IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Delhi Tourism and Transportation Development Corporation - Appellant
Versus
Swadeshi Civil Infrastructure Pvt. Ltd. - Respondent
O.M.P. (T) (COMM.) 56 of 2021 and IA Nos. 7715 of 2021, 7716 of 2021, 7717 of 2021, 9049 of 2021 and 9050 of 2021
Decided On : 30-07-2021
JUDGMENT
[Hearing held through video conferencing]
Vibhu Bakhru, J. (ORAL)--Delhi Tourism and Transportation Development Corporation (DTTDC) (hereinafter `the petitioner') has filed the present petition under Section 14 (2) of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act'), inter alia, praying that the mandate of the learned Arbitrator, be terminated and further directions be issued for substitution of the learned Arbitrator by an independent and impartial Arbitrator.
2. The petitioner claims that the learned Arbitrator has displayed open bias in the conduct of arbitral proceedings and therefore, has rendered himself de facto and de jure unable to perform his functions as an Arbitrator.
3. The petitioner had awarded the Contract for construction of "Dilli Haat at Janakpuri, New Delhi (SH: - Civil, Water Supply, Sanitary Installation, Drainage, Development & Internal Electrical Installation Works etc.)" to the respondent. Certain disputes have arisen between the parties in respect of the said Contract. The respondent invoked the Arbitration Clause for adjudication of the said disputes. On 27.06.2017, the Chief Engineer of the petitioner appointed Sh. Om Prakash Bhatia, Former Additional Director General (Works Special), CPWD as the Sole Arbitrator.
4. The respondent challenged the appointment of Sh. Bhatia, by filing a petition under Section 14 and 15 of the A&C Act [OMP(T)(COMM) 58/2017 captioned M/s Swadeshi Civil Infrastructure Pvt. Ltd. v. Delhi Tourism & Transportation Development Corporation]. The said petition was disposed of by a consent order dated 21.02.2018 and Sh. A.K. Singhal, (Retired) Director General, CPWD was appointed as a Sole Arbitrator to adjudicate the disputes between the parties. This Court also clarified that the said appointment was subject to the learned Arbitrator making the necessary disclosure under Section 12 of the A&C Act and, not being ineligible under Section 12 (5) of the A&C Act.
5. On 07.03.2018, the learned Arbitrator issued notice to both the parties and directed the respondent (the claimant before the Arbitrator Tribunal) to file its Statement of Claim within a period of thirty days from receipt of the notice. It is not disputed that he furnished his consent and made the necessary disclosure, which did not indicate any justifiable grounds to doubt his independence or impartiality.
6. The petitioner contends that the attitude of the respondent towards the petitioner is hostile and it has adopted unfair tactics to influence the Arbitrator. It also claims that the respondent has advanced arguments on the basis of documents, which were not taken on record and copies of the same were not supplied to the petitioner.
7. On 18.07.2018, the parties jointly agreed to extend the mandate of the Arbitral Tribunal for a period of six months from 06.03.2019 to 06.09.2019.
8. The petitioner submitted its Statement of Defence on 30.08.2018. However, at the material time, the petitioner did not file any counter claims.
9. The respondent submitted its rejoinder. It is the petitioner's claim that in its rejoinder, the respondent sought to modify its claims and also introduced new documents for altering the claims as initially made. The petitioner has contested the same and submitted a sur- rejoinder to the rejoinder filed by the respondent.
10. The petitioner contends that during the course of hearings held before the Arbitral Tribunal, the counsel for the respondent had also sought to advance arguments, which were not supported by pleadings. It is stated that at the hearing held on 08.07.2019, learned counsel for the petitioner objected to the same and in view of the objections, learned counsel for the respondent stated that the respondent would file an application under Section 23(3) of the A&C Act for amending its Statement of Claims to supplement its claims.
11. It is contended on behalf of the petitioner that by an application under Section 23(3) of the A&C Ac
Pre-award challenges to an arbitrator's mandate based on perceived bias are impermissible, and such concerns must be raised post-award under Section 34 of the Arbitration and Conciliation Act.
Arbitration - Time limit for arbitral award - A petition under Section 29A of Act cannot be permitted to be used by one of parties to seek substitution of an arbitrator merely on basis of its unsubst....
The challenge for the appointment of Arbitrator under Section 13 of the Act can only be made along with the final award under Section 34.
The main legal point established in the judgment is that the grounds for termination of an arbitrator's mandate must satisfy the circumstances laid down under the Act and the precedents set by the Ho....
The court established that an arbitrator appointed by an ineligible individual cannot act, and waivers of objections regarding ineligibility must be expressed in writing, not inferred by conduct.
Point of Law : It is not open for the petitioner to challenge the learned Arbitrator on the ground that there are justifiable doubts as to his independence and impartiality in terms of the Guidelines....
The appointment of an arbitrator must comply with Section 12(5) of the Arbitration & Conciliation Act, ensuring independence and impartiality, regardless of when the arbitration proceedings were init....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.