IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
P. Naveen Rao, J. Sreenivas Rao, JJ.
M/s. Sri. Rama Constructions (formerly known as Rohini Constructions) - Appellant Versus
M/s. Max Infra (I) Limited and another - Respondents
Commercial Court Appeal Nos.48 & 49 of 2020
Decided On : 02-03-2023
Arbitration and Conciliation Act, 1996 - Section 11 and 34 - Award of work Contract - Termination of Contract - Whether termination of work order Respondent is proper and legal - Held, Though Court below may not be right in reason for not remitting matter to arbitration matter to the Arbitrator - As per Section 34(4) of Act, 1996 if Court deems it appropriate and it is so requested by a party adjourn proceedings in case to give Arbitral Tribunal opportunity to resume arbitral proceedings or to take other action as in opinion of Arbitral Tribunal would eliminate grounds for setting aside the arbitral award - Even this course is available only upon a written application made by a party and not suu-moto - After a decision is made issue of remitting to Arbitrator does not arise - Only course available to the Court in the application under Section 34 is to set aside or to uphold award - Appeal Dismissed.
JUDGMENT :
P.Naveen Rao, J.
Heard learned counsel Sri K.Prabhakar for the appellant and the learned counsel Ms.Pratusha Boppanna appearing for the learned counsel Sri A.Venkatesh for respondent no.1.
2. The appellant in COMCA No. 48 of 2020 and COMCA.No.49 of 2020 is claimant before the learned Arbitrator and petitioner in C.O.P.No.232 of 2017 in the Court of the Judge Commercial Court cum XXIV Additional Chief Judge, City Civil Court, Hyderabad. The respondent herein is respondent before the learned Arbitrator and petitioner in C.O.P.No.195 of 2017. Parties are referred to as arrayed before the learned Arbitrator.
3. The Government of Andhra Pradesh awarded contract to execute balance of the work of ‘Thotapally Barrage Project EPC Package-1’ to a joint venture comprising of respondent and M/s.Prasad Constructions. The agreement was signed on 31.8.2012. In turn the respondent entrusted the entire work to the claimant with same terms as contained in the agreement dated 31.8.2012 entered with the Government. The agreement was entered into on 10.9.2012 called as ‘work order’. However, the agreement envisaged that out of the bills payable for the works executed by the claimant the respondent is entitled to take 17.5 % towards Royalty.
4. Disputes arose between the parties to the agreement dated 10.9.2012. Alleging that the claimant failed to execute the work within the stipulated time, the respondent issued notice dated 26.5.2015 invoking clause 4 of the ‘work order’ calling upon the claimant to explain within 7 (seven) days from the date of receipt of notice, as to why contract should not be terminated. The claimant responded vide his reply dated 22.6.2015. Respondent terminated the contract.
5. ‘Work Order’ envisaged resolution of disputes through medium of arbitration. The claimant filed Arbitration Application No. 145 of 2015 before this Court under Section 11 of the Arbitration and Conciliation Act, 1996 (the Act, 1996) seeking to appoint an arbitrator. This Court appointed former Chief Justice of Patna High Court Hon’ble Sri Justice L.Narasimha Reddy as Arbitrator. The claimant set up 12 claims before the learned Arbitrator. The respondent made a counter-claim of Rs. 6,47,08,361/- with interest at the rate of 24 % per annum.
6. After considering the submissions of both the parties, the learned Arbitrator framed the following issues:
(ii) Whether the claimant is entitled to amounts claimed in Claims No.1 to 12 of the Claim petition?
7. Upon considering of the pleadings and the documentary evidence placed on record, the Learned Arbitrator held that there was no justification for the respondent to terminate the ‘work order’. The learned Arbitrator allowed Claim Nos.1-A, 2, 4, 5, 8, 10 and 12. Aggrieved by the award, both the parties filed applications under section 34 of the Arbitration and Conciliation Act 1996 before the Commercial Court-cum-XXIV Additional Chief Judge, City Civil Court Hyderabad bearing C.O.P.No. 232 of 2017 and C.O.P.No.195 of 2017. While claimant is aggrieved by the award denying all claims, the respondent is unhappy with the award denying his counter-claim was not considered and also on findings recorded on the issues decided in favour of claimant.
8. The Commercial Court clubbed both the C.O.Ps. After hearing the submissions of both parties, the Commercial Court framed the following issues:
(ii) Whether there is any interference required in the award passed by the arbitrator ? and
(iii) Whether the award passed has to be set aside ?
9. By Common Order dated 1.2.2019 both COPs were disposed of. The Commercial Court observed that the leaned Arbitrator had passed the award without framing any issue with regard to the counter-claim made by the respondent. The Court held that Arbitrator is bound by prudent principles of law to give a
The arbitration awards must only address claims within the contractual framework; arbitrary or excessive costs cannot be imposed against a party prevailing in the challenge to non-arbitrable claims.
The main legal point established in the judgment is that the Arbitrator's decisions must be in accordance with the terms of the Agreement and cannot be patently illegal or against the most basic noti....
Judicial interference with an arbitral award under Section 34 is limited to specific grounds. Courts cannot re-appreciate evidence or substitute their own view. Where parties are given adequate notic....
The court emphasized that arbitral awards should not be interfered with solely based on disagreements with findings, affirming the limited grounds for appeal under Section 34 of the Arbitration Act.
The court established that the discretion to remit an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, should only be exercised when there are curable defects in the awa....
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.