SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
IRB Chitradurga Tollway Private Limited - Appellant
Versus
National Highways Authority of India - Respondent
Arb.P. 573 of 2019
Decided On : 16-03-2022




The court emphasized the necessity of arbitration for disputes arising from contractual agreements when the existence of an arbitration agreement is prima facie established, allowing parties to resolve differences through the arbitral process.

Headnote:(A) Arbitration & Conciliation Act, 1996 - Section 11(6) - Disputes arising from a Concession Agreement related to toll collection and premium payments - The appellant sought appointment of an arbitrator due to disputes over revenue shortfalls and compliance with the Supplementary Agreement - The court affirmed that arbitration must be referred if the existence of the agreement is prima facie satisfied. (Paras 8, 15, 18)

(B) Arbitration Agreement - Courts must take a prima facie view of the arbitration agreement at the referral stage, ensuring that disputes are referred if the agreement's existence is established at this level. (Paras 15, 17)

(C) Judicial Intervention - The Law Commission's 246th Report emphasizes limiting intervention in arbitration matters so that only clear nullity or non-existence of the agreement merits refusal to arbitrate. (Paras 16, 17)

Facts of the case:
The appellant entered a Concession Agreement for toll operation that required annual premium payments. Revenue shortfalls led to the invocation of a deferment scheme sanctioned by the respondent, with subsequent disputes arising about the revenue figures and premium compliance.

Findings of Court:
The court decided to refer the dispute to arbitration, appointing a former Supreme Court judge as the arbitrator, affirming the existence of an arbitration agreement.

Issues: The court addressed whether the disputes arising from the Supplementary Agreement could be referred to arbitration under the Concession Agreement.

Ratio Decidendi: The court held that discrepancies in revenue management invoke existing arbitration agreements for resolution and that disputes must be resolved through arbitration if their existence is prima facie established.

Result: Petition allowed, arbitrator appointed.

Table of Content
1. dispute arising from concession agreement (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8)
2. arguments regarding arbitration clause (Para 11 , 12 , 13 , 14)
3. court's view on arbitration agreement (Para 15 , 16 , 17)
4. petition allowed appointing arbitrator (Para 18 , 19 , 20 , 21)
5. final order disposing petition (Para 22)

JUDGMENT

Vibhu Bakhru, J. (Oral)

1. The petitioner has filed the present petition under Section 11(6) of the Arbitration & Conciliation Act, 1996 (hereafter the `A&C Act'), inter alia, praying that an Arbitrator be appointed to adjudicate the disputes between the parties.

2. The parties had entered into a Concession Agreement dated 16.08.2010 for six-laning of the Tumkur-Chitradurga section from KM 75 to KM 189 of National Highway-4 in the state of Karnataka and for operation and maintenance of the Project Highway for a period of 26 years on `Design Build Finance Operate Transfer Basis'.

3. In terms of the aforesaid Concession Agreement, the petitioner was required to pay a premium of Rs.140.40 crores to the respondent for each year with an annual increase at the rate of 5%. The petitioner states that there was revenue shortfall from the realization of the project. Similar issues were also faced by other Concessionaires.

4. In this backdrop, the Central Government floated a `Premium Deferent Scheme' by a Circular dated 04.03.2014. It is stated that in terms of the said Scheme, the premium payment to the extent of shortfall was deferred to a later stage. The petitioner applied to avail benefit of the said Scheme and sought modification of the terms of payment of premium as agreed under the Concession Agreement. The respondent by a letter dated 06.06.2014 approved the same and granted deferment of the premium to the extent of the revenue shortfall as projected.

5. The petitioner states that in terms of Clause 3(b) of the Scheme, interest at the rate of 2% per annum above the bank rate, was payable on the deferred premium amounts.

6. Thereafter on 06.06.2014, the parties entered into a Supplementary Agreement.

7. Certain disputes have arisen between the parties with regard to the shortfall of revenue. The petitioner claims that shortfall of revenue was required to be re-evaluated and, on such re-evaluation, it was found that the shortfall was higher than the earlier projected shortfall. This is contested by the respondent. The respondent claims that the revenue deficit was lesser by more than 5% of the projected revenue and therefore, has demanded additional premium from the petitioner.

8. In view of the disputes between the parties, the petitioner invoked the Dispute Resolution Mechanism as provided under Article 44.2 of the Concession Agreement and sought resolution of the disputes by conciliation. According to the petitioner, the conciliation proceedings were not successful and by a letter dated 03.05.2019, the petitioner declared that the conciliation proceedings had failed. The petitioner invoked the Arbitration Agreement in terms of Article 44.3. of the Conciliation Agreement and also nominated an Arbitrator. It is stated that certain meetings were held between the parties, however, NHAI has failed to appoint an Arbitrator.

9. In the meanwhile, the petitioner filed a petition under Section 9 of the A&C Act [being OMP(I)(COMM) no.270/2019]. The said petition was allowed and certain interim reliefs were granted to the petitioner.

10. Article 44.3 of the Concession Agreement reads as under:

    "44.3 Arbitration

    44.3.1 Any Dispute which is not resolved amicably by conciliation, as provided in Clause 44.2, shall be finally decided by reference to arbitration by a Board of Arbitrators appointed in accordance with Clause 44.3.2. Such arbitration shall be held in accordance with the Rules of Arbitration of the International Centre for Alternative Dispute Resolution, New Delhi (the "Rules"), or such other rules as may be mutually agreed by the parties, and shall be subject to the provisions

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top