SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, Purushaindra Kumar Kaurav, JJ.
Icon Sleeper Track Private Limited - Appellant
Versus
Rail Vikas Nigam Limited - Respondent
FAO(COMM) 38 of 2022
Decided On : 23-12-2022




The interpretation of contract terms, particularly regarding price adjustments and inclusivity of tax components, cannot be altered post-agreement without breaching contract law principles.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Commercial Courts Act, 2015 - Section 13 - Appeal against arbitration award - The Commercial Court upheld the arbitral tribunal's decision rejecting the claim for price adjustment of cement based on contract terms involving base cost and excise duty - The interpretation by the arbitral tribunal was held to be clear and beyond reproach. (Paras 1, 3, 12, 14)

(B) Contracts - Interpretation of terms - The understanding of contract provisions regarding price variations must adhere to the explicit terms established, and deviations from agreed definitions could constitute a rewriting of the contract, which is impermissible. (Paras 11, 13, 15)

(C) Public Policy - The court concluded that the arbitral award did not violate fundamental policy principles of Indian law or morality, thus, appeal dismissed. (Paras 14, 15)

Facts of the case:
The appellants challenged the arbitration award related to a contract for manufacture and supply of railway sleeper plants, focusing on the interpretation of price adjustment terms in the contract.

Findings of Court:
The court affirmed the arbitral tribunal's understanding of contract terms, finding no errors in contractual interpretations causing patent illegality.

Issues: The main issues included the interpretation of terms related to price adjustment and the inclusion/exclusion of excise duty components.

Ratio Decidendi: The court held that the terms of the contract were clear and unambiguous; changes sought would amount to altering the contract instead of applying its terms faithfully.

Result: Appeal dismissed.

Table of Content
1. procedural background of the appeal (Para 1 , 2)
2. claim of patent illegality regarding arbitration award (Para 3)
3. opposition to claims made by appellants (Para 4)
4. framework of price adjustment formula in contract (Para 7 , 8 , 9 , 10 , 11)
5. court's reliance on established contract law principles (Para 12 , 13)
6. importance of adhering to original contract terms (Para 14)
7. conclusion upholding arbitration award (Para 15)

JUDGMENT

Purushaindra Kumar Kaurav, J.

1. This appeal under Section 37 of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as `A&C Act') read with Section 13 of the Commercial Courts Acts, 2015 (hereinafter referred to as `CCA') is directed against the order dated 10.12.2021, passed by the District Judge (Commercial Court)-01 Patiala House Courts, New Delhi, rejecting an application under Section 34 of the A&C Act and affirming the arbitration award dated 03.08.2010 passed by the Arbitral Tribunal (hereinafter referred as `AT').

2. The brief facts leading to filing of the present appeal are as under:

(i) The respondent-Rail Vikas Nigam Limited (RVNL) invited bids for the work of "MANUFACTURE AND SUPPLY OF PSC MONO-BLOCK SLEEPER PLANTS FOR VARIOUS RAIL ROADS PROJECTS IN DIFFERENT REGIONS OF INDIA".

(ii) The appellant No. 2/ M/s Vaman Prestressing Company Private Limited (VPCL) was one of the bidders whose bid was found to be viable and was offered for performance of the work in question. The appellant No. 2/VPCL on 31.08.2007 accepted the offer unconditionally and had a request for exemption from excise duty on raw material and assignment of contract to M/s Icon Sleeper Track Private Limited (ISTPL) as per Clause-36 of Section VI of General Conditions of Contract (GCC). It be noted that ISTPL is appellant No. 1 in the instant appeal.

(iii) On 14.09.2007, RVNL accepted the request of VPCL granting an exemption for excise duty and assignment of contract to ISTPL. The period for completion of the whole work was 18 months from the date of acceptance of the counter-offer by RVNL.

(iv) On 05.11.2007, an agreement was entered into between VPCL & RVNL. During the course of execution of the work, certain disputes arose between the contracting parties. In accordance with the provisions of Clause 10.1 of GCC of the contract agreement, efforts for amicable settlement of the disputes were made between the parties. However, the parties failed to arrive at an amicable settlement. Resultantly, in accordance with the provisions of Clause 10.2 of the GCC, the AT was constituted, consisting of a presiding arbitrator and two other members. The AT after conducting various hearings, passed the final award on 05.08.2019, rejecting the claim of the appellants.

(v) The appellants challenged the award passed by the AT in an application under Section 34 of the A&C Act before the learned Commercial Court. The learned Commercial Court passed the impugned order and did not find any substance in the said application and has rejected the same. Therefore, the appellants have approached this court in the present application under Section 37 of the A&C Act.

3. Learned senior counsel appearing on behalf of the appellants vehemently submitted that the impugned order and award passed by the AT is patently illegal and against the Public Policy of India and hence, deserves to be set aside by this court. According to him, the entire understanding of the AT and the Commercial Court is erroneous, inasmuch as, the appellants are only insisting on the due observance of the terms of the contract in their strict sense. While taking this court through condition 15.2 of the GCC, he has specifically pointed out that C0 is defined as the base cost of the cement per MT including ED, ST/VAT and freight equal to Rs.4,080/- and C1 is defined as the cost of the cement per MT including ED, ST/VAT and freight on the date of adjustment. He, therefore, submitted that C0 is the base cost of cement, which includes excise duty

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top