SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Jyoti Singh, J.
TPF Engineering Pvt. Ltd. - Appellant
Versus
Union of India, Ministry of Road Transport and Highways - Respondent
O.M.P.(I) (COMM.) 198 of 2022 & I.A. 9728-29 of 2022
Decided On : 17-06-2022




The issuance of a termination notice does not terminate the contract if the affected party invokes arbitration within the stipulated period as per the agreement's clause.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 9 - Termination of Consultancy Agreement - Petitioners sought interim relief against the termination notice issued by Respondents, alleging malafide action and lack of opportunity to remedy alleged defaults - Court held that Clause 2.9.6 of the Agreement requires that disputes regarding termination be referred to arbitration; hence, the contract does not terminate except as per arbitral award, allowing for interim stay on termination notice. (Paras 4, 14, 17)

(B) Specific Relief Act, 1963 - Sections 16(c) and 41(e) - The effect of breach and injunctions - The Respondent contended that the contract is determinable and that injunction cannot be granted for contracts which are not specifically enforceable - Court acknowledged the general principle but found that the specific arbitration clause alters standing. (Paras 6, 14)

Facts of the case:
Petition filed by engineering company against Union of India challenging a termination notice issued close to the end of a Consultancy Agreement for infrastructure work. The Petitioners claimed satisfaction with services and lack of prior notice to remedy any alleged defaults. (Paras 2-4)

Findings of Court:
Court found prima facie evidence that issuance of a termination notice does not automatically result in termination of the contract, pending arbitration as per contract provisions. (Paras 14, 16)

Issues: The main issues included the validity of the termination notice and the applicability of arbitration based on the contractual dispute resolution clause. (Paras 4, 14)

Ratio Decidendi: The court upheld that the arbitration clause in the contract creates a prerequisite for termination; thus, a notice does not effectuate termination until arbitration resolves any disputes regarding the contract. (Paras 14, 17)

Result: Stay on operation of the termination notice granted.

Table of Content
1. initiation of arbitration under the 1996 act. (Para 1 , 2)
2. challenging termination and invoking arbitration. (Para 3 , 4 , 5)
3. opposition to stay on termination notice. (Para 6 , 7)
4. stay on termination due to arbitration invocation. (Para 8 , 14 , 15)
5. directing stay on termination notice pending arbitration. (Para 17)

JUDGMENT

Jyoti Singh, J. (Oral)--This is a petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the `1996 Act'), filed by the Petitioners praying for an interim order staying the operation of the impugned notice dated 30.04.2022 issued by Respondents No.1 & 2 (hereinafter referred to as the `Respondents') seeking to terminate the Consultancy Agreement with the Petitioners.

2. The disputes between the parties emanate from the Contract Agreement dated 14.06.2017 executed between the Petitioners as `Authority's Engineer' and the Respondents for the Work of Replacement of Superstructure of Existing Four-Lane Mahatma Gandhi Setu over Ganga River in NH-19, Patna, Bihar, from 212.72 KM to 218.295 KM on Engineering, Procurement and Construction Mode.

3. Learned counsel appearing on behalf of the Petitioners challenging the impugned notice and seeking stay of its operation, raises several contentions, inter alia: (a) Respondents have issued stagewise completion certificate to the Petitioners on being satisfied with the services rendered by them; (b) the action is malafide being initiated at the fag end of the contract when the tenure of the contract has entered the phase of maintenance and the 60 months long contract was to be concluded in the next 17 days; (c) conjoint reading of Clauses 2.8 and 2.9 of the Agreement establishes beyond certitude that the Petitioners were to be afforded an opportunity of remedying any defects/defaults, if any, prior to notice of suspension and only on failure to remedy, a notice of termination of 60 days could be issued which has not happened in the present case since no notice of suspension was issued and no opportunity was given to remedy a purported failure; (d) the report rendered by the Petitioners has been duly accepted by the Respondents; and (e) Completion Certificates dated 30.09.2020 and 16.03.2022 have been issued in favour of the Petitioners expressing satisfaction qua their work.

4. Lastly and emphatically, it was urged by the learned counsel that Clause 2.9.6 of the Consultancy Agreement provides that if either party disputes whether an event specified in paragraphs (a) to (e) of Clause GC 2.9.1 or 2.9.2 has occurred, such party may within 45 days after receipt of termination notice refer the matter to arbitration and this contract shall not be terminated on account of such event except in accordance with the terms of any resulting arbitral award.

5. Relying on an order dated 29.04.2021, passed by a Co-ordinate Bench of this Court in Egis India Consulting Engineers Private Limited v. Pawan Hans Limited, in OMP(I)(COMM.) 148/2021 wherein, reliance was placed on an earlier order dated 22.10.2018 in M/s. Eptisa Servicios De Ingeniera S.L. v. National Highways and Infrastructure Development Corporation Limited, in OMP(I)(COMM.) 371/2018, it is argued that based on a similar clause in the Agreements before the said Courts, interim orders staying the operation of the impugned termination notices have been granted. It is submitted that the Agreement in the present case contains Clause 2.9.6 which contemplates resolution of disputes pertaining to termination of Agreement through arbitration and the Petitioners have invoked the arbitration clause within the stipulated period albeit on the 45th day.

6. Mr. Shukla, on the other hand, opposes the grant of interim relief on the ground that the Agreement in question is a determinable contract. The effect of breach of a contract by a party seeking to specifically enforce the contract under the Indian Law is enshrined in Section 16(c) read with Section 41(e) of

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top