IN THE HIGH COURT OF DELHI
Neena Bansal Krishna, J.
G.D. Builders - Appellant
Versus
KLJ Developers Pvt. Ltd. - Respondent
Arb.P. 546 of 2022
Decided On : 01-11-2022
| Table of Content |
|---|
| 1. petition for appointment of arbitrator and contract details. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7) |
| 2. respondent challenges petition on limitation grounds. (Para 8) |
| 3. court permits both parties to raise all rights before arbitrator. (Para 9 , 11) |
| 4. supreme court ruling on limitation and its application. (Para 10) |
| 5. appointment of arbitrator and arbitration directions. (Para 12 , 13) |
JUDGMENT
1. A petition under Section 11(6) of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as "the Act") has been filed for appointment of the Arbitrator.
2. It is submitted in the petition that respondent sister concern M/s KLJ Town Planners Pvt. Ltd. had invited tender for "Residential Group Housing Project at Sector-77, KLJ Greens, Village Neemka, Faridabad, Haryana". The petitioner was declared as successful bidder. Respondent had issued a letter of intent bearing ref.no. KLJ/TP/FBD/2007-08/04 dated 09th January 2008 on total contractual amount of Rs.27,95,05,150/-. The fresh work order no. KLJ/TP/FBD/2007-08/05 dated 15th February, 2008 was issued by the respondent to the petitioner which contains the terms and conditions oi this work. As per Clause 7 of the Work Order dated 15th February, 2008, the period of completion of work was 30 months i.e. from 1st March, 2008 to 31st August, 2010. The defect liability period was 12 months from the date of handing over of the complete site in terms of clause 2 of letter of intent the work was not commenced as the drawing for excavation was given by the respondent company on 01st May, 2008 and setting layout plan, column layout plan and reinforcement details were given on 17th May, 2008 and 02nd June 2008 respectively, therefore, there was delay in execution of work from 1st March 2008 to 2nd June 2008, which was attributed to the respondent company. Till 17th March, 2015, the rates/scope and value of the contract were revised 20 times and the contractual amount increased to Rs.40,29,33,712/-.
3. The petitioner had completed the entire work on 30th April, 2017 and even prior to that handed over some towers, and the remaining towers were handed over before 10th May, 2017. The petitioner had also completely removed its T&P and materials from the site between 10th May, 2017 to 15th May, 2017.
4. The petitioner had submitted the Final Bill before 20th March, 2018 of the total amount of Rs.2,00,67,062/-. Several meetings were held between the partners of petitioner and the director and representatives of the respondent. Every time in the meetings, only assurances were given by the respondent company.
5. It is claimed that despite repeated verbal assurances given by the respondent for making due payment to the petitioner, the respondent has failed to honour its commitments.
6. The respondent sent a Notice dated 25th December, 2021 under Section 21 of the Act illegally claiming Rs.5,71,71,845/- against the Work Order no. 05 dated 15th February, 2008, no.07 dated 30th July, 2010 and no. 08 and 09 dated 10th June, 2012 awarded by the respondent to the petitioner, to which the petitioner had sent a reply dated 24th January, 2022. The petitioner had also petitioner had sent a legal notice dated 18th January, 2022 thereby invoking arbitration clause and raising legally tenable claims, which was responded by the respondent in their reply dated 15th March, 2022 denying the claims of the petitioner.
7. It is asserted that disputes have arisen between the parties in respect of release of amount for the work done by the petitioner. The Work Order dated 15th February, 2008 contained Arbitration Clause No. 28 which provides for settlement of disputes through Arbitration. A prayer is, therefore made that a Sole Arbitrator may be appointed.
8. Learned Counsel for the respondent has not disputed the Arbitration Clause for resolution of the disputes that may arise between the parties in respect of the Work Order, but has essentially challenged the present petition on the ground
Arbitration clauses must be honored, and disputes regarding limitation can be addressed by the arbitrator, reinforcing that claims raised by either party do not void the arbitration process.
Claims for arbitration may not be barred by limitation where disputes involve mixed questions of fact and law, and both parties may present defenses to the arbitrator.
The court ruled that claims for arbitration were not patently barred by limitation, allowing the petition to proceed despite challenges on this ground.
The central legal point established in the judgment is the court's authority to appoint an arbitrator to resolve disputed claims between parties in accordance with Section 11(6) of the Arbitration an....
The court affirmed that when parties acknowledge disputes in a contractual agreement, an arbitrator must be appointed to resolve these disputes under the Arbitration and Conciliation Act, 1996.
The court upheld the validity of the arbitration agreement and recognized the petitioner’s adherence to the procedural requirements for arbitration, irrespective of the respondent's claims regarding ....
The main legal point established is that a party to a contract cannot absolve its liabilities and must comply with dispute resolution clauses, and claims must be within the period of limitation.
The court ruled that a Sole Arbitrator is to be appointed to resolve disputes under the contract due to the respondent's failure to meet contractual obligations.
Disputes concerning contract completion and payment arise, necessitating arbitration as per the Arbitration and Conciliation Act, 1996.
Court under Section 11(6) appoints arbitrator upon undisputed invocation of arbitration clause in contract, permitting respondents to raise limitation and merits objections before tribunal.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.