SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
C. Hari Shankar, J.
Larsen and Toubro Limited - Appellant
Versus
HLL Lifecare Limited - Respondent
O.M.P. (T) (COMM.) 59 of 2021 & I.A. 8324 of 2021
Decided On : 20-09-2021




The necessity for an express written waiver to validate an arbitrator's appointment under Section 12(5) of the Arbitration and Conciliation Act, 1996.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 12(5) - The validity of the appointment of an arbitrator - The petition arose from a contract between parties with disputes unresolved through pre-arbitral mechanisms - The respondent's unilateral appointment of a sole arbitrator was contested for being contrary to legal provisions. (Paras 3, 6-12)

(B) Waiver of rights and disputes - The court highlighted that any waiver of the ineligibility of an arbitrator under Section 12(5) must be an express agreement in writing, not implied by conduct or actions. (Paras 12-14)

(C) Appellate Jurisdiction - The court emphasized that proceedings must align with statutory mandates, rendering the prior arbitrator incapable. (Paras 11, 12)

Facts of the case:
The arbitration arose out of a 2010 contractual agreement for addressing disputes via arbitration, with claims of improper arbitrator appointment noted.

Findings of Court:
The learned arbitrator had been rendered de jure incapable due to statutory provisions.

Issues: The primary issues considered were the validity of the arbitrator's appointment under Section 12(5) and whether a waiver of such ineligibility existed.

Ratio Decidendi: The court established that an express written waiver is necessary to override the default incapacity of an arbitrator under Section 12(5) of the Act.

Result: The petition was allowed, terminating the current arbitrator's mandate, with a request for a new arbitrator.

Table of Content
1. arbitration clause in contract agreement. (Para 1)
2. petitioner requests for nominee arbitrator. (Para 2 , 3)
3. petitioner claims appointment violates law. (Para 4)
4. respondent invokes legal provision to oppose petition. (Para 5)
5. court analyzes the applicability of section 12(5). (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13)
6. court orders new arbitrator and terminates previous mandate. (Para 14 , 15 , 16 , 17 , 18 , 19)

ORDER (Oral)

O.M.P. (T) (COMM.) 59/2021

1. The arbitral proceedings, forming subject matter of the present petition, emanate out of a contract agreement dated 25th February, 2010, between the petitioner and the respondent. Clause 21 of the General Conditions of Contract (GCC), forming part of the said agreement, provided for arbitration as the mode of resolution of disputes and read thus:

    "21. Arbitration Settlement of Disputes & arbitration

    Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, design, drawings and instructions herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:

    (i) If the contractor considers that he is entitled to any extra payment or compensation in respect of the works over and above the amounts admitted as payable by HLL or in case the contractor wants to dispute the validity of any deductions or recoveries made or proposed to be made from the contract, the contractor shall forthwith give notice in writing of his claim, in this behalf to the Engineer-in-Charge within 30 days from the date of disallowance thereof for which the contractor claims such additional payment or compensation or disputes the validity of any deduction or recovery. The said notice shall give full particulars of the claim, grounds on which it is based and detailed calculations of the amount claimed and the contractor shall not be entitled to raise any claim nor shall HLL be in any way liable in respect of any claim by the contractor unless notice of such claim shall have been given by the contractor to the Engineer-in-Charge in the manner and within the time as aforesaid. The contractor shall be deemed to have waived and extinguished all his rights in respect of any claims not notified to the Engineer-in-Charge in writing in the manner and within the time aforesaid.

    (ii) The Engineer7-in-Charge shall give his decision in writing on the claims notified by the contractor within 30 days of the receipt of the notice thereof. If the contractor is not satisfied with the decision of the Engineer-in-Charge, the contractor may within 15 days of the receipt of the decision of the Engineer-in-Charge submit his claims to the conciliating authority named in Schedule 'F' for conciliation along with all details and copies of correspondence exchanged between him and the Engineer-in-Charge.

    (iii) If the conciliation proceedings are terminated without settlement of the disputes, the contractor shall, within a period of 30 days of termination thereof shall give a notice, in the form prescribed by HLL, to the Chairman & Managing Director, HLL Lifecare Limited for appointment of an arbitrator to adjudicate the notified claims failing which the claims of the contractor shall be deemed to have been considered absolutely barred and waived.

    (iv) Except where the decisions have become final, binding and conclusive in terms of the contract, all disputes arising out of the notified claims of the contractor as aforesaid and all claims of HLL shall be referred for adjudica

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top