SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
Envirad Projects Pvt. Ltd. - Appellant
Versus
NTPC Ltd. - Respondent
Arb.P. 27 of 2022
Decided On : 18-01-2022




Unilateral appointment of an Arbitrator by one party is void under the Arbitration and Conciliation Act, reinforcing the need for impartial adjudication by the court.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Appointment of Arbitrator - Petition filed seeking appointment of sole Arbitrator for disputes between the parties after respondent unilaterally deducted amounts despite delays not attributable to petitioner - Court emphasized that no single party can unilaterally appoint an Arbitrator as it contradicts the principles of unbiased adjudication and is violative of Section 12(5) of the Act, directing the Court to appoint the Arbitrator. (Paras 8, 9, 10, 12)

Facts of the case:
The petitioner, a construction company, sought appointment of an Arbitrator to resolve payments and delay disputes arising from an awarded project, where a substantial amount was deducted by the respondent unjustly.

Findings of Court:
Court allowed the petition, emphasizing the need for impartiality in arbitration, appointing a retired judge as sole Arbitrator to adjudicate disputes.

Issues: Whether the clause allowing one party to unilaterally appoint an Arbitrator is enforceable under the Arbitration and Conciliation Act.

Ratio Decidendi: The court ruled that a clause allowing unilateral appointment by one party violates the principle of impartiality in dispute resolution as established in prior judgments, requiring Court intervention for Arbitrator appointment.

Result: Petition allowed. Mr. Justice S.K. Katriar appointed as sole Arbitrator.

Table of Content
1. factual background of the parties and contract. (Para 2 , 3 , 4 , 5 , 6)
2. contentions regarding arbitration appointment. (Para 7)
3. legal principles governing arbitrator appointment. (Para 8 , 9)
4. appointment of arbitrator and conclusion. (Para 10 , 13)
5. fee structure for the adjudicator. (Para 11 , 12)

JUDGMENT (Oral)

1. The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of sole Arbitrator to adjudicate the disputes inter-se the parties.

2. As per the averments made in the present petition, petitioner is a company registered under the Companies Act, 1956 and is engaged in the business of undertaking civil construction projects. Respondent is also a company registered under the Companies Act, 1956 and is working as a Central Public Sector Undertaking to implement power projects in the country.

3. It is further averred that the respondent-company invited the bid/tender for the subject package, namely, "3rd Raising of Dyke of Ash Pond `A' & `B' at NTPC-Tanda Project" on 05.08.2014 and after final bid, the aforesaid work was awarded to the petitioner vide its Letter of Award in form of Purchase Order dated 07.01.2015 amounting to work value of about Rs.27.50 crores having overall completion period of 20 months wherein the works of Dyke `A' was to be executed within 11 months starting from 10.01.2015 to 09.12.2015, and thereafter, the works of Dyke `B' within 9 months from 10.12.2015 to 09.09.2016. Subsequently, parties entered into a Contract Agreement dated 15.01.2015.

4. It is further averred that though the petitioner mobilised the machineries and manpower to execute the awarded works from day one, yet due to many reasons of delay, work of Dyke `A' and divide bund was handed over to respondent on 09.03.2016. Though the respondent was well aware of the reasons of delay which were not in control of petitioner, respondent deducted huge amount of about Rs.67.51 lacs towards the Liquidated Damages, holding amount from the due payments of running account bills of the petitioner which were raised for the works of Dyke `A' and divide bunds and the same was in complete violation and de hors to terms and conditions of the said Contract Agreement.

5. Learned counsel for petitioner submits that for commencement of Dyke `B' works, the respondent failed to handover the required working fronts for a period of 57 days and the same were partially made available on 05.05.2016. Thus, a justified revised time schedule to give effect to envisaged original 9 months for completing Dyke `B' works starting from 05.05.2016 was ought to be fairly extended up to 04.02.2017 by the respondent, yet the respondent issued unfair and unjust time extension stating that "completion period provisionally extended up to 04.02.2017 without prejudice to levy LD". Thereafter, for the reasons/delays attributable to the respondent six extensions of time for completion of said awarded works of the Contract were issued by the respondent, coupled with unfair deduction of 7.5 % amount in name of "LD Hold amount" from the RA bills raised for the progressive executed works for Dyke `B'. The defect liability period of 12 months for such executed works has also ended on 31.10.2019. However, the respondent has not paid the outstanding due payments of Rs.1,65,44,796/- till date to the petitioner and rather it imposed LD amount of Rs.82,44,435/- in May, 2021. Thereafter, disputes arose between the parties.

6. Petitioner served a notice dated 27.12.2021 upon respondent, seeking appointment of Arbitrator as per terms and provisions of Clause No.56 of GCC and the CMD and other senior officials of the respondent's company have received the said `Notice of Arbitration' on 31.12.2021 as per track consignment/delivery report of India Post websites. Hence, the present petition has been filed.

7. During the course of hearing, learned counsel appearing on behalf of respondent has disput

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top