IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
HEMANT M. PRACHCHHAK, J.
Gujarat Water Supply And Sewerage Board - Appellant
Versus
State Of Gujarat & Anr. – Respondents
R/First Appeal No. 22 of 2007
Decided On : 26-08-2025
| Table of Content |
|---|
| 1. background of the contractual disputes and claims. (Para 1 , 2) |
| 2. arguments presented by both parties regarding contract performance. (Para 5 , 6) |
| 3. court's evaluation of evidence and legal interpretations. (Para 7 , 8 , 9 , 10) |
| 4. conclusion and order to dismiss the appeal. (Para 11) |
JUDGMENT :
HEMANT M. PRACHCHHAK, J.
1. Present appeal is filed by the appellant – original defendant No.2 under Section 96 of the CIVIL PROCEDURE CODE against the judgment and decree dated 24.10.2005 passed by the learned Principal Senior Civil Judge, Civil Court, Gandhinagar (hereinafter referred to as “the trial Court”) in Special Civil Suit No.51 of 1997 (Old Special Civil Suit No. 96 of 1986) whereby the trial Court has allowed the suit and directed the original defendants to pay Rs.10,19,277/- along with the interest.
2. The original plaintiff – respondent No.2 herein is the company incorporated under the provisions of the Indian Companies Act, 1913 and carrying manufacturing of Pre-Stressed Concrete Pipes and also Civil Engineering Works relating to installation of pipe lines. The defendant No.2 is a statutory body established under the Gujarat Water Supply and Sewerage Board Act, 1978. By the said Act the work, assets, liabilities and benefits have been transferred from defendant No.1 to defendant No.2.
2.1 The defendant No.1 issued notice in August / September 1978, being Tender Notice for Bhavnagar Water Supply Scheme Shetrunji Pipeline Project for the purpose of providing, fabricating, laying and jointing of pre- stressed concrete pipes more particularly specified in the notice inviting tenders and the plaintiff submitted the offer for the aforesaid tender. Considerable correspondence, thereafter, ensued between the plaintiffs and the defendant No.1, by which various terms and conditions, as set out in the tender documents of defendant No.1 as also letter of ofÏcers of the plaintiff, were modified and mutually accepted. By a letter dated 27.12.1978, the defendant No.1 issued a work order to the plaintiff for carrying out the aforesaid project. The tender documents, the plaintiff’s letter of offer dated 13.09.1978 and the subsequent correspondence culminating in the Works Order dated 27.12.1978 collectively constitute the contract arrived at between the parties and are preferred to as "the Contract Documents".
2.2 That defendant No.1 had committed considerable default or delay in issue of the 1000 tons of cement such delay ranging from 1.1/2 months to 12 months after the issue of the work order, for which there was delay on the part of the defendant No.1 in issuing the said contract, the plaintiff had to incur additional costs by way of idle labour, interest and cost of raw materials. The damages incurred by the plaintiff amounted to Rs.2,94,000/- and, therefore, the plaintiff claimed the said amount.
2.3 That other outstanding dispute was in relation to the rate at which defendant No.1 were required to pay to the plaintiff for the excavation work under item'2 of Schedule "B". The total estimated excavation was 44,931 cm, the total quantity of excavation done was 39,156.95 cm i.e. the total excavation done was, in fact, less than the estimated quantity of excavation and there was no question of excess excavation. However, the excavation actually carried out was admittedly in harder strata of the soil and the same was required to be done at greater depths. Consequently, the plaintiff were required to be reimbursed for the same at higher rates as accepted by the defendants. There was no question of any alteration in/or addition to the original specifications, drawings, designs and instructions and, accordingly, clause 14 had no application whatsoever for the purpose of determining the rate applicable in respect of the excavation. The defendants, however, wrongly applied Cl.14 and purported to pay the plaintiff at the reduced rates prescribed in Clause 14. Applying the accepted rates for the actual excavation work done, the pla
State Of Gujarat Vs. Shirinbai Pirojshah Wadia
National Fertilizers Limited Vs. Puran Chand Nangia
Chief Secretary, State Of Gujarat Vs. Kothari And Associates
A party may recover damages for breach of contract when the other party fails to fulfill its contract obligations, particularly regarding timely supply of materials.
The judgment clarified the jurisdiction of the Civil Court, the application of the Limitation Act, and the entitlement of the plaintiff to claim losses incurred due to non-cooperation from the defend....
Point of law: When a contract has been broken, if a sum is named in the contract as the amount be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the....
Civil Courts have jurisdiction to hear claims under construction contracts barred from arbitration, provided they arise within the limitation period set by specific contract conditions.
The court upheld the trial court's dismissal of the plaintiffs' suit for damages due to insufficient evidence and the contractor's failure to complete the work as per the contract.
The court upheld the binding nature of the contract, ruling that the Plaintiff's claims were untenable due to failure to exercise contractual options and were barred by limitation.
The suit was within limitation as the cause of action accrued upon the non-payment of the final bill, and not completing the price escalation calculations per the contract terms invalidated the defen....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.