IN THE HIGH COURT OF DELHI
Neena Bansal Krishna, J.
K.B.G. Engineers - Appellant
Versus
Delhi Tourism and Transportation Development Corporation Ltd. - Respondent
Arb.P. 576 of 2022
Decided On : 05-07-2022
| Table of Content |
|---|
| 1. factual background of the case. (Para 2 , 3 , 4 , 5) |
| 2. respondent's procedural objections to arbitration. (Para 6 , 10) |
| 3. court's reasoning on validity of arbitration claims. (Para 8 , 9 , 11) |
| 4. appointment of arbitrator and conclusion. (Para 12 , 13 , 14 , 15) |
JUDGMENT
Neena Bansal Krishna, J. (Oral)--The present petition under Section 11 (6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as `The Act') has been filed on behalf of the petitioner for appointment of an Arbitrator.
2. Facts in brief are that the petitioner is a registered partnership firm and is doing the work of construction in Government and private department since long time. The petitioner was declared successful participant in the Tender published for the execution of the work of "upgradation/Construction of Sub-Registrar Office at DC(South East) Office Complex Gargi College, Lajpat Nagar, New Delhi, SH: Civil work i/c Furniture, Electric and HVAC Work". After completion of all the formalities, Acceptance Letter bearing no. DTTDC/Engg./I(196)/EE(PB-III)/2405 dated 30.07.2014 was awarded to the petitioner.
3. The performance guarantee in terms of the Letter of Acceptance was submitted after which the Agreement bearing No. 7/EE(PB-III)/DTTDC/Engg/2014-15 for execution of work for a total contractual amount of Rs.2,13,59,777/- was entered into between the parties. The date of the commencement of the work was 14.08.2014 and the date of completion was 11.12.2014. The petitioner immediately started the execution of work on issuance of Acceptance Letter but it faced many hindrances during the course of execution of the work at site which were ultimately completed on 28.09.2015. Thereafter, petitioner submitted his Final Bill and Statements of 10CA and 10C vide its letter dated 14.05.2018 and 18.10.2018 against which some payments were made by the respondent in the month of August, 2020.
4. The officers of the respondent failed to make payments of the entire amount despite repeated requests; the petitioner thus sent a letter dated 20.05.2020 to the Executive Engineer to release the entire amount. He also submitted letter dated 21.05.2020 in the office of Chief Project Manager of respondent reiterating its claims and invoking Arbitration clause 25 of GCC of the Agreement. The Superintendent Engineer of the respondent department sent a reply on the pretext that some Undertaking has already been given by the petitioner at the time of release of the Final Bill. The petitioner again submitted a letter dated 20.06.2020 to the Managing Director of respondent. The Chief Engineer of the respondent sent a reply dated 15.07.2020 requesting him to approach Superintending Engineer of respondent in terms of Clause 25 of GCC. A letter dated 10.08.2020 was accordingly submitted to the Superintending Engineer for settlement of disputes and for referring the matter for appointment of Arbitrator for adjudicating of disputes to which a reply dated 04.09.2020 was sent from Chief Engineer of the respondent reiterating the averments made in the letter dated 15.07.2020. The petitioner then submitted a letter dated 21.12.2020 to Chief Engineer of respondent in terms of Clause 25 of the GCC Agreement for settlement of disputes but since no reply came forth, he submitted another letter dated 27.08.2021 to the Managing Director of the respondent despite which the respondent has failed to constitute the Dispute Resolution Committee or to pay the claimed amount along with the interest. It also failed to take any steps for the appointment of the Arbitrator; hence the present petition has been made for appointment of the Arbitrator.
5. The valuation of the subject matter has been done at approximately Rs.10,23,082/- alongwith interest @ 18% per annum from the due date till the date of payment to the petitioner.
6. Learned counsel for the respondent has taken objection that the petitioner had already accepted the Full and Final payment and had eve
The court ruled that jurisdiction under Section 11(6A) is limited to assessing the existence and validity of arbitration agreements, with unresolved factual disputes requiring arbitration.
The court upheld the validity of the arbitration agreement and recognized the petitioner’s adherence to the procedural requirements for arbitration, irrespective of the respondent's claims regarding ....
An arbitration agreement is enforceable despite claims of payment completion, recognizing the agency relationship between parties, allowing disputes to be resolved through arbitration.
Point of Law : Arbitrator making the necessary disclosure as required under Section 12(1) of the Arbitration & Conciliation Act.
The court established that an arbitration agreement exists between the petitioner and the respondents, as the executing agency was acting on behalf of the principal; claims related to payment dispute....
The appointment of an arbitrator is warranted when a valid arbitration clause exists and the opposing party does not object, ensuring prompt resolution of contractual disputes.
The court affirmed that when parties acknowledge disputes in a contractual agreement, an arbitrator must be appointed to resolve these disputes under the Arbitration and Conciliation Act, 1996.
The appointment of an Arbitrator under Section 11(6) requires prima facie consideration of the Arbitration Agreement's existence, not an in-depth examination of disputes, which should be resolved by ....
The central legal point established in the judgment is the court's authority to appoint an arbitrator to resolve disputed claims between parties in accordance with Section 11(6) of the Arbitration an....
The court upheld the arbitrability of disputes arising from contractual obligations, appointing a sole arbitrator under the Arbitration and Conciliation Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.