IN THE HIGH COURT OF DELHI
Sanjeev Narula, J.
Bharat Heavy Electricals Limited - Appellant
Versus
Vasavi Power Services Pvt. Ltd. - Respondent
O.M.P. (COMM) 471 of 2020, I.As. 12171 of 2020, 3560 of 2021, 7480 of 2021 & 7909 of 2021 and O.M.P. (COMM) 472 of 2020, I.As. 12170 of 2020, 3548 of 2021, 6262 of 2021 & 7482 of 2021
Decided On : 19-01-2022
JUDGMENT
[VIA VIDEO CONFERENCING]
Sanjeev Narula, J. (Oral)
CONTENTS
| BRIEF FACTS | 389 | |
| A. | The Contracts | 390 |
| B. | The Dispute | 390 |
| C. | The Arbitration | 390 |
| GENERAL OBJECTIONS390 | ||
| A. | Limited Scope of Judicial Interference under Section 34 of the Act | 391 |
| B. | Findings on breach/delay | 391 |
| C. | Findings on Compensation/Damages | 392 |
| CLAIM-WISE OBJECTIONS AND ANALYSE | 392 | |
| A. | 40% Price increase on balance value | 392 |
| B. | Loss of Profit @ 10% on withdrawn work | 396 |
| C. | Infructuous expenses due to premature withdrawal | 399 |
| D. | Hire Charges of Tools and Plants (T&Ps) after 25th October 2011 | 401 |
| E. | Claim awarded for Loss towards Infructuous Expenses | 404 |
| F. | BG & OD charges along with Interest | 406 |
| G. | Extra Expenditure due to Bad Storage | 408 |
| H. | Refund of Security Deposit/BG and Retention Money Amount | 409 |
| I. | Legal Expenses on Actuals | 411 |
| J. | Legitimate Claims of Interest Charges i.e., Pendente Lite & Pre Reference Interest On Award Amount | 412 |
| COUNTER CLAIMS | 413 | |
1. The present petitions under Section 34 of the Arbitration and Conciliation Act, 1996 [hereinafter `the Act'] have been filed by BHEL seeking setting aside of two separate Impugned Arbitral awards, both dated 10th March, 2020, in respect of Contract No. 659/2010 and 640/2009, which have been challenged separately in O.M.P. (COMM) 471/2020 and 472/2020 respectively [hereinafter referred to as `Awards'].
2. Under the afore-noted Awards, the Sole Arbitrator has partly allowed the claims of the Respondent herein-Vasavi Power Services Private Limited (being the Claimant in arbitration) [hereinafter referred to as `VPSPL'] and rejected BHEL's counter- claims.
3. The nature of claims of VPSPL in the two contracts - which were subject matter of two separate references - are nearly identical. The heads of claim in both the petitions are also overlapping, barring certain additional heads of claims in O.M.P. (COMM) 472/2020. The reasoning and the fact finding is also similar, since the two contracts were interdependent and interrelated. In these circumstances, although there are two separate awards passed by the Arbitrator, the Court finds it apposite to pass a common judgment to decide the two petitions arising out of the two separate awards.
BRIEF FACTS
4. For the sake of brevity and considering the commonality in the two petitions, facts of the case summarised hereinafter as well as the extracts of Impugned Award are culled out from OMP (COMM) 472/2020. The factual differences and objections raised by BHEL that are found to be exclusive to a particular petition will be noted and dealt with separately.
A. The Contracts
4.1. VPSPL, being the L-1 bidder, was awarded the work for "Erection, Testing, Commissioning, Trial Operations and Handing Over of 2X 250 MW STG with related auxiliaries and piping at 1500MW Pragati III CCPP of Pragati Power Corporation at Bawana, Delhi" by BHEL vide the following contracts: (i) No. 621/2009 dated 07th September, 2009, (ii) No. 640/2009 dated 22nd December, 2009, and (iii) No. 659/2010 dated 30th March, 2010. Although the three contracts are separate, but some parts are interdependent for the purpose of completion and execution. For the present judgment, we are concerned with two contracts, being: (i) Contract No. 640/2009, under which, value of the work awarded was Rs.7.5 crores, scheduled commencement date was 19th January, 2010, zero date was decided as 18th March, 2010, and the scheduled completion date as 18th January, 2011 (later extended to December, 2011); and in respect of (ii) Contract No. 659/2010, the value of the work awarded was Rs.7.5 crores, scheduled commencement date and the zero date was decided as 18th March, 2010, and scheduled completion date was 17th March, 2011.
B. The Dispute
4.2. Due to alleged delay, inaction and inability of VPSPL to complete the works in a timely and satisfactory manner, BHEL - vide letter dated 25th and 28th October 2011 - withdrew part of the work from VPSPL's scope of work under the Contracts No. 640/2009 and 659/2010 respectively, (also referred to as `descoped work')
The court confirmed that arbitrators' findings on contractual breaches and damages claims must be upheld unless shown to be improper within limited review under Section 34 of the Arbitration Act.
The court upheld the arbitrator's award, emphasizing that even without precise evidence, reasonable estimates of damages are acceptable in arbitration, reaffirming the principle that awards must be l....
The Court emphasized the limited scope of jurisdiction under Section 34 of the Act and the need for evidence to support claims for loss of profit.
The court affirmed the limited scope of review under Section 34 of the Arbitration and Conciliation Act, emphasizing respect for arbitral awards unless stark violations of public policy or procedural....
The court upheld the Arbitrator's findings that the rescission of the contract was unjust and delays were primarily attributable to the petitioner, affirming the award under Section 34 of the Arbitra....
The scope of judicial review under Section 34 of the Arbitration Act is limited to reasons of law and pertains to the arbitral tribunal's adherence to the contract terms and evidence presented.
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
An arbitral award cannot be sustained if it is based on assumptions without concrete evidence, particularly in claims for damages or losses, as established under the Arbitration and Conciliation Act,....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.