SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
MBL Infrastructures Limited - Appellant
Versus
Pradeep Colonisers and Suppliers Pvt. Ltd. - Respondent
Arb.P. 984 of 2021
Decided On : 01-02-2022




The court directed the appointment of a sole arbitrator under the Arbitration and Conciliation Act, 1996 to resolve contract disputes, affirming the arbitrability of the issues.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Appointment of sole Arbitrator - Petitioner filed a petition for appointment of an arbitrator to resolve disputes arising from a work contract for restoration work awarded by the Government of Bihar - Petitioner claimed delays and poor performance by the respondent led to financial loss and contract termination - Respondent disputed claims but agreed disputes are arbitrable. (Paras 1-6)

(B) Arbitrator's appointment - Court appointed a retired justice as sole Arbitrator, stipulating arbitration to be conducted under the auspices of Delhi International Arbitration Centre, ensuring compliance with relevant Regulations. (Paras 7-9)

(C) Dispute resolution - Agreement requires disputes to be adjudicated by arbitration as per contract terms, with notice to respondent regarding proposed arbitrators ignored. (Paras 5 and 6)

Findings of Court:
The petition to appoint an Arbitrator is allowed.

Result: Petition allowed.

Table of Content
1. petition filed under section 11(6) of arbitration act. (Para 1 , 2)
2. details of the work order and compliance issues. (Para 3 , 4 , 5)
3. disputed claims and agreement on arbitrability. (Para 6)
4. appointment of sole arbitrator and conduct of arbitration. (Para 7 , 8 , 9)
5. disposition of petition and order for action. (Para 10 , 11)

JUDGMENT (Oral)

The hearing has been conducted through video conferencing.

1. The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of sole Arbitrator to adjudicate the disputes with respondent.

2. Petitioner-company, registered under the Companies Act, 1956, was awarded the work of restoration of Narayanpur Sub Distributary and Nawada Sub Distributary under Restoration Work of Western Gandak Canal System, Bihar (Saran Main Canal and its distribution system) (New Major ERN) from the Government of Bihar and a contract was executed between the respondent and the Executive Engineer Saran Canal Division, Gandak Project Marhowrah, Government of Bihar. Subsequently, petitioner executed a Work Order No.02/101/5000/02035-I/2015/335 dated 25.08.2015 in favour of the respondent at Delhi as a "PRW" (Price Rate Worker) for the project of "Part Work of Restoration of Narayanpur Sub Distributary and Nawada Sub Distributary on piece rate basis for estimated value of Rs.48,95,98,859/- inclusive of taxes. Time for completion of the said contract was 18 months as per clause 21 of the work order from the date of commencement.

3. According to petitioner, respondent was paid mobilization advance of Rs.75 lakhs against furnishing of a corporate guarantee in favour of the petitioner and respondent had to execute the said work as per the specifications and stipulations of the work order. Respondent also was required to diligently adhere to the time prescribed and maintain the quality in the execution of the work order as specified in the work order.

4. Petitioner claims that constant delay on the part of the respondent in complying with the said work order, resulted in huge financial loss as well as loss of reputation and foreclosure of the contract of M/s MBL Infrastructures Ltd with Saran Canal Division, Gandak Project Morhowrah Govt. of Bihar. Further, respondent's poor and unsatisfactory performance in execution of the said work order led to forfeiture of performance guarantee. Thereby, petitioner was left with no option but to terminate the contract of the respondent vide letter dated 16.09.2017.

5. During the course of hearing, learned counsel for petitioner submitted that the respondent was provided with valuable plant and machinery for work at site which was to be returned back to the petitioner. However, after termination of the contract, without any information, the respondent started removing the plant and machinery illegally without any permission or consent of the Petitioner. Intention of Respondent was to take possession of the same, unauthorizedly for which a complaint was lodged by the petitioner in the Amnor Police Station, Saran in order to take preventive and penal action against the respondent. Since disputes arose between the parties and the same have to be adjudicated by arbitration in terms of clause 24 of the contract signed between the parties, the petitioner served a notice dated 25.08.2021 on the respondent and proposed a panel of arbitrators and asked the respondent to choose any one arbitrator. However, respondent vide letter dated 22.09.2021 refused to consent to any of the three names of arbitrators suggested by the petitioner and so, petitioner was left with no option but to approach this Court for appointment of a sole arbitrator. Hence, the present petition has been filed.

6. Learned counsel appearing on behalf of respondent has disputed the claims raised in the present petition, however, fairly agreed that the disputes are arbitrable. Further, learned counsel has prayed that an independent

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top