SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Telangana) 2262

IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
APARESH KUMAR SINGH, C.J.
Vishwa Samudra Engineering Pvt. Ltd., Telangana, India – Petitioner 
Versus 
Aeon Infratel Pvt. Ltd., Jammu and Kashmir, India – Respondent 
Arbitration Application No.55 of 2025
Decided On : 31-10-2025

Advocates Appeared:
For the Petitioner: Rajeev Rambhatla rep. (Ms.) Sirnapelly Pooja.
For the Respondent: K. Keertivardhan Reddy.

The MSMED Act operates as a special beneficial legislation, overriding the Arbitration Act in cases involving registered MSMEs, emphasizing exclusive jurisdiction of MSEFC for dispute resolution.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 8 - Micro, Small and Medium Enterprises Development Act, 2006 - Preliminary objections raised concerning the jurisdiction of different forums on the same contract - Arbitral proceedings can be delayed by invoking the jurisdiction of the MSEFC - Special legislation (MSMED Act) prevails over general legislation (Arbitration Act) due to its non-obstante clause. (Paras 12, 13, 16)

(B) The nature of a works contract is distinct and composite, involving both supply of goods and services - Decisions from the Hon’ble Supreme Court clarify that the provisions of the MSMED Act are beneficial and should be liberally interpreted - The Arbitration Act is more general and should yield to the specific provisions in the MSMED Act. (Paras 6, 8, 10)

Facts of the case:
Dispute arose from a Sub-Contractor Agreement dated 04.06.2022 over a construction project, with an arbitration clause present. Despite notices invoking arbitration, the respondent pursued claims through the MSEFC.

Findings of Court:
The Court ruled that given the nature of the contract and existing proceedings under the MSMED Act, the dispute should be adjudicated by the MSEFC and not through arbitration.

Issues: Whether the existence of an arbitral agreement excludes the MSEFC from adjudicating the dispute arising from a works contract.

Ratio Decidendi: The MSEFC is deemed as the appropriate forum under the MSMED Act for resolving disputes involving MSMEs, emphasizing the precedence of special legislation over general law.

Result: Application dismissed.

Table of Content
1. existence of arbitration clause and msefc proceedings. (Para 2 , 4)
2. arguments for and against the appropriate forum for dispute resolution. (Para 5 , 6 , 8)
3. court's findings on jurisdiction and prevailing legislation. (Para 10 , 12 , 13)
4. court’s ruling and decision on the application. (Para 16 , 17)

ORDER :

APARESH KUMAR SINGH, C.J.

Heard Mr. Rajeev Rambhatla, learned counsel representing Ms. Sirnapelly Pooja, learned counsel for the applicant and Mr. K.Keertivardhan Reddy, learned counsel for the respondent.

2. The main issue in the present application is not on the existence of the agreement between the parties or the existence of the dispute between the parties, but the forum before which the dispute can be adjudicated. Applicant is the first party under a Sub-Contractor Agreement dated 04.06.2022, which contains an arbitration clause 49, which is also not disputed by the respondent. The issue, as observed hereinabove, is whether the Micro & Small Enterprises Facilitation Council, Jammu (hereinafter referred to as ‘MSEFC’) would be the proper forum or an independent arbitrator appointed by this Court would be the forum where the dispute between the parties is to be adjudicated. Respondent admittedly is a Micro, Small and Medium Enterprise (hereinafter referred to as “MSME”) registered with the MSEFC, Jammu, on 27.04.2020 under the erstwhile “MSME UDYOG AADHAAR” system, whose registration was further renewed with effect from 15.07.2022 under the new “MSME UDYAM” process. The Sub-Contractor Agreement was entered between the parties on 04.06.2022. In respect of the disputes between the parties, the respondent approached the learned Court of Munsiff, Samba, for perpetual injunction in which the applicant appeared and filed an application under Section 8 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act of 1996”). By order dated 18.09.2024, the learned Court of Munsiff, Samba, accepted the objection of the applicant and disposed of the matter, as the agreement between the parties provided for arbitration clause. Thereafter, the respondent initiated proceedings under the Micro, Small and Medium Enterprises Development Act, 2006 (hereinafter referred to as ‘the MSMED Act’) before the MSEFC on 01.02.2025. On 15.02.2025, the respondent submitted hard copies of documents relating to the claims in response to the MSEFC’s requisition. The present applicant issued notice invoking arbitration clause through Registered Post on 17.02.2025, which returned due to “insufficient address”. Thereafter, on 25.02.2025, the applicant sent an e-mail notice to the respondent invoking arbitration clause. On 04.03.2025, the MSEFC issued notice to the applicant. The present arbitration application was filed on 13.03.2025 by the applicant wherein there was no mention of the proceedings before the MSEFC. Applicant also replied to the notice dated 04.03.2025 from the MSEFC on 17.03.2025 after filing of the arbitration application.

3. In the present arbitration application, counter affidavit was filed by the respondent on 12.06.2025. Rejoinder thereto has been filed on 20.06.2025.

4. On the part of the applicant, the following plea has been taken. That parties entered into a Sub-Contractor Agreement on 04.06.2022 for shifting of electrical utilities (including distribution and transmission) and water pipeline utilities in relation to the project titled “Construction of four/six lane access-controlled expressway from Gurha Baildaran to Junction with Jammu Ring Road (NH 244A) near Jakh village (468+100 km to 503+250) of Delhi Amritsar Katra Expressway”. The agreement was executed on an item rate contract basis, with the rates being based on the cost data of the Utility-owning department prevailing at the time of the agreement’s execution. Despite multiple extensions by the applicant in good faith, respondent failed to complete the work within stipulated timeframe of six months from the date of agreement i.e.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top