IN THE HIGH COURT OF DELHI
Chandra Dhari Singh, J.
BBR (India) Private Limited - Appellant
Versus
ATS Dream Zone Private Limited - Respondent
Arb.P. 1249 of 2022
Decided On : 21-12-2022
| Table of Content |
|---|
| 1. appointment of sole arbitrator for dispute resolution (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9) |
| 2. opposition to claims but acceptance of arbitration (Para 10) |
| 3. referral of disputes to arbitration (Para 11) |
| 4. conclusion and order on arbitration appointment (Para 12 , 13) |
ORDER
Chandra Dhari Singh, J. (Oral)
I.A. 18553/2022 (Exemption)
Exemptions allowed subject to just exceptions.
The applications stand disposed of.
ARB.P. 1249/2022
1. The present petition has been filed on behalf of the petitioner seeking the appointment of a Sole Arbitrator under the provision of Section 11 of the Arbitration and Conciliation Act, 1996 qua the dispute arising out of the Standard Terms and Conditions of Contract and Work Order.
2. Learned counsel for the petitioner submitted that the petitioner is a Civil Engineering Contractor working in and around National Capital Territory of Delhi on a wide range of civil engineering projects, from conception to completion. The respondent is an entity inside the ATS Group, of which it is a subsidiary.
3. It is submitted on behalf of the petitioner the respondent's primary business activity consists of building residential properties in the National Capital Territory of Delhi. The respondent hired the Petitioner to carry out the tasks outlined in the contract.
4. Learned counsel for the petitioner further submitted that respondent contracted Petitioner for "Post Tensioning Work" at their Project named "ATS Bouquet, Sector-132, Noida, U.P." via Letter of Intent/Award dated 22nd August, 2018 and 28th June, 2019.
5. It is submitted that respondent thereafter, issued a Work Order dated 22nd August, 2018 in favour of petitioner, outlining the provisions of the contract, including the scope of work, contract price, start and end dates, and general terms and conditions.
6. It is submitted by the learned counsel appearing for the petitioner that the petitioner was responsible for finishing the job in issue that was given to them by the work order. With the work order, the petitioner expressed concern regarding the ongoing and periodic Bill(s). After making the appropriate adjustments for the amount that was received in payment of the bill or bills that were incurred due to the Project, it was discovered that the petitioner is still owed a total amount that is due, payable, and overdue in the amount of Rs.64,77,340.
7. It is submitted that the Petitioner made numerous statements and requests to the respondent in an effort to get the aforementioned debts paid off. The respondent neglected to pay and present the dues of the petitioner despite absence of any objection, complaint, or grievance.
8. It is submitted that the Work Order provides for the dispute resolution clause whereby the disputes between the parties shall be resolved by binding arbitration in accordance with Clause 1.18. It is further submitted that the respondent's director must select and appoint the sole arbitrator in order to arbitrate the disputes arising between the parties.
9. It is further submitted that in consequence thereto, the petitioner was forced and compelled to issue a formal Notice on 14th March, 2020 demanding the payment of their dues or, as an alternative, constitution of an Arbitral Tribunal or Sole Arbitrator.
10. Learned counsel on behalf of the respondent vehemently opposed the averments made by learned counsel for the petitioner, however it is accepted that dispute in question are arbitral in nature. It is also submitted that there is no objection if the instant dispute is referred by the Court to a sole arbitrator.
11. As agreed on behalf of the parties, it is evident that the parties intend the Court to refer the disputes to arbitration, by appointing a sole arbitrator. In view of the request made by the parties, to resolve the dispute, the said disputes and differences arising between the parties are referred to arbitration, by appointing an arbitral tribunal. Hence, the following Order
The court affirmed that the disputes between the parties were arbitral in nature and appointed a sole arbitrator under the Arbitration and Conciliation Act, 1996.
The court appointed a sole arbitrator to resolve contractual disputes under the Arbitration and Conciliation Act, 1996, affirming the parties' mutual agreement for arbitration.
No single party can be permitted to unilaterally appoint the Arbitrator, as it would defeat the purpose of unbiased adjudication of dispute between parties.
Unilateral appointment of an arbitrator is impermissible; parties must appoint an arbitrator jointly or seek court appointment to ensure unbiased dispute resolution.
The court's decision emphasized the arbitrability of disputes and the appointment of a sole arbitrator under the Arbitration and Conciliation Act, 1996.
The main legal point established is the court's authority to appoint a Sole Arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 to resolve disputes between parties as agreed upo....
The court confirmed the existence of an arbitration agreement and mandated the appointment of a sole arbitrator to adjudicate contract disputes, highlighting the necessity of complying with contractu....
The main legal principle established is the appointment of a Sole Arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 to resolve disputes arising from a Tender Agreement.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.