SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Guj) 50

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
SUNITA AGARWAL, C.J., PRANAV TRIVEDI, J.
ILA Kirit Shelat & Ors. – Petitioners 
Versus 
Union of India & Ors. – Respondents 
R/Special Civil Application No. 16174 of 2024 With R/Special Civil Application No. 16175 of 2024 With R/Special Civil Application No. 16074 of 2024
Decided On : 29-11-2024

Advocates Appeared:
For the Petitioners: Mr. Mihir Joshi, Sr. Adv. With Mr. Rutul Desai.
For the Respondents: Government Pleader, MS Archana U. Amin.

The issuance of notifications under the Railways Act must adhere to statutory requirements of consultation and competent authority endorsement to ensure compliance with natural justice.

Headnote:(A) Railways Act, 1989 - Sections 20A and 2(37A) - Petitioners challenged acquisition notifications - Validity questioned based on lack of meeting of competent authority regarding special project status - Claim of violation of natural justice due to the absence of consultations with land owners. (Paras 1-8)

(B) Principles of Natural Justice - Requirement for proper consultation in land acquisition - Argument that mechanical notifications lack application of mind by the authority. (Paras 6-8)

Facts of the case:
The petitioners are challenging multiple notifications related to the acquisition of land under the Railways Act, claiming that the required consultations and proper procedures were not followed, questioning the declaration of the project as a Special Railway Project as per Section 2(37A).

Findings of Court:
All issues raised in the writ petition require consideration; status quo is to be maintained regarding possession of the lands-in-question.

Issues: Validity and application of the notifications concerning the acquisition process, and adherence to principles of natural justice and consultation requirements.

Ratio Decidendi: Notifications issued under the Railways Act must comply with statutory requirements, including proper authorizations and necessary consultations as mandated for public projects. Ignoring these may constitute a breach of natural justice.

Result: Issues require consideration.

Table of Content
1. challenge to validity of acquisition notifications (Para 1 , 2)
2. argument against validity of proceedings and lack of natural justice (Para 3 , 4 , 6 , 7 , 8)
3. court’s need for considering raised issues (Para 5 , 9)
4. maintaining status quo till next hearing (Para 10 , 11 , 12)

ORDER :

SUNITA AGARWAL, C.J.

Learned counsel for the petitioners prays and is granted permission to make correction in the prayer clause in the writ petitions during the course of the day to make proper prayers.

2. By means of the abovenoted three writ petitions, the petitioners are challenging the validity of the acquisition notifications dated 11.10.2023 and 12.10.2023 under Section 20A of the Railways Act, 1989 and the declaration notifications under Section 20E dated 08.10.2024 and 09.10.2024. The challenge is also to the validity of the Notification dated 02.02.2023 issued under Section 2(37A) of the Railways Act, 1989. The three writ petitions have been tagged and heard together as they are on common questions of law and facts.

3. Challenging the acquisition proceedings drawn by the Railways with the notifications issued by the Ministry of Railways (Western Railways)(Construction Organisation), noted hereinbefore, it was submitted by Mr. Mihir Joshi, the learned senior advocate for the petitioners in one of the writ petitions that the proceedings for acquisition under the Railways Act can be invoked in a case where the Central Government is satisfied that any land is required for the public purpose, which should be for execution of a Special Railway Project. Before issuance of the proposal under Section 20A declaring the intention of the Central Government to acquire any land, there is a necessity of making a declaration by means of the notification as per Section 2(37A) by the Central Government that the project-in-question is a Special Railway Project, which fulfills the condition of being a project for providing national infrastructure for a public purpose and is to be executed in a specified time-frame.

4. The further submission is that on the publication of the proposal for acquisition under Section 20A, the petitioners herein filed their objections on 31.10.2023, raising specific queries, pertinent amongst which are asking to provide relevant documents of the proposal for considering the project-in-question as a Special Railway Project within the meaning of Section 2(37A) of the Railways Act; the feasibility report, if any, in relation to the proposal in question; the survey report, if any, undertaken; the report regarding consultation with the land owners who would be affected by the acquisition. Inviting attention of the Court to the response of the Railways to the said queries raised by the petitioners, the learned senior advocate appearing for the petitioners has taken us through page No. ‘190’ of the paper book, the reply to the representation dated 29.11.2023 filed by some of the petitioners therein.

5. Giving parawise remarks to the objections raised by the petitioners in the table provided in the communication dated 08.01.2024 sent by the Deputy Chief Engineer/C/II-ADR, in response to the query about the proposal for considering the project as a Special Railway Project, the copy of the notification dated 02.02.2023 has been enclosed. However, in response to the query with regard to the minutes of the meeting of the concerned competent authority wherein the decision was taken to treat the project as a Special Railway Project, it was stated that considering the importance and urgency of the project, the proposal was submitted to railway’s competent authority to declare it as a Special Railway Project and the authority decides itself on the merits of the project. It is further stated therein that there was no meeting organised for the purpose.

6. The submission of the learned senior counsel, thus, is that the notification dated 02.02.2023 is not backed by any decision of the competent authority arrived at by application of

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top