IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
BIREN VAISHNAV, NISHA M. THAKORE, JJ.
Kheda District Panchyat - Appellant
Versus
Arvindbhai C. Patel - Defendant
R/First Appeal Nos. 2344, 2345 of 1998
Decided On : 12-06-2024
Contract - Recovery Claims - Civil Procedure Code - Sections 1, 2, 3 - The court interpreted the provisions regarding breach of contract and recovery of damages, emphasizing that delays caused by the other party's failure to perform their obligations do not warrant penalties against the contractor.
Fact of the Case:
The Contractor filed a suit for recovery of payments due for work on a road construction project, claiming delays were due to the Panchayat's failure to hand over the site on time. The Panchayat countered with a suit for recovery of payments made to the Contractor, alleging non-completion of work.
Finding of the Court:
The court found that the Contractor was not at fault for delays, as the Panchayat failed to provide timely possession of the land, and thus upheld the Contractor's claims while dismissing the Panchayat's suit as time-barred.
Issues: Whether the Contractor was entitled to recover payments despite the Panchayat's claims of non-completion of work and whether the Panchayat's suit was time-barred.
Ratio Decidendi: The court held that when delays are caused by the other party's failure to fulfill their obligations, the contractor cannot be penalized, and claims for damages due to loss of profit are admissible.
Result: The appeals of the Panchayat are dismissed.
ORDER :
Biren Vaishnav, J.
1. These appeals are filed against the common judgement and decree passed by the 3rd Joint Civil Judge (SD), Nadiad, District : Kheda, dated 02.01.1998. It is a common judgement and decree in Special Civil Suit No. 185 of 1993 filed by the Contractor Shri Arvindbhai C. Patel for recovery of Rs.8,20,792/- and in Special Civil Suit No. 205 of 1993 filed by the Kheda District Panchayat for recovery of Rs.21,44,722.32/-. By the aforesaid judgement and decree, the learned Trial Judge allowed the suit of the Contractor, namely, Special Civil Suit No. 185 of 1993 directing that an amount of Rs.8,20,792/- be recovered with 12% penal interest from the Kheda District Panchayat. Special Civil Suit No. 205 of 1993 filed by the Kheda District Panchayat was dismissed. Hence, the respective appeals.
2. Facts in brief indicate that the work order was issued on 27.03.1987 by the Kheda District Panchayat to Shri Arvind C. Patel for constructing Sarkhej – Kakarkhad Ravadavad road II stage. Since the Contractor was the last bidder whose tender amount was Rs.14,74,396.10/-, the contract was awarded to the Contractor. The date of completion was stipulated to be 26.06.1988.
2.1 It was the case of the plaintiff – Contractor that since the site was not handed over on time due to pending land acquisition proceedings, the work could not be completed within the stipulated time. Payments also were irregular. Claims, therefore, were raised against the Kheda District Panchayat, six in number, which are as under:-
(ii) Rs.20,000/- for work done but not paid.
(iii) Claim No.3 amounting to Rs.30,000/- as account of the metal, machine out and quarry west.
(iv) Claim No.4 amounting to Rs.2,65,468/- on account of loss of profit at the rate of 20%.
(v) Claim No.5 is of Rs.4,42,350/- on account of establishment charges.
(vi) Claim No.6 amounting to Rs.27,183/- final bill Rs.1,500/- asked for notice charges and total amount comes to Rs.8,20,792/- found due against defendant which may be allowed together with 18% penal interest by passing a decree against defendant along with the cost of the suit.”
2.2 After hearing the parties, the suit of the Contractor, namely, Special Civil Suit No. 185 of 1993 was decreed as above.
2.3 Special Civil Suit No. 205 of 1993 filed by the Kheda District Panchayat on the ground that the work was not completed within the stipulated time, and therefore, the work had to be allotted to one Shri Rakesh Shah as a result of which amounts were to be recovered from the Contractor of Rs.17,87,381.30/- paid by the plaintiff – Panchayat, was dismissed by a common judgement and decree. Since the respective suits were allowed and / or dismissed, the Kheda Panchayat is in appeal.
3. Mr. H.S. Munshaw, learned counsel appearing for the Kheda District Panchayat, being aggrieved by the decree in favour of the Contractor, would submit as under:
3.1 There were several set of evidences on record to show that the Contractor did not complete the work within the stipulated time limit which was clearly established. He would press into service the documents at Exhs 29 and 35 i.e. the last bill given to the subsequent Contractor, to submit that the suit of the Kheda District Panchayat ought not to have been dismissed on the ground of limitation as the last bill was of the year 1991 whereas the suit was filed in the year 1993.
3.2 Mr. Munshaw, learned Counsel, would submit that the learned Judge committed an error in holding that the land acquisition proceedings were pending. He would submit that the possession of the Survey Nos. 119, 283, 284, 319 & 322 was already handed over to the earlier Contractor M/s. Nihil Corporation. The work which was to be executed by the Contractor could not be completed due to his sole negligence.
3.3 Mr. Munshaw, learned Counsel, would submit that notices were given to
Hind Construction Contractors, M/s. Vs. State of Maharashtra
AI
A contractor is entitled to recover damages for loss of profit when delays are caused by the other party's breach of contract, and penalties cannot be imposed on the contractor under such circumstanc....
A fundamental breach of contract occurs when one party fails to perform essential obligations, justifying claims for damages by the aggrieved party.
The court upheld the trial court's dismissal of the plaintiffs' suit for damages due to insufficient evidence and the contractor's failure to complete the work as per the contract.
The court established that an Employer's failure to fulfill contractual obligations can invalidate penalties imposed on a contractor for delays, emphasizing fairness in administrative decisions.
The dismissal of the appeal underscores the necessity for the claimant to substantiate their claims within the limitation period, as per Article 18 of the Limitation Act.
The judgment clarified the jurisdiction of the Civil Court, the application of the Limitation Act, and the entitlement of the plaintiff to claim losses incurred due to non-cooperation from the defend....
The main legal point established in the judgment is the importance of adhering to the terms of the contract, including the dispute resolution mechanism, and the court's limited revisional powers in i....
The court upheld the binding nature of the contract, ruling that the Plaintiff's claims were untenable due to failure to exercise contractual options and were barred by limitation.
The lack of privity of contract and failure to establish a cause of action were central to the court's decision.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.