IN THE HIGH COURT OF DELHI
Neena Bansal Krishna, J.
G.D. Builders - Appellant
Versus
KLJ Developers Pvt. Ltd. - Respondent
Arb.P. 544 of 2022
Decided On : 01-11-2022
JUDGMENT
1. A petition under Section 11(6) of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as "the Act") has been filed for appointment of the Arbitrator to adjudicate the disputes between the parties.
2. It is submitted in the petition that the respondent issued a Letter of Intent bearing reference No.KLJ/DP/FBD/LOI/2012-13/06 on 02.06.2012 for total contractual amount of Rs.2,09,55,000/-. The Work Order KLJ/DP/FBD/WO/2012-13/08 dated 10.06.2012 containing terms and conditions of the work was issued in favour of the petitioner Partnership Firm. The respondent also awarded the work of external development of "Platinum Floors" (Pocket-G)-Group Housing Project at Village Neemka, Sector-77, Faridabad (Haryana) vide Letter of Intent bearing ref. no. KLJ/DP/FBD/LOI/2012-13/07 on 02nd June, 2012 for total contractual amount of Rs.47,00,000/- to the petitioner. The period of contract for both the Works was nine months which was to commence from 15th June, 2012 and the date of completion was 14th March, 2013.
3. During the course of the execution of the work, the respondent made three amendments in the Agreement modifying the scope of work and the contractual amount last stated was Rs.70,52,359/-. During the course of execution of the work, the respondent made seven amendments in the Agreement thereby increasing the contract amount to Rs.3,70,68,517/- through 7th Amendment dated 11th September, 2015.
4. The petitioner completed the entire work of Pocket-G. Thereafter, on the request of the petitioner vide letter dated 12th March, 2015, the respondent acknowledged that the work was completed vide letter dated 18th March, 2015. Similarly, the work of Pocket-A was completed and taken over by the respondent. No Notice of defects was ever issued by the respondent regarding the completion of both Work Orders.
5. The respondent had agreed to reconcile and pay the Final Bill after completion of entire work awarded to the petitioner at Faridabad and Bahadurgarh, Haryana. The petitioner was not allowed to execute further work of Bahadurgarh since October, 2013. However, the work of Faridabad was completed in April, 2017 and handed over the remaining executed work which was to be handed over on or before 15th May, 2017.
6. Since the execution of Work, petitioner had been pursuing its case to finalize the contract at Bahadurgarh and Faridabad and several meeting were held. But the respondents neither finalized the contract nor paid the legal dues of the petitioner.
7. The respondent sent a Notice under Section 21 of the Act dated 25th December, 2021 raising claims of Rs.5,71,71,845/- against the work Orders No. 05 dated 15th February, 2008, No. 07 dated 30th July, 2010 and No. 08 and 09 dated 10th June, 2012 awarded by the respondent to the petitioner. The petitioner vide its reply dated 24th January, 2022 sent through email and speed post, raised its own Claims which were denied by the respondent vide their reply dated 15th March, 2022.
8. It is asserted that disputes have arisen between the parties in respect of release of amount for the work done by the petitioner. The work order dated 10th June, 2012 contained Arbitration Clause No.29 which provides for settlement of disputes through Arbitration. A prayer is, therefore made that a Sole Arbitrator may be appointed.
9. Learned Counsel for the respondent has not disputed the Arbitration Clause for resolution of the disputes that may arise between the parties in respect of the Work Orders but has essentially challenged the present petition on the ground of Limitation. It is submitted that as per the petitioner himself, the Work was completed on 18th March, 2015 and the additional work was completed on 15th May, 2017. The Letter of Invocation of Arbitration has been issued only on 02nd February, 2022 which was also by way of reply to the Notice of the respondent claiming amounts and seeking referral of the disputes to Arbitration. It is vehemently argued that
The court ruled that claims for arbitration were not patently barred by limitation, allowing the petition to proceed despite challenges on this ground.
Arbitration clauses must be honored, and disputes regarding limitation can be addressed by the arbitrator, reinforcing that claims raised by either party do not void the arbitration process.
Claims for arbitration may not be barred by limitation where disputes involve mixed questions of fact and law, and both parties may present defenses to the arbitrator.
The court upheld the validity of the arbitration agreement and recognized the petitioner’s adherence to the procedural requirements for arbitration, irrespective of the respondent's claims regarding ....
The court has the authority to appoint a sole Arbitrator when disputes arise under an arbitration clause and the responding party does not object to the appointment.
The court's decision emphasizes the validity of invoking arbitration in accordance with the arbitration clause of the work order and the importance of compliance with Section 12 of the Arbitration an....
Arbitration Agreement - Appointment of - The learned Arbitrator shall ensure compliance of Section 12 of Arbitration and Conciliation Act, 1996 before commencing the arbitration.
The court confirmed the validity of invoking arbitration under the Arbitration and Conciliation Act when disputes arise over contract performance and payment.
Court under Section 11(6) appoints arbitrator upon undisputed invocation of arbitration clause in contract, permitting respondents to raise limitation and merits objections before tribunal.
The court upheld the arbitrability of disputes arising from contractual obligations, appointing a sole arbitrator under the Arbitration and Conciliation Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.