NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Subhash Chandra, Presiding Member
Anant Ram and Anr. —Complainants
versus
Cloud 9 Projects Pvt. Ltd. —Opp. Party
Consumer Case No.2058 of 2016
Decided on 29.9.2022
Consumer Protection Act, 1986—S.21[Consumer Protection Act, 2019—S.58] - Services – Real Estate – Allotment of Flat – Delayed Possession – Right to get compensated for Delayed possession - Compliant has been filed for seeking possession or in the alternative, refund of the amount deposited along with penal interest and other compensation in respect of the flat booked by them with the opposite party - The right of the consumer to be compensated for inordinate delay in the offer of possession of a residential apartment booked by them due to inordinate delays by builders when the complainants are bonafide consumers who have duly paid the instalments and waited for the promise of allotment to fructify. In the instant case, as possession has already been handed over and taken on the payment of all charges and the sale deed registered - Admittedly, the opposite party had indicated a period of 39 months with a 3 month period of grace from the date of the Agreement (09.04.2010), i.e. 10.06.2013. Possession was, however, not offered till 19.12.2018. The intervening period of 5 years and 6 months is not a short period and the complainant is justified in seeking compensation for the same – Therefore, consumer complaints stand disposed of. [Paras 11 to 14]
Result: Complaint disposed off.
ORDER
Subhash Chandra, Presiding Member—This complaint has been filed under Section 21 of the Consumer Protection Act, 1986 (in short, the ‘Act’) is filed by the complainants alleging deficiency in service and unfair trade practice on account of deficiency in service and unfair trade practices, seeking possession or in the alternative, refund of the amount deposited along with penal interest and other compensation in respect of the flat booked by them with the opposite party viz., M/s Cloud 9 Projects Pvt. Ltd., in a project promoted and developed by it.
2. Briefly, the facts of the case are that the complainants had booked a flat in a residential Group Housing project “Lotus Boulevard – Espacia Housing Project” (in short, ‘project’) promoted and developed by the Opposite party located at Sector 100, Noida, Uttar Pradesh for their residential purpose. The booking was originally in the name of their son (‘Original Allottee’) on 24.12.2009. An offer of allotment letter was issued by the opposite party to the original allottee on 10.03.2010 allotting apartment no. 1402 in Tower 37, admeasuring 237.83 sq ft for a total sale consideration of Rs.93,88,600/-. As per clause 5.1 of the Agreement, possession was promised to be given in 39 months with three months of grace i.e. by 10.06.2013.
3. Despite the complainants having regularly paid the instalments in time, there was inordinate delay on the part of the opposite party in handing over possession despite several efforts to contact him and the raising of various demands for payments. Dates promising possession was indicated from time to time which were not adhered to by the opposite party. The complainants finally approached this Commission on 11.11.2016 by of this complaint seeking the following relief:—
(a) Hold and declare that the opposite party guilty of following unfair trade practices and restrain them from following such activities;
(b) Direct the opposite party to immediately hand over the possession of the apartment worth Rs.93,88,600/- to the complainants on payment of the final instalment amount;
in the alternative
Direct the opposite party to pay the entire amount of Rs.90,68,300/- along with interest to be calculated from the respective date of deposits at the rate of 18% per annum;
(c) Direct the opposite party to pay interest at the rate of 18% per annum on account of delay, calculated from the due date, i.e., 10.06.2013 on the amount of Rs.90,68,300/- already paid by the complainants, till the time the possession of the apartment is handed over to the complainants;
(d) Direct the opposite party to pay delay charges of approximately Rs.9,66,400/- calculated upto 09.10.2016 in terms of clause 5.5 of the agreement for the delay caused in the completing the construction and handing over the peaceful and vacant possession of the apartment and to pay the delay charges at the rate of Rs.25,600/- per month for further delay post 09.10.2016 upto the actual handing over of the possession of the apartment;
(e) Direct the opposite party to give possession of the apartment without any enhanced additional charges for the increased area, that were not agreed between the parties and charge only for the agreed upon area of 2560 sq ft; and
(f) Any other order which this court may deem fit in the interest of justice and equity.
4. The opposite party contested the complaint by way of reply and evidence by way of affidavit. The opposite party in his reply stated that the complainants were not ‘consumers’ under the purview of section 2(g), that the complaint was without pecuniary jurisdiction, several allottees including complainants defaulted in making payments and that the delay was largely due to reasons not attributable to the opposite party, in view of (a) shortage of manpower and construction material due to Commonwealth Games, (b) National Green Tribunal’s order dated 11.01.2013 which injuncted builders from extracting ground water for construction purposes resulting in h
Pioneer Urban Land and Infrastructure Ltd. vs. Govindan Raghavan
Kavita Ahuja vs. Shipra Estates
Ambarish Kumar Shukla and Ors. vs. Ferrous Infrastructure Pvt. Ltd.
Right to Compensation - The right of the consumer to be compensated for inordinate delay in the offer of possession of a residential apartment booked by them due to inordinate delays by builders when....
(1) Delay - the construction of a residential apartment constitutes a ‘service’ and that the delay in not adhering to the indicated time schedule constitutes deficiency in service.(2) Refund – the de....
Installment – Once the instalments were collected, the buyers are sought to be non-suited on a multitude of grounds, primarily the liability of the Government in not providing infrastructure and to c....
Unreasonable Delay - In a case of an unreasonable delay in offering possession, a buyer cannot be compelled to accept possession at a belated stage and is entitled to seek refund of the amount paid w....
The court held that the delay in possession does not constitute a deficiency in service, provided the developer adheres to the agreed timeline including permissible grace periods.
Delay in delivery of possession constitutes unfair trade practice under the Consumer Protection Act.
Right to claim refund - the complainant in the present circumstances have a legitimate right to claim refund alongwith fair delay compensation/interest from the OP.
(1) Bald assertion – In the absence of any evidence being brought on record, merely a bald assertion that the project was delayed due to in action by the Government or its statutory organisations and....
Delays in possession of real estate mandate full refund to consumers under the Consumer Protection Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.