SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Sanjeev Narula, J.
Bharat Heavy Electricals Limited - Appellant
Versus
Vasavi Power Services Pvt. Ltd. - Respondent
O.M.P. (COMM) 471 of 2020, I.As. 12171 of 2020, 3560 of 2021, 7480 of 2021 & 7909 of 2021 and O.M.P. (COMM) 472 of 2020, I.As. 12170 of 2020, 3548 of 2021, 6262 of 2021 & 7482 of 2021
Decided On : 19-01-2022




The court confirmed that arbitrators' findings on contractual breaches and damages claims must be upheld unless shown to be improper within limited review under Section 34 of the Arbitration Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral awards - Withdrawal of work by respondent deemed unjustified, held to be a breach of contract resulting in liability for damages including price escalation and loss of expected profits awarded to claimant - Court emphasizes limited scope of judicial interference and upholds the arbitral findings on delay and compensation. (Paras 6.6, 6.12, 13.3, 41.1)

(B) Legal principles - Arbitrators should not interfere with findings unless there is a clear error or illegality; evidence presented to the Tribunal is subject to its assessment. (Paras 6.1, 6.2)

(C)

Facts of the case:
The appellant, having withdrawn work from the respondent based on alleged delays, was found liable for unjust withdrawal and for the ensuing losses the respondent faced, including costs for inflation. The arbitration ruling favored the respondent, leading to the present challenge. (Paras 4.2, 6.6)

(D)

Findings of Court:
The Court supported the arbitral rulings on damages, upholding awards for increased costs and profits lost due to breach of contract by the appellant while denying claims that were unsupported by evidence. (Paras 6.10, 13.3, 29.4) (E)

Issues: The main issues involved whether the withdrawal of work was justified, the claim for damages due to delays, and the validity of calculated losses due to bad weather and storage conditions. (Paras 4.2, 37.1) (F)

Ratio Decidendi: The court accurately adjusted the arbitral award, entitling the respondent to losses incurred strictly based on the underlying contractual obligations and delays attributable to the appellant. (Paras 41.5, 50.1) (G)

Result: Appeals are partially allowed in terms of re-evaluating some awards but overall upheld against the appellant's major claims. (Paras 52.1, 52.2)

JUDGMENT

[VIA VIDEO CONFERENCING]

Sanjeev Narula, J. (Oral)

CONTENTS

BRIEF FACTS389
A. The Contracts390
B. The Dispute390
C. The Arbitration390
GENERAL OBJECTIONS390
A.Limited Scope of Judicial Interference under Section 34 of the Act 391
B. Findings on breach/delay 391
C.Findings on Compensation/Damages392
CLAIM-WISE OBJECTIONS AND ANALYSE392
A.40% Price increase on balance value392
B.Loss of Profit @ 10% on withdrawn work396
C.Infructuous expenses due to premature withdrawal399
D.Hire Charges of Tools and Plants (T&Ps) after 25th October 2011401
E. Claim awarded for Loss towards Infructuous Expenses404
F.BG & OD charges along with Interest406
G.Extra Expenditure due to Bad Storage408
H. Refund of Security Deposit/BG and Retention Money Amount409
I.Legal Expenses on Actuals411
J.Legitimate Claims of Interest Charges i.e., Pendente Lite & Pre Reference Interest On Award Amount412
COUNTER CLAIMS413

1. The present petitions under Section 34 of the Arbitration and Conciliation Act, 1996 [hereinafter `the Act'] have been filed by BHEL seeking setting aside of two separate Impugned Arbitral awards, both dated 10th March, 2020, in respect of Contract No. 659/2010 and 640/2009, which have been challenged separately in O.M.P. (COMM) 471/2020 and 472/2020 respectively [hereinafter referred to as `Awards'].

2. Under the afore-noted Awards, the Sole Arbitrator has partly allowed the claims of the Respondent herein-Vasavi Power Services Private Limited (being the Claimant in arbitration) [hereinafter referred to as `VPSPL'] and rejected BHEL's counter- claims.

3. The nature of claims of VPSPL in the two contracts - which were subject matter of two separate references - are nearly identical. The heads of claim in both the petitions are also overlapping, barring certain additional heads of claims in O.M.P. (COMM) 472/2020. The reasoning and the fact finding is also similar, since the two contracts were interdependent and interrelated. In these circumstances, although there are two separate awards passed by the Arbitrator, the Court finds it apposite to pass a common judgment to decide the two petitions arising out of the two separate awards.

BRIEF FACTS

4. For the sake of brevity and considering the commonality in the two petitions, facts of the case summarised hereinafter as well as the extracts of Impugned Award are culled out from OMP (COMM) 472/2020. The factual differences and objections raised by BHEL that are found to be exclusive to a particular petition will be noted and dealt with separately.

A. The Contracts

4.1. VPSPL, being the L-1 bidder, was awarded the work for "Erection, Testing, Commissioning, Trial Operations and Handing Over of 2X 250 MW STG with related auxiliaries and piping at 1500MW Pragati III CCPP of Pragati Power Corporation at Bawana, Delhi" by BHEL vide the following contracts: (i) No. 621/2009 dated 07th September, 2009, (ii) No. 640/2009 dated 22nd December, 2009, and (iii) No. 659/2010 dated 30th March, 2010. Although the three contracts are separate, but some parts are interdependent for the purpose of completion and execution. For the present judgment, we are concerned with two contracts, being: (i) Contract No. 640/2009, under which, value of the work awarded was Rs.7.5 crores, scheduled commencement date was 19th January, 2010, zero date was decided as 18th March, 2010, and the scheduled completion date as 18th January, 2011 (later extended to December, 2011); and in respect of (ii) Contract No. 659/2010, the value of the work awarded was Rs.7.5 crores, scheduled commencement date and the zero date was decided as 18th March, 2010, and scheduled completion date was 17th March, 2011.

B. The Dispute

4.2. Due to alleged delay, inaction and inability of VPSPL to complete the works in a timely and satisfactory manner, BHEL - vide letter dated 25th and 28th October 2011 - withdrew part of the work from VPSPL's scope of work under the Contracts No. 640/2009 and 659/2010 respectively, (also referred to as `descoped work')

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top