SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Jyoti Singh, Anoop Kumar Mendiratta, JJ.
Pink City Expressway Private Limited - Appellant
Versus
National Highways Authority of India - Respondent
FAO(OS) (COMM) 158 of 2022
Decided On : 15-06-2022




The court clarified that the powers under Section 9 of the Arbitration and Conciliation Act cannot extend to granting specific performance of a contract or automatic extensions beyond terms explicitly communicated.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 9 - Appeal regarding extension of Concession Agreement - Appellant contended that under Article 29 of the CA, the extension is automatic due to actual traffic falling short of target traffic - Respondent's refusal to formally extend the Concession Period led to debt recovery proceedings - Learned Single Judge dismissed the Section 9 petition stating no automatic extension exists as various communications regarding approval were unchallenged - The court noted the powers under Section 9 cannot extend to granting specific performance of the contract. (Paras 13-20)

(B) Judicial review - Scope of interference in a Section 9 petition is limited to preserving the subject matter of the dispute until Arbitral Tribunal resolves the issue, not extending contracts. (Paras 19, 22)

Facts of the case:
The Appellant, a Special Purpose Vehicle, executed a six-laning project under a Concession Agreement with the Respondent - Dispute arose over the failure of the Respondent to provide a formal acknowledgment for extension of the Concession Period as advised by the Independent Engineer - Subsequent actions led to debt recovery proceedings against the Appellant due to the Respondent's denial to extend the Concession Period.

Findings of Court:
The court upheld the learned Single Judge's finding that there is no automatic extension of the Concession Period and the Appellant did not challenge the relevant communications effectively.

Issues: The main issues included whether the Concession Period should be extended automatically under Article 29 and whether the powers under Section 9 could grant specific performance of a contract.

Ratio Decidendi: The court reasoned that the absence of a challenge to the communications regarding the Concession Period's extension undermined the Appellant's claims, confirming that Section 9 cannot be applied to extend the contract.

Result: Appeal dismissed.

Table of Content
1. establishment of contract extension and disputes. (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12)
2. appellant's arguments for contract extension. (Para 13)
3. respondent's objections to appellant's claims. (Para 14)
4. court's assessment of claims and judgments. (Para 15 , 16 , 17 , 18 , 19 , 20)
5. conclusion and dismissal of appeal. (Para 21 , 22)

JUDGMENT

Jyoti Singh, J. (ORAL)

CM APPL. 28396/2022 (Exemption)

1. Allowed, subject to all just exceptions.

2. Application stands disposed of.

FAO(OS) (COMM) 158/2022 & CM APPL. 28395/2022 (Interim relief)

3. Present appeal arises from the impugned judgment dated 03.06.2022, passed by the learned Single Judge in O.M.P.(I) (COMM.) 166/2022 filed by the Appellant under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the `Act').

4. A brief narrative of the facts, to the extent necessary and relevant for disposal of the present appeal, is that the Appellant is a Special Purpose Vehicle promoted and incorporated specifically for the purpose of executing the work of Six-Laning of Gurgaon-Kotputli-Jaipur Section of NH-8 from KM 42.70 to KM 273.00 on Build, Operate and Transfer (`BOT') basis awarded by National Highways Authority of India (hereinafter referred to as the `Respondent'), in terms of Concession Agreement (`CA') dated 06.06.2008.

5. As per the case set up by the Appellant, on 25.07.2018 Respondent conducted a Traffic Sample Survey in accordance with Article 29.1.1 of the CA, for the years 2016, 2017 and 2018, whereby it was established that as on the Target Date, the Actual Traffic had fallen short by 14.86% of the Target Traffic and accordingly, Respondent wrote to the Independent Engineer (`IE') for factual determination qua modification in the CA.

6. Pursuant to a determination by the IE on 01.08.2018, the Concession Period was deemed extended by 28 months and 24 days, i.e., upto 26.08.2023. Even though the factual determination was made by the IE, the Senior Lenders/Respondent No.2 herein, wanted a formal letter from the Respondent acknowledging the extension upto 26.08.2023, before considering the Resolution Plan of the Appellant. Accordingly, the Senior Lenders and the Appellant requested the Respondent to issue a formal letter according administrative approval. However, despite assurances, a formal letter was not issued and in absence thereof, the Senior Lenders started considering initiation of debt recovery proceedings against the Appellant.

7. In light thereof, the Appellant approached this Court in W.P.(C) 6693/2020 seeking a direction to the Respondent to give its administrative approval in accordance with the determination made by the IE. Vide order dated 21.09.2020, Court directed the Respondent to communicate its stand within 4 weeks to the Appellant. On 10.12.2020, Respondent communicated its acknowledgement for an interim extension of 14 months out of the total 28 months and 24 days.

8. Between January 2021 to February 2022, Senior Lenders also wrote to the Respondent to communicate its approval for the entire period of 28 months and 24 days as per Article 29 of the CA, however, due to the rigid stand of the Respondent, they refused to consider the Resolution Plan and on 10.12.2021, initiated debt recovery proceedings against the Appellant and its promoter companies before the DRT in O.A. No.926/2021.

9. Constrained by the said proceedings, Appellant approached this Court on 10.03.2022 in W.P.(C) 4151/2022, seeking a direction to the Respondent to grant the administrative approval, in accordance with Article 29 of the CA. Vide order dated 25.03.2022, this Court directed the Respondent to duly evaluate the prayer and communicate a decision in respect thereof to the Appellant. Letter dated 29.04.2022, was sent by the Respondent to the Appellant communicating its stand that the interim extension granted upto 02.06.2022 was full and final and also threatened to forcibly takeover the toll plazas on

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top