SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Totem-Premco (JV) - Appellant
Versus
Rail Vikas Nigam Limited - Respondent
O.M.P. (COMM) 130 of 2021
Decided On : 12-10-2021




Arbitral awards are not subject to interference unless they exhibit patent illegality; the interpretation of contractual obligations falls within the jurisdiction of the Arbitral Tribunal.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Disputes arising from a construction contract - The Arbitral Tribunal awarded Rs.34,43,708 with interest at 10%, rejecting claims related to performance bank guarantees and mobilization advances, affirming the legality of the agreement termination. (Paras 4, 36, 63)

(B) Legal effect of an Arbitral Award - Grounds for setting aside an arbitral award under Section 34 must be established, and the courts should not interfere with the tribunal's factual determinations unless they reflect patent illegality. (Paras 45, 63)

Facts of the case:
The petitioner, a joint venture executing a railway project, disputed the enforcement of performance bank guarantees and termination of the contract due to alleged site access issues leading to abandonment of works. The Tribunal found the contract termination lawful based on the petitioner’s failure to adhere to a joint work programme.

Findings of Court:
The Tribunal upheld the validity of termination and limited refunds for mobilization advances while rejecting most petitioner claims.

Issues: The primary issue was whether the Tribunal's decision to uphold the termination of the contract and reject certain claims was legally tenable.

Ratio Decidendi: The court concluded that the Tribunal's findings regarding the abandonment of the project by the petitioner, as well as the encashment of bank guarantees being consistent with the contractual terms, warranted no judicial intervention.

Result: Petition dismissed.

Table of Content
1. arbitral award issued on prior proceedings. (Para 1 , 2 , 3)
2. contract establishment and bid acceptance. (Para 4 , 5 , 6)
3. contractual obligations and progress issues. (Para 7 , 8 , 9 , 10 , 11 , 12)
4. termination notice and joint meetings. (Para 20 , 21 , 22)
5. arbitrator's conclusion and dissent. (Para 36 , 37 , 38)
6. parties' arguments on tribunal's findings. (Para 39 , 40 , 41 , 42 , 43)
7. court's observations on contractual interpretation. (Para 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55)
8. no ground found for setting aside award. (Para 58 , 59 , 60 , 63)

JUDGMENT

Vibhu Bakhru, J. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act') impugning an Arbitral Award dated 03.06.2020 (hereinafter `the impugned award') delivered by the Arbitral Tribunal comprising of three Arbitrators, Mr. M. Ravindra, Major General K.T. Gajria (Retired) and Justice (Retired) Jaspal Singh, as the Presiding Arbitrator. Whilst Justice (Retired) Jaspal Singh and Mr. M. Ravindra delivered the impugned award by majority, Major General K.T. Gajria (Retired) entered a dissenting opinion on 03.06.2020.

2. The impugned award has been rendered in the context of disputes that have arisen between the parties in relation to the Contract Agreement dated 13.11.2010.

3. By the impugned award, the Arbitral Tribunal entered an award for a sum of Rs.34,43,708. The Arbitral Tribunal further allowed interest at the rate of 10% per annum on the said amount calculated from 31.12.2015 till realisation. The Arbitral Tribunal did not accept the petitioner's claim for refund of the amount recovered by the respondent by invoking the performance bank guarantee submitted by the petitioner.

Factual Context

4. On 30.06.2010, Rail Vikas Nigam Limited (hereinafter `the respondent') issued Notice Inviting Tenders (NIT) for the "Construction of New Line between Dankuni-Furfura Sharif via Jangalpara (20 KM) in Howrah Division of Eastern Railway in the State of West Bengal, India" (hereinafter `the Project'), on the terms and conditions stipulated therein.

5. The petitioner entered is a Joint Venture (JV) between Totem Infrastructure Limited and M/s Premco Rail Engineers Limited. The petitioner was formed for the purpose of submitting a bid pursuant to the aforesaid NIT.

6. Pursuant to the said NIT, the petitioner submitted its bid for executing the project works on 17.08.2010. The petitioner's bid was accepted by the respondent and a contract for implementation of the Project for an amount of Rs.89,70,13,691.61 was awarded to the petitioner by the Notification of Award dated 20.09.2010 (hereinafter `the NoA')

7. In terms of the said NoA, the petitioner was called upon to furnish a Performance Security in accordance with Clause 41.1 of Instruction to Bidders, for an amount equivalent to 10% of the agreed contract amount (that is, for an amount of Rs.8,97,01,369.16) and further, a Bank Guarantee in terms of Clause 35.5 of Instruction to Bidders, for an amount of amount of Rs.19,37,779.20. The same were required to be furnished within twenty-eight days of the receipt of the said NoA. And, the petitioner furnished the Bank Guarantees as required.

8. Thereafter, on 13.11.2010, the parties entered into an agreement (hereinafter `the Agreement'), whereby the petitioner agreed to complete the Project within a period of twenty-four months from the date of commencement of work. The defect liability period was agreed as six months after the completion of the works

9. By a communication dated 30.11.2010, the petitioner informed the respondent about the various hindrances existing between "Take off Point to Ch:1391 from CSB of Dankuni-Region". The petitioner also requested for a schedule for handing over of land as well as the drawings for minor bridges, major bridges and station buildings. The petitioner also stated in the letter that even after the lapse of thirty

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top