SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 60

IN THE HIGH COURT OF DELHI AT NEW DELHI
PURUSHAINDRA KUMAR KAURAV, J.
Ntpc Ltd Through Its Authorised Representative Mr. Salil Kumar Pandey - Appellant
Versus
Ampl Resources Private Limited (Erstwhile Ambey Mining Private Limited) Through Its Directors / Authorized Representative – Respondent 
O.M.P. (COMM) 186 of 2025, I.A. 12141 of 2025&I.A. 12142 of 2025
Decided On : 26-02-2026

Advocates Appeared:
For the Appellant : Mr. Adarsh Tripathi, Mr. Vikram Singh Baid and Mr. Ajitesh Garg, Advs.
For the Respondent: Mr. Udayan Jain, Ms. Kajal Sharma, Mr. Ranjan Mishra, Mr. Harsh Jaiswal, Ms. Amiti Gupta, Ms. Geetika Vyas, and Mr. Sonal Jain, Advs.

The non-breaching party is entitled to damages that place them in a position as if the contract had been performed, with the awarded loss of profits upheld based on reasonable calculations.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 31(7) - Enforcement of arbitral award - Disputes regarding contractual terms and claims for damages - Court upheld sole arbitrator's decision finding breach of contract and determining loss of profits at 15% based on contract value; claims for fixed costs and expenses rejected as non-additional - Award deemed neither perverse nor illegal despite objections. (Paras 40, 51)

(B) Contract Law - Principles of damages - Non-breaching party entitled to be placed in the same position as if contract performed; evidence considered for calculating loss of profits; deviation clauses ruled. (Paras 135, 170)

Facts of the case:
The claimant was awarded a contract for coal transportation but claimed dues when the respondent suspended operations citing lower coal requirements. The sole arbitrator allowed partial claims for loss of profits and retention money while dismissing claims for fixed costs.

Findings of Court:
The sole arbitrator found that the contract allowed for a fixed quantity of coal despite deviations and correctly ruled on losses due to breach, rejecting claims for fixed costs as part of the contractual obligations.

Issues: Whether the awarded damages for loss of profits were justified, and whether the rejection of claims for fixed costs was perverse.

Ratio Decidendi: The court confirmed the arbitrator's findings, emphasizing that damages should reflect the contractual expectations without speculative deviations and that the contract's interpretation assured the earnings expected from its execution.

Result: Petitions dismissed, award upheld.

Table of Content
1. factual background of the case (Para 1 , 2 , 3 , 4 , 5)
2. determining breach of contract (Para 6 , 8 , 10)
3. legal evaluations of claims and defenses (Para 7 , 14 , 15 , 16 , 18)
4. claims for costs and legal expenses (Para 11 , 12 , 20 , 21)
5. final adjudication and dismissal of petitions (Para 49 , 51 , 52)

JUDGMENT :

PURUSHAINDRA KUMAR KAURAV, J.

The present set of petitions has been filed both by the claimant as well as the respondent against the award dated 19.12.2024 (hereinafter referred to as the “impugned award”). The claimant, AMPL Resources Private Limited (hereinafter referred to as “petitioner”) is the petitioner in OMP (COMM) 240/2025 and the respondent, NTPC Limited (hereinafter referred to as the “respondent”), is the petitioner in OMP (COMM) 186/2025. The petitioner had instituted arbitration proceedings against the respondent seeking recovery of money allegedly due under Contract dated 17.12.2019 (hereinafter referred to as “the Contract”). In the impugned award, the claim of the petitioner has been partly allowed and the petitioner seeks severance and setting aside of the part rejecting its claim and award of the full claim in its favour. The respondent seeks that the award be set aside in toto.

Facts

2. The petitioner was awarded the Contract for coal transportation from a designated mine to designated railway sidings for a period of one year with effect from 26.11.2019, which was extendable for a further period of six months. The terms of the Contract were contained in the General Conditions of Contract (hereinafter referred to as the “GCC”), Special Conditions of Contract (hereinafter referred to as the “SCC”), the Technical specifications and drawings, Schedule of Quantities, Contractor's Bid Proposal No. 50727, and the Purchase Order dated 18.11.2019 (hereinafter referred to as the “Purchase Order”), among other documents. Under the terms thereof, the respondent would provide monthly schedules to the petitioner, specifying the quantity of coal to be transported.

3. After commencement of the work at the scheduled time, the respondent, vide letter dated 13.04.2020, citing lower coal requirements, directed the petitioner to suspend transportation till further notice. The petitioner, thereafter, on various dates, claimed dues under various heads. The respondent, in its letter dated 04.12.2020, refuted the claims, stating that the Contract stipulated payment only according to the quantity of coal which is transported, and therefore, the petitioner's claim for the whole contract was not acceptable. Disputes persisted with regard to the petitioner's claims, leading to the institution of arbitral proceedings.

4. In the arbitral proceedings, the petitioner sought recovery of its purported dues (principal amount) as per the table extracted below:

5. The claims for loss of profit and retention money dues were allowed, and the claims for fixed office expenses and fixed costs were rejected.

Findings in the Impugned Award

6. The following points for determination were framed by the sole arbitrator:

1. Whether the Claimant is entitled to the outstanding principal amount in the sum of Rs. 24,20,55,520.00?

2. Whether the claimant is entitled to interest on the outstanding principal @12% per annum up to 31.03.2023 in the sum of Rs. 6,77,22,492.00?

3. Whether the Claimant is entitled to pendente lite and future interest @12% p.a. on the allowed outstanding principal and interest amounts cumulatively?

4. Whether the Claimant is entitled to the legal expenses as per actuals?

7. One of the questions framed by the sole-arbitrator for adjudicating the claim for the outstanding principal amount, which also has a bearing on the claim for interest on the principal amount, was whether the contract envisaged the transportation of a fixed quantity of coal.

8. The sole-arbitrator has examined the relevant clauses and recitals in the Contract, more particularly, the Bill of Quantity forming a part of the Letter of Intent, the Bill o

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top