IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Totem-Premco (JV) - Appellant
Versus
Rail Vikas Nigam Limited - Respondent
O.M.P. (COMM) 130 of 2021
Decided On : 12-10-2021
| Table of Content |
|---|
| 1. arbitral award issued on prior proceedings. (Para 1 , 2 , 3) |
| 2. contract establishment and bid acceptance. (Para 4 , 5 , 6) |
| 3. contractual obligations and progress issues. (Para 7 , 8 , 9 , 10 , 11 , 12) |
| 4. termination notice and joint meetings. (Para 20 , 21 , 22) |
| 5. arbitrator's conclusion and dissent. (Para 36 , 37 , 38) |
| 6. parties' arguments on tribunal's findings. (Para 39 , 40 , 41 , 42 , 43) |
| 7. court's observations on contractual interpretation. (Para 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55) |
| 8. no ground found for setting aside award. (Para 58 , 59 , 60 , 63) |
JUDGMENT
Vibhu Bakhru, J. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act') impugning an Arbitral Award dated 03.06.2020 (hereinafter `the impugned award') delivered by the Arbitral Tribunal comprising of three Arbitrators, Mr. M. Ravindra, Major General K.T. Gajria (Retired) and Justice (Retired) Jaspal Singh, as the Presiding Arbitrator. Whilst Justice (Retired) Jaspal Singh and Mr. M. Ravindra delivered the impugned award by majority, Major General K.T. Gajria (Retired) entered a dissenting opinion on 03.06.2020.
2. The impugned award has been rendered in the context of disputes that have arisen between the parties in relation to the Contract Agreement dated 13.11.2010.
3. By the impugned award, the Arbitral Tribunal entered an award for a sum of Rs.34,43,708. The Arbitral Tribunal further allowed interest at the rate of 10% per annum on the said amount calculated from 31.12.2015 till realisation. The Arbitral Tribunal did not accept the petitioner's claim for refund of the amount recovered by the respondent by invoking the performance bank guarantee submitted by the petitioner.
Factual Context
4. On 30.06.2010, Rail Vikas Nigam Limited (hereinafter `the respondent') issued Notice Inviting Tenders (NIT) for the "Construction of New Line between Dankuni-Furfura Sharif via Jangalpara (20 KM) in Howrah Division of Eastern Railway in the State of West Bengal, India" (hereinafter `the Project'), on the terms and conditions stipulated therein.
5. The petitioner entered is a Joint Venture (JV) between Totem Infrastructure Limited and M/s Premco Rail Engineers Limited. The petitioner was formed for the purpose of submitting a bid pursuant to the aforesaid NIT.
6. Pursuant to the said NIT, the petitioner submitted its bid for executing the project works on 17.08.2010. The petitioner's bid was accepted by the respondent and a contract for implementation of the Project for an amount of Rs.89,70,13,691.61 was awarded to the petitioner by the Notification of Award dated 20.09.2010 (hereinafter `the NoA')
7. In terms of the said NoA, the petitioner was called upon to furnish a Performance Security in accordance with Clause 41.1 of Instruction to Bidders, for an amount equivalent to 10% of the agreed contract amount (that is, for an amount of Rs.8,97,01,369.16) and further, a Bank Guarantee in terms of Clause 35.5 of Instruction to Bidders, for an amount of amount of Rs.19,37,779.20. The same were required to be furnished within twenty-eight days of the receipt of the said NoA. And, the petitioner furnished the Bank Guarantees as required.
8. Thereafter, on 13.11.2010, the parties entered into an agreement (hereinafter `the Agreement'), whereby the petitioner agreed to complete the Project within a period of twenty-four months from the date of commencement of work. The defect liability period was agreed as six months after the completion of the works
9. By a communication dated 30.11.2010, the petitioner informed the respondent about the various hindrances existing between "Take off Point to Ch:1391 from CSB of Dankuni-Region". The petitioner also requested for a schedule for handing over of land as well as the drawings for minor bridges, major bridges and station buildings. The petitioner also stated in the letter that even after the lapse of thirty
Point of Law : Arbitral Tribunal had erred in concluding that the petitioner had abandoned the works, is also unpersuasive. The finding that the petitioner had abandoned the works is a finding of fac....
The encashment of a performance bank guarantee does not require proof of loss, but must comply with the contract's terms; failure to evaluate these terms constitutes patent illegality.
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Termination of a contractual agreement during a lock-in period is invalid unless justified under specific contractual provisions, emphasizing the need to adhere to agreed terms for contract terminati....
The main legal point established in the judgment is that the decision of the arbitral Tribunal is entitled to substantial discretion in awarding interest, and the court does not sit as the first appe....
The court reinforced that unconditional bank guarantees cannot be restrained unless egregious fraud or irretrievable injustice is established, which was not proven by the petitioner.
The arbitral tribunal's decision to deny claims for damages due to lack of supporting evidence is valid under Section 34 of the Arbitration and Conciliation Act, emphasizing minimal judicial interfer....
The court affirmed that a performance security cannot be withheld post-acknowledgment of contract performance, and interim relief must balance equities in arbitration under Section 17 of the Act.
Statutory limitation under Section 34 of the Arbitration Act is strict and cannot be relaxed without sufficient justification; defective petitions lead to being treated as non-est.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.