IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
A.S. Supehia, J.
Delta Rubber And Plastic Products – Appellant
Versus
Divya Exports Pvt. Ltd. & 1 Others – Respondents
R/First Appeal No. 761 Of 2002
Decided On : 11-10-2022
Retained Amount - Contract Dispute - State Financial Corporation Act - Section 29, Order XXXVII Rule 3(b) of the CPC - Article-II Payment terms - Exh.35, Exh.58
Fact of the Case:
The appellant appealed the dismissal of the Summery Suit No.7031 of 1991, claiming the remaining amount of Rs.1,50,815 from defendant No.2. The appellant argued that the Trial Court did not appreciate the communication/contract dated 20.04.1990 and the agreement between the plaintiff and defendant No.1, which contained clauses regarding the supply of machinery and payment of amount.
Finding of the Court:
The Court found that the suit was already decreed in favor of the plaintiff against defendant No.1, and the issue of the plaintiff's inability to execute the decree against defendant No.1 could not be addressed in the appeal proceedings. The Court also noted that the defendant No.2 had taken possession of the plant and machinery under Section 29 of the State Financial Corporation Act.
Issues: The issues included whether the plaintiff could pursue the suit against defendant No.2, and whether the commitment made to the plaintiff was for the entire amount of the consideration of the plant and machinery.
Ratio Decidendi: The Court held that the plaintiff failed to establish successful operation of the plant and machinery, and there was no privity of contract between the plaintiff and defendant No.2. The plaintiff could not claim the amount retained by defendant No.2 based on the commitment letter given by defendant No.2 on behalf of defendant No.1.
Final Decision: The appeal was dismissed, and the Court found no illegality or perversity in the impugned order.
JUDGMENT :
1. The appellant–original plaintiff has assailed the judgment and decree dated 26.07.2001 dismissing the Summery Suit No.7031 of 1991 passed by Court of City Civil Judge, (Court No.8) at Ahmedabad. It is the case of the appellant that the impugned judgment and decree is required to be quashed and set aside, since the same is passed without appreciation of the evidence.
2. Learned advocate Mr.Bhatt appearing for the appellant has submitted that the Court below had already decreed the suit in favour of the defendant No.1, by the judgment and decree dated 28.08.1992 by allowing the claim of the plaintiff against the defendant No.1 for a sum of Rs.5,19,833.20, however, so far as the amount of 10%, which has been retained by defendant No.2–Andhra Pradesh State Financial Corporation, the suit was continued further and ultimately, the same is rejected.
3. Learned advocate Mr.Bhatt has submitted that the plaintiff is entitled to claim the remaining amount of Rs.1,50,815/- from the defendant No.2, in view of the contract between the plaintiff and defendant Nos.1 and 2. It is submitted that the Trial Court has not appreciated the communication/contract dated 20.04.1990, below Exh.35, wherein it is recorded that the amount of Rs.9,66,400/- would be paid to the plaintiff in view of supply of machinery. It is submitted that the Trial Court has also not appreciated the agreement between the plaintiff and defendant No.1 at Exh.58, which contains various clauses with regard to supply of machinery and the payment of amount.
3.1 Learned advocate Mr.Bhatt has invited the attention of this Court to the deposition recorded below Exh.55 i.e. the employee of defendant No.2-Corporation, and has submitted that he had admitted that an amount of 10% was retained in view of the contract between the plaintiff and defendant No.1. It is submitted that 10% amount has been retained by the defendant No.2 on the ground that there was a defect in the machinery, which was supplied by the plaintiff to the defendant No.1. It is submitted that there was no evidence adduced by the defendant No.2, which would indicate that the machinery, which was supplied by the plaintiff to the defendant No.1 was suffering with any defect. It is submitted that no technical expert was examined and hence, the amount of 10% could not have been retained by the defendant No.2 and the same was required to be paid.
3.2 Learned advocate Mr.Bhatt has further submitted that at the time of the contract, the employee/officer of the defendant No.2–Corporation, who has entered the contract, was not examined and some other person, who has been examined below Exh.55 and hence, his evidence is required to be discarded to the effect that there was defect in the machinery, which was supplied by the plaintiff to the defendant No.2. Learned advocate Mr.Bhatt has submitted that even if it is assumed that there was no privity of contract between the plaintiff and defendant No.2–Corporation, however, from the evidence on record, it can be assumed that there was a contract between the plaintiff and defendant No.2.
3.3 Learned advocate Mr.Bhatt has thus submitted that 10% amount could not have been retained by the defendant No.2 on the pretext that the machinery, which was supplied by the plaintiff to the defendant No.2, was having any defect or the plant was not erected and the commissioning of plant was not done. It is submitted that in absence of any evidence, which would prove that the plant was not in operation to the satisfaction of the defendant No.1, the defendant no.2 cannot retain the amount. Learned advocate Mr.Bhatt has further submitted that the decree of payment against the defendant No.1, is not executed and hence, the plaintiff is entitled to recover the amount of 10% of the total amount, which is retained i.e. Rs.1,50,815/- by the defendant No.2 and hence, the impugned judgment and decree is required to be quashed and set aside.
4. In response to the aforesaid submissions, learned
AI
The main legal point established in the judgment is that in the absence of privity of contract, a party cannot claim a payment based on a commitment letter given by another party on behalf of a third....
Claim for damages will remain confined to what is expressly provided under Agreement.
(1) Summary suit (Money suit) – Generally, prayer for leave to defend is to be denied in such cases where defendant has practically no defence and is unable to give out even a semblance of triable is....
In a suit based on invoices, the invoices must be treated as a written contract. If the Defendant raises no genuine triable issues or the defense is frivolous, the Plaintiff shall be entitled to judg....
An arbitral award cannot be sustained if it is based on assumptions without concrete evidence, particularly in claims for damages or losses, as established under the Arbitration and Conciliation Act,....
The judgment established the principles of liquidated damages and reasonable compensation under the Indian Contract Act, 1872, and emphasized the importance of genuine triable issues in determining t....
A fully performed contract discharges all obligations, barring further claims unless legally warranted, as affirmed by prior judicial decisions and Supreme Court principles.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.