SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, Gaurang Kanth, JJ.
Indian Oil Corporation Ltd. - Appellant
Versus
Institute of Geo Informatics Pvt. Ltd. - Respondent
FAO(OS) (COMM) 189 of 2017
Decided On : 10-01-2023




The arbitration awards must only address claims within the contractual framework; arbitrary or excessive costs cannot be imposed against a party prevailing in the challenge to non-arbitrable claims.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Legal standards for interference with Arbitral Awards - The court focuses on arbitrability, jurisdiction, and the grounds of public policy & patent illegality. (Paras 17, 31, 39)

(B) Contracts - Performance, claims and counterclaims - Arbitral Tribunal's jurisdiction must align with notified claims under the contract, with subsequent judicial approval - Claims deemed non-arbitrable are set aside, leaving findings on counterclaims intact unless perverse or without reason. (Paras 35, 39)

(C) Costs - Costs follow the event; if the appellant prevails, prior costs awards not justified. (Paras 52, 54)

Facts of the case:
The appellant sought to terminate a survey contract, resulting in disputes over claims by both parties following arbitration. The Arbitral Tribunal's award was partially set aside by a Single Judge, which led to appeals and review petitions concerning costs and counterclaims.

Findings of Court:
The court ruled in favor of the respondent on certain claims while dismissing the appellant's counterclaims regarding performance deficiencies. The court upheld previous findings that the costs awarded were excessive.

Issues: The primary legal questions addressed involved the applicability of arbitration to non-notified claims, and whether the costs awarded were justifiable based on the nature of the outcomes.

Ratio Decidendi: The court affirmed that jurisdictional issues and the foundation of claims require clear contractual alignment; otherwise, findings are subject to set aside. Disallowance of costs awarded harms the principle of costs following the event when an appeal leads to prevailing party outcomes.

Result: Appeals disposed of in favor of the respective claims and costs determinations.

JUDGMENT

Gaurang Kanth, J. By a common order dated order dated 23.08.2018, this court had disposed of the above captioned appeal as well as the appeal preferred by the respondent [FAO(OS)(COMM) 197/2017] against an order dated 14.09.2017 passed by the learned Single Judge. In OMP (COMM) 317/2017. The present appeal was taken up for hearing pursuant to the order dated 17.01.2020 passed by this Court, whereby the appellant's review petition (Review Petition No. 348/2018) seeking review of the order dated 23.08.2018 was allowed. The appellant had sought review of the said order dated 23.08.2018 on the ground that its challenge to rejection of counter-claims was not considered. The respondent has also filed a petition seeking review of the said order dated 23.08.2018 (Review Petition No. 361/2018), which was confined to setting aside the award of costs. This Court had disposed of the said petition by observing that the said aspect of costs would be considered at the time of disposal of the appeal.

2. The Learned Single Judge of this Court, vide order dated 04.09.2017 ("Impugned Order") in OMP (COMM) 317/2017 captioned as "Indian Oil Corporation Limited Pipelines Division (PLHO) Vs Institute Of Geo-Informatics Pvt. Ltd." had partly allowed the application filed by the Appellant under Section 34 of the Arbitration & Conciliation Act, 1996 Act ("A&C Act") seeking to set aside the arbitral award dated 05.05.2017 ("Impugned Award").

3. Aggrieved by the said Impugned Order, both the parties filed separate Appeals, i.e., FAO (OS) (Comm) 189/2017 titled as Indian Oil Corporation Ltd. Vs Institute of Geo Informatics Pvt. Ltd. & FAO (OS) (Comm) 197/2017 titled as Institute of Geo Informatics Pvt Ltd Vs Indian Oil Corporation Ltd.. The Division Bench of this Court vide Judgment dated 23.08.2018, was pleased to allow FAO (OS) Comm) 189/2017 to the extent of setting aside the award of costs, and dismiss FAO (OS) (Comm) 197/2017.

4. Subsequently, both the parties filed Review Petitions for reviewing the Judgment dated 23.08.2018. The Appellant filed Review Petition No.348/2018 and the Respondent filed Review Petition No. 361/2018. This Court vide order dated 17.01.2020 allowed the Review Petition No.348/2018 to a limited extent holding, inter alia, as follows:

    "For the aforesaid reasons, we allow the review petition to the extent that this Court did not deal with the appellant's submissions qua the non-consideration by the learned Single Judge of the appellant's objections to the rejection of the counter claim by the learned Arbitrator."

This Court disposed of the Review Petition No.361/2018, inter alia, observing as follows:

    "We dispose of this review petition by observing that the aforesaid aspect would be considered by the Court at the stage of disposing of the appeal on the aspect on which the judgment dated 23.08.2018 stands reviewed."

FACTUAL MATRIX RELEVANT FOR THE DISPOSAL OF THE PRESENT APPEAL ARE AS FOLLOWS:

5. Before proceeding further with the analysis, it will be apposite to refer to the relevant facts necessary to address the controversy raised in the present appeal.

6. The Appellant is a Government of India undertaking engaged in petroleum refining, marketing and transportation and maintenance of crude and petroleum products pipelines throughout the length of the country. For the laying of one such LPG pipeline, the Appellant required certain detailed surveys to be carried out. For this purpose, the Appellant invited sealed tenders on 19.11.2009.

7. Pursuant to the Respondent being declared as the successful bidder, a Letter of Acceptance dated 15.06.2010 ("LOA") was issued to the Respondent which was followed by execution of the main Contract No. PLCC/PHDPL/CL/0960 (Work Order No. 23166768) on 14.07.2010. The Contract envisaged execution of work of "Detailed Engineering survey, Soil survey, Cadastral survey & providing services for establishing ROU in ROW of Paradip-Haldia-Durgapur LPG Pipeline Project" (TENDER NO. P

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top