts to execute the work on time, the respondent kept on delaying the same and the petitioner faced various hindrances, attributable to the respondent.

5. On the other hand, respondent has denied the averments made on behalf of the petitioner stating that petitioner had filed a petition under Section 9 of the Act [OMP (I) (COMM) 72/2021] and by virtue of order dated 10.03.2021, the claims made by petitioner stand fully settled and discharged.

6. Pertinently, petitioner on 09.04.2021, sent a Notice under Clause 33 of the Contract No. 646/2009 dated 26.11.2009 r/w Section 11 of the Arbitration & Conciliation Act, 1996 for appointment of a sole Arbitrator.

7. At the hearing, learned counsel for petitioner submitted that various disputes have arisen between the parties and these disputes can be settled in terms of Arbitration Agreement between the parties, as contained in Clause 33 of Section 11 of Arbitration & Conciliation Act, 1996.

8. Though the aforesaid submission of petitioner's counsel is disputed by counsel for respondent, however, he has not controverted that a quietus has to be given to the disputes between the parties by appointing an Arbitrator.

9. In view of the above, the present petition is allowed. Accordingly, Justice Pradeep Nandrajog, former Chief Justice of the High Court at Bombay (Mobile: 9818000130), is appointed as the Sole Arbitrator to adjudicate the disputes between the parties. All the issues raised by the parties shall remain open and shall be decided by the Arbitrator as per law.

10. The fee of the learned Arbitrator shall be governed by the Fourth Schedule of the Arbitration and Conciliation Act, 1996.

11. A copy of this order be sent to learned Arbitrator for information.

12. With aforesaid directions, the present petition is accordingly disposed of.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top