SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
judgment-img

2026 Supreme(Bom) 19

IN THE JUDICATURE OF HIGH COURT AT BOMBAY AURANGABAD BENCH
ARUN R. PEDNEKER, VAISHALI PATIL-JADHAV
Executive Director, G.M.I.D.C. – Appellant
Versus
Gurunanak Industries, Now G.N.I. Infrastructure Pvt. Ltd. – Respondent


Advocates Appeared:
For the Appellant : S.G. Bhalerao
For the Respondents: A.P. Bhandari, A.R. Kale

Judgement Key Points

Certainly. Here are the key points derived from the provided legal document:

  1. The suit was filed within the limitation period because the cause of action arose upon the non-payment of the final bill, specifically after the last R.A. Bill was measured and drawn on 12/04/2016. The limitation period started from this date, making the suit filed in 2017 timely (!) (!) (!) (!) .

  2. The contractual work was completed on 30/06/2013, but the final measurement and payment were only made on 12/04/2016. The cause of action for the claim regarding price escalation crystallized only after this final payment, which is why the limitation period is considered to begin from this date (!) (!) (!) .

  3. The dispute primarily concerns the interpretation of the price variation clause (Clause 56). The clause prescribes that escalation should be calculated separately for each R.A. Bill based on the period covered by that bill, rather than averaging escalation over the entire contract period (!) (!) (!) (!) (!) (!) (!) (!) (!) (!) .

  4. The contractual scheme involves paying escalation amounts in each R.A. Bill, which are based on the specific period for that bill. The contractor accepted these payments over nearly 20 years, indicating acceptance of the escalation calculations at each stage (!) (!) .

  5. The interpretation that the entire contract period should be averaged for escalation calculation is inconsistent with the language of the clause, which explicitly refers to the "cost of work done during the period under consideration" (i.e., each R.A. Bill period). The formulas are designed to compute escalation separately for each bill period, not cumulatively over the entire contract duration (!) (!) (!) .

  6. The payments made under each R.A. Bill, including the final one, were in accordance with the contractual formulas, and the plaintiff's claim for additional escalation based on a cumulative average is unsupported by the contractual language (!) .

  7. Since the escalation was properly computed and paid in each R.A. Bill, the claim for a lump sum additional amount of Rs. 5,76,25,112/- is without contractual or legal basis and is thus rejected (!) .

  8. The appellate court found that the suit was within the limitation period, and the interpretation of the contractual clauses was correct. Consequently, the judgment in favor of the plaintiff was set aside, and the appeal was allowed (!) (!) .

Would you like a detailed summary or specific legal implications based on these points?


JUDGMENT :

ARUN R. PEDNEKER, J.

1. The present Commercial Appeal is filed by the original defendants, who are aggrieved by and dissatisfied with the judgment and decree dated 09/08/2019, passed by the learned District Judge-1, Jalna, in Commercial Suit No. 08 of 2019, whereby the suit for recovery of an amount of Rs.5,76,25,112/- along with interest at the rate of 15% per annum from the date of filing of the suit till realisation is decreed.

2. Heard the learned Counsel Mr. S.G. Bhalerao for the appellants, the learned Counsel Mr. A.P. Bhandari for respondent No.1 and the learned AGP Mr. A.R. Kale for respondent No.2-State.

FACTS :

3. The case of the plaintiff, as pleaded in the plaint, in brief, is as follows :

The original defendants invited tenders for the construction work of “Nimna Dudhana Project – Earthen Dam, Chainages 580 to 2810 meters” situated in Jalna District. The plaintiff emerged as the lowest bidder and was awarded the contract by Defendant No.5 on 16/03/1995. The stipulated period for completion of the work was 24 calendar months, i.e. up to 15/03/1997.

4. The estimated cost of the work was Rs.2,09,92,740/-, whereas the accepted contract value was Rs.2,80,25,309/-. The

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top