SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 194

IN THE HIGH COURT OF DELHI AT NEW DELHI
JASMEET SINGH, J.
Dalmia Cement (Bharat) Limited – Appellant
Versus
M/s ESS ESS Technofabs Private Limited – Respondent
Arb. Pet. Nos. 1723, 1725 of 2024
Decided On : 07-02-2026

Advocates Appeared:
For the Appellants : Anirudh Bakhru, Niyati Kohli, PrathaVir Agarwal, Shubhi Agarwal
For the Respondents: Varun Bedi, Swati Ahalwat

The court upheld that statutory remedies under the MSMED Act take precedence over private arbitration agreements, affirming the Facilitation Council’s jurisdiction in disputes involving MSMEs.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11 - Micro, Small and Medium Enterprises Development Act, 2006 - Sections 18 and 24 - Applicability of statutory remedies - Petitioners sought to appoint a Sole Arbitrator for disputes arising from work orders; however, the MSMED Act’s jurisdiction was upheld, establishing that statutory proceedings take precedence over private arbitration agreements. (Paras 1, 18, 35, 47)

(B) Jurisdiction - The High Court found that the MSMED Act governs disputes between specific parties and that facilitation councils have jurisdiction over these issues. (Paras 30, 46)

(C) Prior registration as MSME - The respondent was held to be a registered MSME at the time of contract execution; hence, the statutory provisions of the MSMED Act were applicable. (Paras 48, 50)

Facts of the case:
The appellant, a cement manufacturer, engaged the respondent to provide services for various projects, which led to disputes when the latter failed to meet deadlines. The respondent initiated claims under the MSMED Act, which the petitioner disputed, asserting jurisdictional challenges.

Findings of Court:
The court confirmed that jurisdiction under MSMED Act is mandatory and overrides previous arbitration agreements.

Issues: Key issues included the authority of the Facilitation Council to adjudicate on matters involving works contracts and whether jurisdiction could be challenged after arbitration had commenced.

Ratio Decidendi: The High Court reasoned that the MSMED Act establishes a special process for disputes arising from its provisions, taking precedence over the Arbitration and Conciliation Act.

Result: Petitions disposed with directions to adhere to statutory remedies under the MSMED Act.

Table of Content
1. jurisdictional basis of arbitration disputes. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10)
2. petitioner's arguments against facilitation council's jurisdiction. (Para 17 , 18 , 19 , 20 , 21 , 22)
3. respondent's counterarguments regarding jurisdiction. (Para 23 , 24 , 25 , 26 , 27 , 28)
4. court's preliminary observations on maintainability. (Para 29 , 30 , 31 , 32 , 33)
5. supremacy of msmed act over arbitration act. (Para 34 , 35 , 36 , 37 , 38 , 39)
6. court's determination on statutory remedies and jurisdiction. (Para 40 , 41 , 42)
7. court's refusal to adjudicate pending issues before msme. (Para 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51)
8. final conclusion and dismissal of petitions. (Para 52 , 53)

JUDGMENT :

JASMEET SINGH, J.

1. These are petitions filed under Section 11 of the Arbitration and Conciliation Act, 1996, (“the Act”) arising out of the work order/purchase order dated 11.10.2020 and 04.11.2020, respectively, seeking appointment of a Sole Arbitrator to adjudicate disputes between the parties.

FACTUAL MATRIX AS PER THE PETITIONER

2. The petitioner, namely Dalmia Cements (Bharat) Limited is a public company engaged in the business of manufacturing and selling of cement and other allied products.

3. The respondent, namely M/S Ess Ess Technofabs Private Limited is engaged in the business of Manufacturing and installation of fabricated metal products.

4. In the year 2020, the petitioner engaged the respondent for providing material and services for mechanical fabrication and erection job of two projects, namely AFR feeding system and clinker silo at its DDSPL unit based in Rohtas, Bihar (“Project 1”) and the installation of cooler at Rajgangpur unit, Odisha (“Project 2”) respectively.

5. As regards with the project 1, the letter of indent was issued on 15.09.2020 and subsequently the petitioner issued a work order/purchase order dated 11.10.2020.

6. As regards with the project 2, the Letter of Indent was issued on 30.10.2020 and subsequently the petitioner issued a work order/purchase order dated 04.11.2020.

7. The aforesaid said work order/purchase order contained an arbitration clause being Clause No. 28 of the general terms and conditions of the work order/purchase order.

8. The nature of purported disputes in both these petitions are similar, hence are being dealt, together. It is the case of the petitioner that the respondent failed to execute the work within the time schedule and the petitioner had to engage the third party contractors for completion of the projects.

9. Subsequently, the respondent sent two demand notices dated 06.01.2023 and 10.01.2023, making demands of Rs. 61,65,000/- and Rs. 87,00,000/- along with interest, respectively.

10. In view of the disputes between the parties, on 04.08.2023 the respondent filed reference under Section 17 and 18 of the Micro, Small and Medium Enterprise Development Act, 2006 (“the MSMED Act”) relating to the both the claims before the District Micro & Small Enterprises Facilitation Council, Mohali, Punjab (“the Facilitation Council”) for an amount of Rs. 1,01,65,000/- along with interest with respect to the project 1 and Rs.87,00,000/- along with interest, with respect to the project 2.

11. The petitioner disputed the jurisdiction of the Facilitation Council by raising a preliminary objection and also filing an application under section 16 of the Act on 14.12.2023.

12. The petitioner then proceeded to file its Statement of Defence (“SOD”) on merits, it was filed without prejudice to the objections raised under Section 16 application.

13. In view of the disputes between the parties, the petitioner invoked the dispute resolution clause i.e. Clause No. 28 of the general terms and conditions of the work/purchase order by sending a notice invoking arbitration under Section 21 of the Act dated 12.01.2024.

14. On 30.04.2024, the petitioner also filed its evidence before the Facilitation Council. However, on 08.07.2024 the petitioner filed writ petitions being CWP

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top