SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Neena Bansal Krishna, J.
G.D. Builders - Appellant
Versus
KLJ Developers Pvt. Ltd. - Respondent
Arb.P. 544 of 2022
Decided On : 01-11-2022




The court ruled that claims for arbitration were not patently barred by limitation, allowing the petition to proceed despite challenges on this ground.

Headnote:(A) Arbitration & Conciliation Act, 1996 - Section 11(6) - Petition for appointment of Arbitrator - Disputes arose regarding payment for work completed - Respondent admitted the arbitration clause but challenged on grounds of limitation - Completion dates for work were acknowledged - Supreme Court ruling on limitation applied. (Paras 1, 9, 12, 15)

(B) Limitation - Mixed question of fact and law - Claims not patently barred - Respondent permitted to raise contentions before the Arbitrator. (Paras 9, 13)

Facts of the case:
The petitioner completed contractual work for a specified amount, but the respondent delayed payments and issued a claim notice. The petitioner invoked the arbitration clause based on additional claims and disputes. (Paras 2, 6, 9)

Findings of Court:
The court found no limitation barring the petition and appointed an Arbitrator to address the disputes. (Paras 9, 15)

Issues: Whether the claims were barred by limitation and whether arbitration should proceed. (Paras 9, 13)

Ratio Decidendi: The court emphasized that questions of limitation can be determined by the Arbitrator, and the ongoing claims presented by the respondent indicated that the arbitration clause remained valid. (Paras 14, 15)

Result: Petition succeeds; Arbitrator appointed.

JUDGMENT

1. A petition under Section 11(6) of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as "the Act") has been filed for appointment of the Arbitrator to adjudicate the disputes between the parties.

2. It is submitted in the petition that the respondent issued a Letter of Intent bearing reference No.KLJ/DP/FBD/LOI/2012-13/06 on 02.06.2012 for total contractual amount of Rs.2,09,55,000/-. The Work Order KLJ/DP/FBD/WO/2012-13/08 dated 10.06.2012 containing terms and conditions of the work was issued in favour of the petitioner Partnership Firm. The respondent also awarded the work of external development of "Platinum Floors" (Pocket-G)-Group Housing Project at Village Neemka, Sector-77, Faridabad (Haryana) vide Letter of Intent bearing ref. no. KLJ/DP/FBD/LOI/2012-13/07 on 02nd June, 2012 for total contractual amount of Rs.47,00,000/- to the petitioner. The period of contract for both the Works was nine months which was to commence from 15th June, 2012 and the date of completion was 14th March, 2013.

3. During the course of the execution of the work, the respondent made three amendments in the Agreement modifying the scope of work and the contractual amount last stated was Rs.70,52,359/-. During the course of execution of the work, the respondent made seven amendments in the Agreement thereby increasing the contract amount to Rs.3,70,68,517/- through 7th Amendment dated 11th September, 2015.

4. The petitioner completed the entire work of Pocket-G. Thereafter, on the request of the petitioner vide letter dated 12th March, 2015, the respondent acknowledged that the work was completed vide letter dated 18th March, 2015. Similarly, the work of Pocket-A was completed and taken over by the respondent. No Notice of defects was ever issued by the respondent regarding the completion of both Work Orders.

5. The respondent had agreed to reconcile and pay the Final Bill after completion of entire work awarded to the petitioner at Faridabad and Bahadurgarh, Haryana. The petitioner was not allowed to execute further work of Bahadurgarh since October, 2013. However, the work of Faridabad was completed in April, 2017 and handed over the remaining executed work which was to be handed over on or before 15th May, 2017.

6. Since the execution of Work, petitioner had been pursuing its case to finalize the contract at Bahadurgarh and Faridabad and several meeting were held. But the respondents neither finalized the contract nor paid the legal dues of the petitioner.

7. The respondent sent a Notice under Section 21 of the Act dated 25th December, 2021 raising claims of Rs.5,71,71,845/- against the work Orders No. 05 dated 15th February, 2008, No. 07 dated 30th July, 2010 and No. 08 and 09 dated 10th June, 2012 awarded by the respondent to the petitioner. The petitioner vide its reply dated 24th January, 2022 sent through email and speed post, raised its own Claims which were denied by the respondent vide their reply dated 15th March, 2022.

8. It is asserted that disputes have arisen between the parties in respect of release of amount for the work done by the petitioner. The work order dated 10th June, 2012 contained Arbitration Clause No.29 which provides for settlement of disputes through Arbitration. A prayer is, therefore made that a Sole Arbitrator may be appointed.

9. Learned Counsel for the respondent has not disputed the Arbitration Clause for resolution of the disputes that may arise between the parties in respect of the Work Orders but has essentially challenged the present petition on the ground of Limitation. It is submitted that as per the petitioner himself, the Work was completed on 18th March, 2015 and the additional work was completed on 15th May, 2017. The Letter of Invocation of Arbitration has been issued only on 02nd February, 2022 which was also by way of reply to the Notice of the respondent claiming amounts and seeking referral of the disputes to Arbitration. It is vehemently argued that

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top