IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
HK Toll Road Private Limited - Appellant
Versus
National Highways Authority of India - Respondent
O.M.P.(I) (COMM.) 118 of 2022
Decided On : 12-04-2022
| Table of Content |
|---|
| 1. injunction sought under a&c act. (Para 3 , 4 , 5 , 6 , 7 , 8) |
| 2. dispute over damages and escrow account. (Para 9 , 10 , 11 , 12 , 13) |
| 3. interpretation of concession agreement clauses. (Para 14 , 15 , 16) |
| 4. court analysis of enforceability of certified damages. (Para 17 , 19 , 20) |
| 5. petition dismissed. (Para 21) |
JUDGMENT
Vibhu Bakhru, J. (Oral)
IA No.5668/2022 (for exemption)
1. Exemption is allowed, subject to all just exceptions.
2. The application is disposed of.
O.M.P.(I) (COMM.) 118/2022
3. The petitioner has filed the present petition under Section 9 of the Arbitration & Conciliation Act, 1996 (hereafter the `A&C Act'), inter alia, praying as under:
"a) Grant an injunction against the Respondent from recovering any amount whatsoever for alleged breach of contractual obligations in terms of letter dated 08.10.2021 from the Escrow Account bearing No. 1903201010137 of Canara Bank at Prime Corporate Branch, Mumbai.
b) Grant an injunction on the operation of the letter dated 09.09.2021 issued by the Respondent and the IE's letters dated 22.10.2021 and 02.02.2022, directing the proposed levy and recovery of the damages from the Petitioner.
c) Grant ex parte ad interim reliefs in terms of the above."
4. The respondent (hereinafter `NHAI') had invited proposals by issuing a Request for Qualification (RFQ) for shortlisting the bidders for "construction, operation and maintenance of NH-7 Six-laning of Hosur-Krishnagiri, Km 33.130 to Km 93.000 in the state of Tamil Nadu under NHDP Phase-V on BOT (Toll) on DBFOT basis" (hereinafter `the Project').
5. On 13.05.2010, NHAI had accepted the bid of Reliance Infrastructure Ltd. and instructed furnishing of the Bank Guarantee for a sum of Rs.52.60 crores. Thereafter, the petitioner company was incorporated as a Special Purpose Vehicle for executing the Project.
6. On 02.07.2010, the parties entered into the Concession Agreement for executing the said Project.
7. It is stated that the petitioner had completed the Project and on 05.04.2016, a Provisional Completion Certificate was issued by the Independent Engineer. The Project was thereafter, placed in commercial service.
8. The petitioner indicates that there were some issues with regard to collection of toll and carrying out the maintenance works. The petitioner claims that it had notified NHAI about the occurrence of a force majeure event on account of the outbreak of Covid-19 and the measures taken for combating the pandemic. The petitioner also claimed certain reliefs on account of the said force majeure events.
9. According to the respondent, the petitioner was required to carry out certain rectification works and to maintain the highway. On 01.12.2020, the Independent Engineer issued a letter to the petitioner to carry out certain rectification work in respect of certain defects, in terms of Clause 17.8 of the Concession Agreement. Thereafter, on 16.12.2020, NHAI also issued a notice under Clause 17.9.1 of the Concession Agreement requiring the petitioner to carry out certain repair/remedial measures in respect to the stated defects, within a period of fifteen days. According to the petitioner, it submitted a detailed work programme and also complied with the said directions. However, it apparent that there is a dispute in this regard because according to NHAI, certain defects have not been remedied.
10. On 05.08.2021, the Independent Engineer sent a letter to the respondent estimating the damages at Rs.10,24,42,009/-, on account of breach on the part of the petitioner to comply with its maintenance obligations. The petitioner disputes that it is in default of any of its obligations.
11. On 08.10.2021, NHAI sent a letter to the Canara Bank (Escrow Agent) requesting it to charge damages amounting to Rs.10,24,42,009/- from the Escrow Account (Account bearing no. 1903201010137) of the petitioner. The said letter also indicates the abstract of damages, which the respondent claims is
Damages under the Concession Agreement can be recovered from the Escrow Account based on certification, irrespective of ongoing disputes, ensuring compliance with contractual obligations.
Right to recover damages as per contractual agreements is independent of prior remedial measures, allowing unilateral calculations by authorities for damages under specified articles.
The main legal point established in the judgment is that NHAI's right to recover damages from the escrow account is independent of the remedies provided under Article 15.8, and the damages contemplat....
Point of Law : Limited scope of the jurisdiction of this Court vested in it by Section 34 of the 1996 Act, no occasion arises for this Court to revisit the said findings of the learned Arbitral Tribu....
Point of Law - Limited scope of the jurisdiction of this Court vested in it by Section 34 of the 1996 Act, no occasion arises for this Court to revisit the said findings of the learned Arbitral Tribu....
NHAI is contractually obliged to pay 90% of the Debt Due to lenders irrespective of defaults by the concessionaire, with no deductions permitted.
The court determined that the petition for termination of the Concession Agreement by a non-party under Section 9 of the Arbitration Act was beyond its scope, as it sought final relief rather than in....
If the Concessionaire is able to recover any amount from NHAI, PNB would be well within its right to seek attachment of the said proceeds or take such steps for recovery of the amount from the Conces....
Parties are entitled to interest on payments due under contracts; if no timeframe is specified, payments are due within 15 days of demand. The distinction between interest payments and debt repayment....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.