IN THE HIGH COURT AT CALCUTTA
I. P. Mukerji, Md. Nizamuddin, JJ.
Pam Developments Pvt. Ltd. – Petitioner
Versus
State of West Bengal & Anr. – Respondents
FMAT No. 376 of 2019, COT No. 54 of 2019
Decided On : 03-06-2021
Arbitration and Conciliation Act, 1996 – Section 37 – Interest Act, 1978 – Arbitrator – Counter claim – Award is for scrutiny – Nature of damages –Held, If claim for interest had to be made on escalation bills, appellant did not have any right, as a matter of course to claim interest – Proper notice under Interest Act, 1978 had to be served on respondent – There is nothing in the award to state when this notice was served if at all – Hence, this part of award is erroneous for lack of reasons and for missappreciation of the law which goes to root of matter, resulting in patent illegality – Learned arbitrator could only have granted interest for pendente lite period and post award interest in respect of this head of award and only post award interest for the award for claim No.2 – Disposed of.
JUDGMENT :
I. P. MUKERJI, J.
1. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 is the third round. The first round was before the learned arbitrator. He made and published an award on 30th January, 2018 for Rs.1,37,25,252/-in favour of the appellant dealing with their claims 1 to 5 together with interest and the counter claim of the respondent state. The second round was an application by the respondent under Section 34 of the said Act before the learned District Judge, Purba Medinipur, challenging the award. The learned District Judge by a detailed judgment and order dated 8th March, 2019 set aside the award for claims 1 and 2, and upheld the rest of the award. The third round is the appeal before us. The respondent has preferred a cross-objection.
2. Before us, on one hand, the award is for scrutiny. On the other hand, are the principles of law circumscribing the powers of the appeal court in interfering with the judgment of the court below made after a detailed scrutiny of the award.
3. A short background of the case is now necessary.
4. The agreement between the parties was made on 22nd December, 2010.
5. The work involved was widening and strengthening of 13 kms. of Egra, Bajkul Road (43 km – 30 km) in the Tamluk Highway division of Purba Medinipur district. The appellant was engaged by the respondent as a works contractor. They were to do this work in about one and a half years from 22nd December, 2010, the date of the work order. The date of completion of the work was 22nd June, 2012. It could not be completed in this period. Both the parties exchanged allegations against each other for the delay in the completion of the work. It was ultimately completed on 9th November, 2012. There was no formal extension of the time period for completion. More than six months after completion of the project, the appellant on 12th June, 2013 raised a bill for escalation.
6. In 20th May, 2016, the appellant invoked the arbitration clause. They made a total claim of Rs.4,71,16,939/-before the learned arbitrator which is more fully shown in the table below:
| Sl. No. | Particulars of Claim as described in the Statement of Claim | Claimed Amount [Rs.] |
| 1. | Loss of business | 80,84,649/- |
| 2. | Uneconomic Utilization of Plant and machinery | 1,67,40,000/- |
| 3. | Labour Charges for uneconomical and certain stoppage of work | 47,57,000/- |
| 4. | Interest on delay in payment of Running Account Bills and Escalation Bills 1,37,50,000/- |
|
| 5. | Escalation Bill | 37,85,290/- |
|
| Total | 4,71,16,939/- |
| 6. | Interest @18% p.a. on awarded sum |
|
| 7. | Cost |
|
7. There is no grievance of the appellant with regard to the payment of the consideration under the contract. In fact, the appellant has admitted in their written notes of argument that measurement of the work was taken by the respondent and payment made. There is a claim for interest for the delay in payment and for payments for extra works together with claims in the nature of damages.
8. Before the learned arbitrator the appellant made claims under several heads.
9. The first was captioned as “loss of business”. The claimed amount was Rs.80,84,649/-. The foundation for this claim was this. The value of work executed beyond the completion date was Rs.4,04,23,245/-. This amount became payable to them after five months, which was the overrun period. They were deprived of enjoying the “profit” that would have been earned had the work deem done and payment been made on time. This was estimated to be Rs.87,26,876/- applying a formula known as Hudson formula in building engineering contract.
10. The learned arbitrator in his award dated 30th January, 2018 went by a completely different route. Although not claimed by the appellant, he treated this claim as one for “off site expenses”. He ruled that 1.5% of the proportionate contract
Ssangyong Engineering & Construction Co. Ltd. vs. National Highways Authority of India (NHAI)
Municipal Corporation of Delhi vs. M/s. Jagan Nath Ashok Kumar and Anr.
Assam State Electricity Board & Ors. vs. Buildworth Private Limited
Associate Builders vs. Delhi Development Authority
Associated Construction vs. Pawanhans Helicopters Limited
General Manager, Northern Railway and Anr. Vs. Sarvesh Chopra
K. N. Sathyapalan (Dead) By Lrs. Vs. State Of Kerala & Anr.
Ssangyong Engineering & Construction Co. Ltd. vs. National Highways Authority of India (NHAI)
Sutlej Construction Limited vs. Union Territory of Chandigarh
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
An arbitrator's award may be upheld if it conforms to contract terms, despite challenges regarding procedural compliance or interpretation, provided it does not contravene public policy.
Grant of interest – Power of Arbitrator to award pre-reference and pendente lite interest is not restricted when agreement is silent on whether interest can be awarded or does not contain a specific ....
An arbitrator cannot exceed jurisdiction by awarding claims not supported by written approval as mandated by the contract, rendering the award illegal.
The appellate jurisdiction under section 37 is limited to the grounds prescribed under section 34. Courts cannot re-appreciate evidence or substitute their views for that of the arbitrator, provided ....
Arbitration Agreement – Award -Scope of interference by the courts into the award is quite limited. A court considering an application under Section 30 of the Act neither sits in appeal over an award....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.