IN THE HIGH COURT OF DELHI AT NEW DELHI
RAVINDER DUDEJA, J.
Union Of India & Anr. - Petitioners
Versus
Sudhir Tyagi - Respondent
CM(M) 4025 of 2024
Decided on : 17-04-2025
| Table of Content |
|---|
| 1. nature of the issue before the court. (Para 1 , 2) |
| 2. factual background of the arbitration case. (Para 3 , 4 , 5) |
| 3. execution of the arbitral award. (Para 6 , 7 , 8) |
| 4. interpretation of post-award interest provisions. (Para 11 , 17) |
| 5. judicial precedents on post-award interest. (Para 19 , 20 , 21) |
| 6. mandatory nature of post-award interest. (Para 22 , 23) |
| 7. conclusion and result of the case. (Para 24 , 25) |
JUDGMENT :
RAVINDER DUDEJA, J.
1. This petition under Article 227 of the Constitution of India impugns the order dated 25.10.2024, passed by the learned District Judge in Ex. 55/2017, titled “ Sudhir Tyagi Vs. Union of India .”
2. At the core, the issue is whether the expression “unless the award otherwise directs” in Section 31 (7)(b) of the Arbitration & Conciliation Act, 1996 [“the Act”], relates to rate of interest and not entitlement of interest.
3. Shorn of all the unnecessary details, the relevant facts are that petitioner No. 1 i.e., Northern Railway, awarded contractual work to the respondent, but due to certain disputes, respondent invoked the arbitration clause of the agreement. The High Court, vide order dated 16.11.2012, appointed a sole arbitrator.
4. Following three issues were raised and considered by the learned Arbitrator:-
i) Is the time essence of the contract between the parties or not?
ii) Whether the respondent imposed any penalty/liquidated damages upon the complainant till the completion of work?
iii) Whether the complainant is entitled to claim amounts as per the claim petition?
5. Issues No. 1 & 2 were decided in favour of the respondent and against the petitioners. The findings of learned Sole Arbitrator on Issue No. 3 are extracted herein below:-
“Respondent shall pay a sum of Rs. 61,48,277/- (Rs. Sixty One Lakhs, forty eight thousand, two hundred and Seventy Seven with interest on sum of Rs. 10,84,385/- @ 10% per annum w.e.f. 18.01.2005 till payment as per following break-up:-
| (a) Rs. 10,84,285/- | allowed with interest @ 10% Per annum w.e.f. 18.01.2005 till the date of realization/payment as against claim No. 1 & 8 (Consolidated); |
| (b) Rs. 46,83,892/- | Allowed against claim No. 2,3,4 & 5 |
| (c) Rs. 50,000/- | Allowed against claim No. 7 |
| (d) Rs. 3,50,000/- | Allowed against claim No. 9 |
| Total Rs.61,48,277.00 |
The award is made as above.”
6. Petitioner filed an Objection Petition under Section 34 of the Act before the learned District Judge against the aforesaid Arbitral Award. The petition was dismissed by the learned District Judge. Petitioners then preferred an appeal (FAO 158/2024) before this Court against the order dated 07.07.2023, passed by the learned District Judge.
7. In the meanwhile, respondent filed an Execution Petition bearing Ex. No. 55/2017 for the execution of the arbitral award dated 13.10.2015. Petitioners made complete payment of Rs. 82,86,547.62 to the respondent as per award dated 13.10.2015. However, respondent filed an application under Section 151 CPC on 20.09.2024, praying inter alia,:-
“6. Hence it is prayed that Decree Holder is entitled to Rs. 77,1800/- (Seventy Seven lacs & eighteen thousand) on Rs. 46,83,892/- from 13.10.2015 to 25.08.2024 as on 25.08.2024, Since Ld. Arbitrator did not direct post award interest on Rs. 46,83,892/- on claim No. 2,3,4 & 5.”
8. The learned executing court passed the impugned order that post-award interest at the rate of 18% per annum as per the mandate of Section 31 (7)(b) of the Act would be payable and accordingly directed the petitioners/JD to make payment of Rs. 77,18,000/- within two months. This order was passed by the learned executing court while relying upon the decision of the Supreme Court in the case of R.P. Garg Vs. The Chief General Manager, Telecom Department and Ors. Civil Appeal No. 10472/224
9. The award in this case was passed on 25.10.2024. Section 31 of the 1996 Act deals with form and contents of the arbitral award. Section 31 has eight Sub Sections. Sub Section (7) is relevant for the purpose for decision in this case. S
Arbitral awards inherently carry a statutory interest rate of 18% for post-award periods, ensuring prompt compliance regardless of parties' prior decisions.
Arbitrator has discretion to grant post-award interest – If Arbitrator does not grant post-award interest, award holder is entitled to post-award interest at eighteen percent.
Post award interest – Granting post-award interest is not subject to contract between parties – Rate of interest can be provided by Arbitrator and in default statutory prescription will apply.
The Arbitral Award holds primacy in determining post-award interest, and interest on costs is to be granted by the Arbitral Tribunal.
Arbitral Tribunal's power to grant interest for the period post award till realization is subject to the discretion only in respect to the rate as it is the mandate of the law to grant such interest ....
An arbitral award's stipulations on interest must be strictly enforced as per the parties' agreement, disallowing claims for compound interest unless explicitly provided, reinforcing party autonomy i....
Arbitral Awards prevail over statutory default provisions regarding interest unless explicitly stated otherwise in the Award.
The Arbitral Tribunal's authority to award interest is governed by the arbitration agreement, with specific provisions for pre-award and post-award interest under the Arbitration Act.
(1) Interest has to be awarded as specified in contract and in absence of any contract, as per discretion of Arbitral Tribunal - Arbitral Tribunal can grant pre-reference interest from date on which ....
The court clarified that post-award interest includes both principal and pre-award interest, overruling previous decisions that restricted such calculations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.