IN THE HIGH COURT OF JUDICATURE AT MADRAS
KRISHNAN RAMASAMY, J.
Project Director, Tamil Nadu Road Sector Project II, (For and behalf of the Governor of State of Tamil Nadu) Highways Department, Government of Tamil Nadu – Appellant
Versus
M/s. SPK & Co-KMC (JV), Ramanathapuram – Respondent
Arb.O.P.(Com.Div.)No. 201 of 2023
Decided On : 27-06-2023
Arbitration - Termination of Arbitrator's Mandate - Sections 14 and 15 of the Arbitration and Conciliation Act, 1996 - Schedule V - Categories 26 and 34 - The court held that the challenge for the appointment of Arbitrator under Section 13 of the Act can only be made along with the final award under Section 34. The petition to set aside the order passed by the learned Arbitrators under Sections 14 and 15 of the Act is not maintainable at this stage.
Fact of the Case:
The petitioner filed an Arbitration Original Petition to terminate the mandate of the Arbitrators, alleging justifiable doubts with regard to their independence and impartiality. The respondent argued that the petition was not maintainable as the challenge under Section 13 of the Act can only be made along with the final award under Section 34.
Finding of the Court:
The court found that the present original petition was not maintainable and dismissed it. The court refrained from expressing an opinion on the merits of the challenge.
Issues: The main issue was whether the petition to set aside the order passed by the learned Arbitrators under Sections 14 and 15 of the Act was maintainable at this stage.
Ratio Decidendi: The court held that the challenge for the appointment of Arbitrator under Section 13 of the Act can only be made along with the final award under Section 34. Therefore, the present original petition was not maintainable.
Final Decision: The Arbitration Original Petition was dismissed.
JUDGMENT
(Prayer: Arbitration Original Petition filed under Sections 14 and 15 read with Schedule V of the Arbitration and Conciliation Act, 1996 to terminate the mandate of the Hon''ble Mr. Justice G.M.Akbar Ali and Hon''ble Ms. Justice K.B.K.Vasuki by setting aside the order passed in 2/2022 dated 03.02.2023 and to consequently appoint substitute Arbitrators to proceed further in the Arbitration and to fix the fees for the newly appointed Arbitrators.)
This Arbitration Original Petition has been filed under Sections 14 and 15 read with Schedule V of the Arbitration and Conciliation Act, 1996 (hereinafter called as “the Act”) to terminate the mandate of the Hon''ble Mr. Justice G.M.Akbar Ali and Hon''ble Ms. Justice K.B.K.Vasuki by setting aside the order passed in 2/2022 dated 03.02.2023.
2. Mr.Ramanlal, learned Additional Advocate General appearing for the petitioner would submit that this petition has been filed to terminate the Mandate of the learned Arbitrators as they have become de jure unable to perform their functions by virtue of the fact that they fall within the categories 26 and 34 of Schedule V of the Act. Further, he would submit that in the present case, there are two learned Arbitrators namely Hon''ble Ms. Justice K.B.K.Vasuki and Hon''ble Mr. Justice G.M.Akbar Ali. Both the learned Arbitrators are having office at the same premises and also having professional relationship and therefore, they are de jure unable to perform their function as Arbitrators. In this regard, an application was also filed before the learned Arbitrators and the same was rejected vide order dated 03.02.2023. Aggrieved over the same, the present original petition has been filed to set aside the aforesaid order passed by the learned Arbitrators dated 03.02.2023.
3. The learned Additional Advocate General appearing for the petitioner would refer to Category 26 to Schedule V of the Act, which reads as follows:
“26. The Arbitrator was within the past three years a partner of, or otherwise affiliated with, another arbitrator or any of the counsel in the same Arbitration.”
4. Further, at the time of arguments, he would refer to Category 34 to Schedule V of the Act, which talks about the affiliate of one of the parties. He would also submit that though these issues were raised before the learned Arbitrators, they had arrived at the conclusion that they are all independent professionals and they are merely shared their office. Apart from sharing office, they did not have any professional relationship with each other and they are also not connected with any of the firm jointly. By referring the said conclusion of the learned Arbitrators, the learned Additional Advocate General would submit that the observation of the learned Arbitrators is not correct and in fact, since they are having office in the same premises and having professional relationship, they are not supposed to act as Arbitrators.
5. Further, he would fairly submit that both the learned Arbitrators were appointed in some other cases and they had also decided the matters. However, the professional relationship between the learned Arbitrators came to be known recently, due to which the petitioners had filed an application before the learned Arbitrators and the same was rejected. Further they have also not disclosed their interest in terms of Section 12(1)(b) read with Schedule VI of the Act. Therefore, he would submit that there is a justifiable doubt with regard to the independence and impartiality of the learned Arbitrators. Hence, he prays that the said appointment has to be terminated in terms of Sections 14 and 15 of the Act.
6. In support of his submission, he had also referred to a judgement of the Hon''ble Apex Court in Voestalpine Schienen GMBH vs. Delhi Metro Rail Corporation Limited reported in (2017) 4 SCC 665 and prays for setting aside the order passed by the learned Arbitrators and also to terminate the Mandate of the learned Arbitrators.
7. Per contra, Mr.Vi
The challenge for the appointment of Arbitrator under Section 13 of the Act can only be made along with the final award under Section 34.
The main legal point established in the judgment is that the grounds for termination of an arbitrator's mandate must satisfy the circumstances laid down under the Act and the precedents set by the Ho....
Arbitration - Time limit for arbitral award - A petition under Section 29A of Act cannot be permitted to be used by one of parties to seek substitution of an arbitrator merely on basis of its unsubst....
An arbitrator's mandate can be terminated when they fail to act without undue delay; new appointments must ensure impartiality as per updated legal standards.
The appointment of an arbitrator must comply with Section 12(5) of the Arbitration & Conciliation Act, ensuring independence and impartiality, regardless of when the arbitration proceedings were init....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.