IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
SUNITA AGARWAL, C.J., PRANAV TRIVEDI, J.
Gujarat Water Supply and Sewerage Board - Appellant
Versus
Aakar Construction - Defendant
R/First Appeal No. 2445 of 2024 With Civil Application (For Stay) No. 1 of 2024
Decided On : 02-07-2024
Arbitration - Arbitration and Conciliation Act, 1986 - Sections 34, 37 - The court upheld the limited scope of interference in arbitral awards, emphasizing the finality of arbitration and the narrow grounds for setting aside awards under the Act.
Fact of the Case:
The appellant, a state-owned board, terminated a contract with the respondent for failing to complete work on time. The respondent challenged the termination and the invocation of a bank guarantee, leading to arbitration, which ruled in favor of the respondent. The appellant's challenge to the arbitration award was rejected by the Commercial Court.
Finding of the Court:
The court found no merit in the appellant's claims, affirming that the arbitrator acted within the scope of the agreement and that the issues raised were properly adjudicated. The court emphasized the limited grounds for interference with arbitral awards.
Issues: Whether the arbitrator exceeded the scope of the joint settlement and whether the appellant provided necessary permissions for the contract execution.
Ratio Decidendi: The court reiterated that the scope of judicial review of arbitral awards is limited, and courts should not interfere unless there is a clear violation of public policy or principles of natural justice.
Result: The appeal was dismissed, upholding the arbitration award.
ORDER :
Pranav Trivedi, J.
1. The instant First Appeal has been filed under Section 37 of the Arbitration and Conciliation Act, 1986 (hereinafter referred to as the “Act 1996”) challenging the judgment and order dated 11.09.2023 passed by the learned 4th Additional District Judge, Vadodara, Commercial Court (for short the “Commercial Court”) in Commercial Civil Misc. Application No. 76 of 2022, wherein the Commercial Court, rejected the application preferred by the appellant under Section 34 of the Act.
2. The facts resulting into filing of the First Appeal is that the appellant is a Board constituted under the provisions of the Gujarat Water Supply and Sewerage Board Act, 1978 and is wholly owned and controlled by the State of Gujarat. The appellant issued tender for the work related to ‘Dabhoi Water Supply Scheme’. The respondent participated in the tender issued by the appellant. Pursuant thereto, the parties executed the agreement dated 01.11.2011 being Agreement No. B:2-74-2011/12 and B:2/75-2011/12 for a stipulated period of 12 months. The respondent also submitted bank guarantee of Rs.31,22,150/- as per the terms and conditions of the tender.
2.1. It is the case of the appellant that the respondent failed to carry out the contract works within the stipulated time as well as extended time. Consequently, the respondent issued notice of termination dated 15.07.2013. Therefore, the contract agreement came to be terminated by the appellant on 16.08.2013. Pursuant thereto, the respondent was also black-listed for a period of three years and the bank guarantee was ordered to be invoked.
2.2. Pursuant to the termination of the agreement and order of injunction of bank guarantee, the respondent preferred regular civil suit being Regular Civil Suit No. 455 of 2013 against the appellant, inter alia praying for setting aside the termination notice and permanent injunction restraining the appellant from encashing the bank guarantee. During the pendency of the suit, both the parties filed joint ‘purshis’ before the Commercial Court and on the basis of the joint settlement purshis, judgment and decree dated 23.11.2013 came to be passed. However, the settlement ‘purshis’ was not executable and enforceable, which resulted into the appellant again preferring suit before the Commercial Court being Regular Civil Suit No. 640 of 2014 inter alia praying for declaration and permanent injunction against the implementation of the said judgment and decree dated 23.11.2013. In Regular Civil Suit No. 640 of 2015, Exhibit-5 application was filed for interim injunction which came to be rejected, by way of order dated 30.08.2016.
2.3. Being aggrieved by the rejection of Exhibit-5 application, the appellant preferred appeal being Misc. Civil Appeal No. 17 of 2017 before the learned District Judge, Vadodara. During the course of hearing of the aforesaid appeal, second settlement agreement came to be executed and the court below referred all the issues to the Arbitrator. Upon consent of the parties, on the name of the Arbitrator, Regular Civil Suit No. 640 of 2014 as well as appeal Misc. Civil Appeal No. 17 of 2017 came to be withdrawn by the appellant.
2.4. Pursuant to the withdrawal of the suit as well as the appeal, the dispute was referred to the Arbitrator. The Arbitrator after hearing both the parties at length, passed an award dated 20.03.2018, partly allowing the claim of the respondent by directing the appellant to pay sum of Rs.65,58,939/- along with 8% interest from the date of termination of the contract till the date of payment. Aggrieved by the award dated 20.03.2018, the appellant preferred application under Section 34 of the Act, which came to be numbered as Commercial Civil Misc. Application No. 76 of 2022. The said Commercial Misc. Application came to be rejected by way of order dated 11.09.2023. It is this order dated 11.09.2023 is impugned in the present appeal.
3. The main ground of challenge urged by the learned counsel for the appellant w
UHL Power Company Limited vs. State of Himachal Pradesh
The judgment reinforces the principle that courts have limited grounds to interfere with arbitral awards, respecting the finality of arbitration under the Arbitration and Conciliation Act.
The court affirmed that judicial interference in arbitral awards is limited, focusing on the necessity of cogent reasoning and adherence to public policy.
The court confirmed that judicial interference in arbitral awards is limited to cases of patent illegality or perverse findings, respecting the finality of arbitration.
The court confirmed that judicial interference in arbitral awards is limited to specific grounds, emphasizing respect for the arbitral process and the finality of awards.
The court upheld the principle that arbitral awards should not be interfered with unless there is a clear violation of public policy or a patent illegality.
The court affirmed that judicial intervention in arbitral awards is limited to grounds of public policy or patent illegality, emphasizing respect for the Arbitrator's findings.
The appeal was allowed, reinstating the arbitrator's award which concluded that the termination of the contract was illegal due to failure in fulfilling mutual obligations concerning site availabilit....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.