IN THE HIGH COURT OF DELHI AT NEW DELHI
Prateek Jalan
UOI – Appellant
Versus
Jasbir Singh – Respondent
JUDGMENT :
1. By way of this petition under Section 34 of the Arbitration and Conciliation Act, 1996 [hereinafter, “Act”], the petitioner- Union of India [hereinafter, “UoI”] seeks to assail an arbitral award dated 01.10.2014, by which a learned sole arbitrator has adjudicated disputes between the parties under an agreement dated 02.09.2005, bearing No. 24/ee(E)/FCED/2005-06. By way of the impugned award, a sum of Rs.23,09,504/- has been awarded to the respondent- Jasbir Singh, sole proprietor of M/s Kalsi Engineers.
A. Facts:
2. The petitioner invited tenders in the year 2005 for the execution of electrical work at the Regional Labour Institute at Sector- 47, Faridabad, Haryana. The tender was awarded to the respondent under a letter of award dated 18.08.2005. The contractual value of the work was Rs.24,91,256/-, and the period for completion of work was stipulated as nine months, calculated from the 22nd day after the award of the work, i.e., 10.09.2005 to 10.06.2006. UoI issued a letter of commencement to the respondent on 02.08.2005. The time for completion of the work was extended on 09.06.2006 until 10.08.2006, and again on 07.08.2006 until 09.10.2006. The work was ultimately co
K.N. Sathyapalan v. State of Kerala and Anr.
The court upheld the arbitrator's award, affirming that delays were attributable to the petitioner, justifying the respondent's claims for additional expenses.
The judicial review under Section 34 of the Arbitration and Conciliation Act is restricted to issues of patent illegality, ensuring that arbitrator's findings are not disturbed unless they fundamenta....
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
The court upheld the Arbitrator's findings that the rescission of the contract was unjust and delays were primarily attributable to the petitioner, affirming the award under Section 34 of the Arbitra....
Arbitration Agreement – Award -Scope of interference by the courts into the award is quite limited. A court considering an application under Section 30 of the Act neither sits in appeal over an award....
The court emphasized the requirement for the arbitrator to assign reasons in support of the award and the limited scope of interference by the court in arbitration awards.
The specified authority's decision on quantification of compensation for delay is final, but the responsibility for the delay is subject to arbitration. The court also emphasized the importance of ev....
The court upheld the arbitral tribunal's findings on delays caused by the Municipal Corporation but set aside the award for loss of profit due to insufficient evidence.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.