SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Guj) 63

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
SUNITA AGARWAL, ANIRUDDHA P. MAYEE, JJ.
M/s Sadbhav Engineering Limited – Appellant
Versus
Efftech Infra Engineers – Respondent
R/FIRST APPEAL NO. 4806 of 2023 With CIVIL APPLICATION (FOR STAY) NO. 1 of 2023 In R/FIRST APPEAL NO. 4806 of 2023
Decided on : 08-01-2024

Advocate Appeared:
For the Appellant :MR UNMESH SHUKLA, SR. COUNSEL, FOR THAKKAR AND PAHWA ADVOCATES
For the Respondent: MR SHALIN MEHTA, SR. COUNSEL, WITH MR SAURIN A MEHTA, WITH MR KRISHAL H PATEL

The main legal point established in the judgment is that the Court applied the principles of strong prima facie case and weighing the balance of convenience in favor of the respondent company in granting the interim measure under Section 9 of the Arbitration and Conciliation Act, 1996.

Headnote:

Attachment - Arbitration and Conciliation Act, 1996 - Section 9 - 9

Fact of the Case:

The appellant was directed to furnish a bank guarantee of Rs.29,61,159/- by the learned Commercial Court at City Civil Court, Ahmedabad in response to an application under Section 9 of the Arbitration and Conciliation Act, 1996 filed by the respondent company. The respondent company had completed the works as per the required standards and mutually finalized measures with the rates and schedules to the satisfaction of the appellant company. The appellant company did not make payment against the payment certificates without reasons, and the respondent company invoked Clause 12 of the work order requesting for settlement of the outstanding dues. The appellant company's financial condition was not sound, and there were 18 applications pending before the NCLT, Ahmedabad for initiating action under the Insolvency and Bankruptcy Code, 2016.

Finding of the Court:

The Court found that the respondent company had made out a prima facie case of pending dues of Rs.29,61,159/- recoverable from the appellant company and that the appellant company was not in a position to discharge its financial obligation. The Court also noted that the financial condition of the appellant company was not sound and there were 18 applications pending before the NCLT, Ahmedabad for initiating action under the Insolvency and Bankruptcy Code, 2016.

Issues: The issues revolved around the appellant's failure to make payment against the payment certificates issued to the respondent, the financial condition of the appellant company, and the respondent's application under Section 9 of the Arbitration and Conciliation Act, 1996.

Ratio Decidendi: The Court applied the principles of strong prima facie case and weighing the balance of convenience in favor of the respondent company. It found that the respondent had made out a prima facie case of pending dues and that the appellant was not in a position to discharge its financial obligation. The Court also considered the financial condition of the appellant company and the pending applications before the NCLT, Ahmedabad.

Final Decision: The First Appeal was dismissed, and the appellant was directed to furnish a bank guarantee of Rs.29,61,159/- in favor of the respondent company.

JUDGMENT :

1. Heard Mr. Unmesh Shukla, learned Senior Advocate appearing for Thakkar and Pahwa Advocates for the appellant and Mr. Shalin Mehta, learned Senior Advocate assisted by learned advocates Mr. Sauin A. Mehta and Mr. Krishal H. Patel for the defendant.

2. The present First Appeal impugns the judgment and order dated 27.10.2023 passed by the learned Commercial Court at City Civil Court, Ahmedabad in Commercial Civil Misc. Application No.171 of 2023 whereby the learned Court has allowed the application under Section 9 of the Arbitration and Conciliation Act, 1996 [“Act of 1996” for short] and directed the appellant to furnish a bank guarantee of Rs.29,61,159/-.

3. The brief facts of the case are that the appellant herein was awarded a contract by the National Highway Authority of India [“NHAI” for short] for ‘augmenting existing road from 180.478 km to 221.610 (design chainage from 181.450 km to 222.400km) on the Una to Kodinar National Highway No.8E in Gujarat by four laning’. The total project cost was Rs.40.95 crores. The appellant further subcontracted the said work to the respondent company vide Work Order bearing No.SEL/SBHPL/FY17-18/WO/03841 dated 10.2.2018. The respondent carried out the work for the appellant under the said work order. Accordingly, inspections came to be made and running bills were raised by the respondent. Further, for the period between 1.4.2018 to 30.09.2022, the respondent raised invoices and accordingly, payment certificates came to be issued by the appellant herein in favour of the respondent. Thus, as per the agreement between the parties, the respondent concluded the work order and a sum of Rs.25,97,639/- remained due and payable to the respondent by the appellant. Despite several reminders, the appellant did not make the payment of the outstanding dues. The respondent also proposed a settlement with the appellant, but it did not make any payment even as per the settlement proposed by the respondent. It is the case of the respondent that the appellant is liable to pay a sum of Rs.29,61,159/- in total towards the outstanding dues.

3.1 We may note that the work order consisted of an arbitration clause. The respondent company came to know that the appellant had received entire amount for the work done from the NHAI. Further, the audited accounts of the company for the financial year ended on 31.3.2023, showed huge losses. Also there was a negative cash flow in the balance sheet and profit and loss account. Apprehending genuine prejudice to its rights and interest, the respondent company moved an application under Section 9 of the Act of 1996 praying for the following reliefs:-

    “28A. Direct the Respondent to provide monetary security by way of a Bank Guarantee of any Nationalized and/or Schedule Bank or any other appropriate security of Rs.34,88,713/- along with pendent lite interest in favour of the Applicant and/or deposit an equal amount of Rs.34,88,713/- along with pendent lite interest with this Hon’ble Court securing the amount in dispute in the Arbitration;

B. Pass an order of attachment of the Bank Account of the Respondent, to be disclosed by the Respondent by way of an affidavit, being in its special knowledge, for an amount of Rs.34,88,713/- along with pendent lite interest;

C. Pending hearing and till final disposal of the present Application, this Hon’ble Court may be pleased to direct Respondent to keep Rs. 34,88,713/- separately in its Bank Accounts and not deal with the same nor create any lien, charge, interest etc. over the same.

D. Pass an ex-parte ad interim relief in terms of Para 28(C);”

3.2 The appellant company filed its reply opposing the said application. It was contended by the appellant that the respondent company is trying to seek priority amongst other creditors. The respondent company being an unsecured operational creditor, by way of the said application wants to rank equal to the secured creditors. It was submitted that there is no urgency for granting the relief as

            Click Here to Read the rest of this document
            1
            2
            3
            4
            5
            6
            7
            8
            9
            10
            11
            SupremeToday Portrait Ad
            supreme today icon
            logo-black

            An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

            Please visit our Training & Support
            Center or Contact Us for assistance

            qr

            Scan Me!

            India’s Legal research and Law Firm App, Download now!

            For Daily Legal Updates, Join us on :

            whatsapp-icon telegram-icon
            whatsapp-icon Back to top