IN THE HIGH COURT OF DELHI
Neena Bansal Krishna, J.
Om Prakash Kasat - Appellant
Versus
Delhi Development Authority - Respondent
O.M.P(l)(Comm.) No. 313 of 2019
Decided On : 26-05-2022
| Table of Content |
|---|
| 1. background on contract and claims (Para 1 , 2 , 3 , 4 , 5 , 6) |
| 2. respondent's objections and defenses (Para 7 , 8) |
| 3. court's procedural observations (Para 9 , 10 , 11) |
| 4. dismissal of the petition (Para 12) |
JUDGMENT
Neena Bansal Krishna, J. (Oral)--A commercial arbitration petition under Section 9 of the Arbitration & Conciliation Act, 1996 read with section 2(1) (C) of the Commercial Courts, Commercial Division and Commercial Appellate Division of the High Courts Act, 2015 has been filed on behalf of the petitioner.
2. It is stated that the petitioner is an "A" Class Government contractor and was granted tender for construction of Community Hall HAF Pocket, Phase-2, Sector-13 Dwarka. The estimated cost of the project was Rs.6,51,10,646/- and earnest money of Rs.13,02,213/- was part of the contract. The period of completion was twelve months. The Tender was accepted by the petitioner with modified letter for a sum of Rs.4,64,01,993/and the Agreement was duly executed. Pursuant thereto FDR for Rs.23,201,00/- till the validity period of one year three months drawn on Allahabad Bank, was furnished.
3. The petitioner vide letter dated 12th June, 2018 informed the respondents about the completion of the entire work on 24th April, 2018 and made a request for release of Performance Guarantee deposited at the time of award of Tender and also to issue extension of time proforma. The petitioner re-submitted his claims in regard to the payment of GST on the contract amount as awarded before 1st July, 2017 but executed after 1st July, 2017 in accordance with the Circular issued by CPWD. The original books and measurement books, cement register and other hindrance register are all in the custody of the respondent.
4. The petitioner has raised claims against the respondent and requested for release of the same including the security deposit along with interest. The respondent despite repeated requests has failed to make the final payment even after a period of six months.
5. Clause 25 of the Agreement, the dispute settlement mechanism has been provided as Arbitration. The petitioner issued letter on 10th July, 2019 to the respondent invoking Arbitration clause with a request to nominate a sole arbitrator on the requisite proforma of the respondent, but no action has been initiated.
6. It is claimed that the respondent has committed breach of the Agreement dated 22nd March, 2016 and has failed to release Rs.79,03,0367/- which is the agreed and settled payment vide final bill dated 07th March, 2019 despite the completion of the project by the petitioner. It is, therefore, submitted that an ex-parte ad-interim injunction be given directing the respondent to release the payment of the Final bill.
7. The respondent DDA in its reply has taken a preliminary objection that by way of the present petition, the petitioner is seeking an award of final claim which is beyond the scope of Section 9 of the Arbitration & Conciliation Act. In fact, no arbitrable dispute has arisen between the parties. Had he rightly invoked Clause 25 and written to Executive Engineer In-charge of work, he would have been informed that the Final Bill is being processed and is likely to be released within a month. Likewise, dispute qua security deposit has also not arisen in terms of Clause 17 of the Agreement. Moreover, the Agreement was only between the petitioner and Delhi Development Authority and the respondent No.2 Executive Engineer, has no role to play in its individual capacity and is a stranger to arbitration Agreement.
8. On merits, it has been explained that Rs.11,60,050/- out of the security deposit being 90% has already been paid to the petitioner on 17th July, 2019 and the remaining amount shall be released as per Clause 17 of the Agreement, for which the stage has not yet arrived. In regard to final bill in the sum of Rs.79,03,0367/- it is asserted that the time for making payment is six months and not three months as claimed by t
The court dismissed the petition for interim relief under Section 9 of the Arbitration Act, ruling that no arbitrable dispute existed as the respondent had already made the required payments.
The court ruled that jurisdiction under Section 11(6A) is limited to assessing the existence and validity of arbitration agreements, with unresolved factual disputes requiring arbitration.
An interim order can restrain the encashment of bank guarantees pending arbitration if there is a risk of irreparable harm to the aggrieved party.
The court emphasized the need to balance equities between the parties and highlighted the importance of following contractual provisions for submission of the final bill and processing thereof.
The court upheld the validity of the arbitration agreement and recognized the petitioner’s adherence to the procedural requirements for arbitration, irrespective of the respondent's claims regarding ....
Claims for interest on delayed payments are non-arbitrable if precluded by the terms of the Agreement, particularly following the execution of release and discharge certificates.
Point of Law : Arbitrator making the necessary disclosure as required under Section 12(1) of the Arbitration & Conciliation Act.
The main legal point established is the determination of arbitrability of a dispute and the acceptance of belated pleas in the context of appointment of an arbitrator.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.