IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
Biren Vaishnav, Nisha M. Thakore, JJ.
State Of Gujarat – Appellant
Versus
Associated Business Corp. – Respondent
R/FIRST APPEAL NO. 1170 of 1997 With R/FIRST APPEAL NO. 1606 of 1997
Decided On : 05-07-2024
Contract - Breach of Contract - Code of Civil Procedure Section 96 - The court analyzed the claims of the plaintiff against the defendant's failure to fulfill contractual obligations, emphasizing the importance of timely performance and the consequences of non-compliance.
Fact of the Case:
The plaintiff, a contractor, filed a suit against the State for breach of contract due to delays in providing necessary resources and payments for a construction project, leading to multiple claims for compensation.
Finding of the Court:
The court found that the defendant had committed a fundamental breach of contract by failing to provide timely access to the work site and necessary materials, resulting in the plaintiff's inability to complete the project on time.
Issues: Whether the defendant's failure to fulfill contractual obligations constituted a breach and warranted the claims made by the plaintiff.
Ratio Decidendi: The court held that the defendant's failure to provide timely access and resources constituted a fundamental breach of contract, justifying the claims made by the plaintiff.
Result: Both appeals are dismissed with no order as to costs.
JUDGMENT :
BIREN VAISHNAV, J.
1. Both these appeals are filed under Section 96 of the Code of Civil Procedure. On being aggrieved by the judgement and decree dated 29.10.1996 passed by the 4th Joint Civil Judge (SD), Godhra, in Special Civil Suit No.54 of 1988, First Appeal No.1170 of 1997 has been filed by the State insofar as, the suit of the plaintiff (respondent in the appeal) has been partly allowed. First Appeal No.1606 of 1997 has been filed by the original plaintiff insofar as some of the claims were disallowed and though the decree prayed for was of Rs.44,01,542/-, the Trial Court awarded a decree of Rs.14,86,414/-.
2. Facts in brief are as under:
3.Mr.Vivek Bhamare learned counsel appearing in First Appeal No.1606 of 1997 would submit as under:
Claim-1: Mr.Bhamare would submit that the amount to be awarded was Rs.1,76,400/- whereas the award amount was Rs.1,60,200/-. Exhs.162, 165, 166, were referred to and it was submitted that it was admitted by the witness Shri N.V.Patel in cross-examination that earth work was done. In other words therefore, once there was clear admission of the work done, there should not have been a short payment.
Claim-9: With regard to this claim Mr.Bhamare would submit that though the amount asked was Rs.1,60,000/-, awarded amount was Rs.80,000/- when it was an admitted fact that the contractor had carried out work of Rs.22,00,000/- out of Rs.30,00,000/- and therefore, 20% of the amount of the difference of the work would come to Rs.1,60,000/-.
Claim-14: This claim was also not granted by the Trial Court, Mr.Bhamare would want us to refer to Exhs.79 and 80 and submit that it was clearly stated in the cross-examination of the witness of the defendant Shri N.V.Patel that the plaintiff had suffered a loss due to non-receipt of the entire possession of the land for the road to be constructed. The Trial Court committed an error in holding that the claim was too general. The evidence on record indicated that earth work was done that there was carting and staking of metal sand soft murrum and earth work of which measurements were on record.
Claim-15: Where the claim was on account of loss suffered by the strike of Government Servants from 07.06.1985 to 19.08.1985, where it was claimed that the loss suffered was Rs.7,32,000/-, the trial Court awarded only Rs.5,47,500/-. Mr.Bhamare would submit that it was not disputed that the Government Servants were on strike and in accordance with clause-16 of the tender, trucks engaged for collecting metal, sand etc. were not operated and therefore the claim should ha
AI
A fundamental breach of contract occurs when one party fails to perform essential obligations, justifying claims for damages by the aggrieved party.
Point of law: When the appeal is presented in terms of Section 96 CPC and when this Court is considering this appeal not only as a last Court of fact but also in terms of law, it is open for the appe....
Contractors cannot claim damages for delays caused by their own inaction or failure to meet contractual obligations, even if land acquisition delays occur.
The court affirmed that a contractor's claims for delays caused by defendants were valid, and it has the discretion to adjust interest rates based on economic conditions.
Civil Courts have jurisdiction to hear claims under construction contracts barred from arbitration, provided they arise within the limitation period set by specific contract conditions.
The court upheld the trial court's dismissal of the plaintiffs' suit for damages due to insufficient evidence and the contractor's failure to complete the work as per the contract.
The judgment clarified the jurisdiction of the Civil Court, the application of the Limitation Act, and the entitlement of the plaintiff to claim losses incurred due to non-cooperation from the defend....
The court established that an Employer's failure to fulfill contractual obligations can invalidate penalties imposed on a contractor for delays, emphasizing fairness in administrative decisions.
A contractor is entitled to recover damages for loss of profit when delays are caused by the other party's breach of contract, and penalties cannot be imposed on the contractor under such circumstanc....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.