2026 Supreme(Del) 1204
2026 DHC 8409
IN THE HIGH COURT OF DELHI AT NEW DELHI
MINI PUSHKARNA, J.
M/S. Dwarika Projects Ltd. – Petitioner
Versus
New Okhla Industrial Development Authority – Respondent
O.M.P. (COMM) 182 of 2019
Decided On : 28-09-2026
Advocates Appeared :
For the Petitioner : Mr. Abhishek Mohanty and Mr. Ansh Kajauria, Advocates
For the Respondent : Mr. Sourav Roy, Mr. Anshu Deshpande, Mr. Hemant Gupta, Advocates
Important Points
Subject
Civil Law - Arbitration
Act Referred
Headnote
(B) Contractual Interpretation - Price Variation - Original Contract Period - A finding that rates in the Bill of Quantities hold good without considering the qualifying phrase "barring adjustment (which may be plus or minus) to be made as provided for herein" in the Special Conditions of Contract constitutes an incomplete reading of the contract and is patently illegal. (Para 27-33)
(C) Contractual Interpretation - Price Variation - Extended Contract Period - Where the contract expressly provides for a specific method of calculating price variation for delays attributable to the contractor, treating such delay as a complete bar to entitlement is an error that amounts to rewriting the contract and is patently illegal. (Para 40-45)
(D) Arbitral Award - Finding on Delay - If the Arbitrator's finding regarding the attribution of delay is based on a plausible view of the evidence and documents on record, the Court shall not interfere under Section 34 even if another view is possible. (Para 57, 66)
Issues: Whether the Arbitral Award rejecting the claim for price variation for both original and extended contract periods was patently illegal and whether the findings on the attribution of delay were perverse.
For the Appellants/Petitioners: Abhishek Mohanty, Ansh Kajauria
For the Respondents: Sourav Roy, Anshu Deshpande, Hemant Gupta
JUDGMENT :
MINI PUSHKARNA, J.
INTRODUCTION
1. The present petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”), seeking partial setting aside of the Arbitral Award dated 10th December, 2018 (“Award”), passed by the Sole Arbitrator in the arbitral proceedings, bearing Arbitration Case No. 14/2017, titled as M/s. Dwarika Projects Ltd. Versus New Okhla Industrial Development Authority and Anr.
2. By way of the impugned Award dated 10th December, 2018, the Sole Arbitrator, held the petitioner entitled to Claim no. 1 for Rs. 75,11,727/- as well as Claim no. 3 for Rs. 18,93,296/-. Claim no. 2 was also partly allowed in favour of the petitioner for Rs. 8,90,033/-, thereby, bringing the total amount awarded in favour of the petitioner to Rs. 1,02,95,056/-. The respondent was held entitled to deduct the taxes paid or payable by it on Claim no. 1, after giving proof of the same to the petitioner.
3. The petitioner has been further held to be entitled to pre-arbitration interest from 16th May, 2012, to 21st August, 2017, and interest during the arbitral proceedings up to 10th December, 2018, both at the interest rate of 12% compounded annually. Further, the petitioner has also been held entitled to interest under Section 31(7)(b) of the Arbitration Act at 2% higher than the current rate of interest prevalent on the date of the Award up to the date of payment. The petitioner has also been awarded Rs. 12,36,025/-as costs of arbitral proceedings.
4. Claim nos. 4 to 10, as raised by the petitioner, were rejected.
FACTUAL BACKGROUND
5. The facts relevant for adjudication of the present petition, as culled out from the impugned Award and the pleadings on record, are as under:
5.1 The petitioner, i.e., M/s. Dwarika Projects Ltd., is a company incorporated under the Companies Act, 2013, and is engaged, inter alia, in the business of construction of roads and bridges. The respondent, i.e., New Okhla Industrial Development Authority, is a statutory authority responsible for the development and planning of Noida, Uttar Pradesh.
5.2 The respondent floated a tender for “Construction of Bridge No. 2 on Irrigation Drain between Sector-78 & 49, Noida”, in respect of which the petitioner made a bid, thereby, offering rates 18.80% below the quoted rate.
5.3 The respondent awarded the tender to the petitioner and issued a Letter of Acceptance dated 27th November, 2009, for works amounting to Rs. 18,09,47,233.04/-.
5.4 Thereafter, a Contract Agreement dated 07th December, 2009, was executed between the parties for “Construction of Bridge No. 2 on Irrigation Drain between Sector-78 & 49, Noida” (“Contract”).
5.5 The construction work was to be completed within a period of twelve (12) months, i.e., by 06th December, 2010, but was completed considerably beyond the said date, with each party attributing the delay to the other.
5.6 Disputes having arisen between the parties in relation to the delayed completion of the work and non-payment of the final bill bearing no. 18 dated 18th August, 2017 (“Final Bill”), the petitioner sought arbitration under Clause 34 of the General Conditions of Contract (“GCC”).
5.7 As the respondent failed to act upon the petitioner’s request for appointment of an Arbitrator, the petitioner approached the High Court of Judicature at Allahabad by way of Arbitration and Conciliation Application No. 108/2015.
5.8 The said High Court, vide order dated 21st August, 2017, sought consent of the proposed Sole Arbitrator, and having received the same, allowed the petitioner’s application on 18th September, 2017.
5.9 Before the Sole Arbitrator, the petitioner filed a Statement of Claim dated 25th October, 2017, seeking twelve (12) claims, whereas, the respondent filed a Reply dated 23rd December, 2017, seeking three (3)counter-claims.
5.10 Vide order dated 25th September, 2017, the learned Arbitrator recorded that the place of arbitration shall be at New Delhi as agreed between the parties, and informed by le