IN THE HIGH COURT OF ALLAHABAD
MANOJ MISRA, DINESH PATHAK, JJ.
Jaiveer Singh And 2 Others – Appellant
Versus
Union Of India And 4 Others – Respondents
Writ C.No. -2959 of 2020, 42537, 42577, 43014 of 2019
Decided on : 27-08-2021
respectively, of the Railways Act, 1989 - Sections 20-A and 20-E - Amount of compensation - Specifically claim - Special Railway Project - Petitioners in leading Writ is that to acquire land for Special Railway Project Freight Corridor in district Nagar in State of Uttar Pradesh a notification was issued which was followed by declaration - Pursuant thereto an award was passed and physical possession hectare of land falling in village was taken- Despite having taken possession of that land was not utilised- Later in a mala fide manner on request of Greater Noida Authority (for short GNIDA) impugned –Held, Appellants to be assessed Section said Act as per current market value of land - Competent Authority is directed to compute amount of compensation on basis of current market value of land which may be determined with reference stretch of land landowners were satisfied with amount awarded and have not approached this Court these circumstances despite our finding that Respondents have breached mandatory provisions of Act court do not think this is a fit case to set aside entire acquisition proceedings relief granted in present case is confined to Appellants herein and would not become a precedent for other landowners who have not challenged acquisition proceedings before this Court case also as we have noticed earlier out of a total cost of have been spent and out of total length linear length remains to be completed due to resistance offered by few land-owners- Importantly completion of project to extent indicated above has been set out in counter affidavits of which there is no specific denial- In these circumstances if court set aside declaration now it would result in huge wastage of public money as entire alignment of freight corridor would have to be redone – Petition dismissed
JUDGMENT :
Manoj Misra, J.
1. As these four petitions question the acquisition of land under a common notification, they have been clubbed together.
Writ petition (Group C) numbers 2959 of 2020; 42537 of 2019; and 42577 of 2019 seek quashing of notifications dated 11.02.2019 and 06.11.2019 issued under Sections 20-A and 20-E, respectively, of the Railways Act, 1989 (for short the 1989, Act) to acquire land for a Special Railway Project i.e. Eastern Dedicated Freight Corridor (for short Freight Corridor) in district Gautam Budh Nagar. Whereas, Writ C No. 43014 of 2019 has been filed by persons who claim themselves to be aggrieved with the impugned notifications though their land is not included in the impugned notification. The petitioners of Writ C No. 2959 of 2020 have their land at village Chamrawali-Boraki, Tehsil Dadri, District Gautam Budh Nagar whereas the petitioners in the remaining three petitions have their land at village Rithauri in the same district.
2. As in Writ C No. 2959 of 2020 pleadings are elaborate and parties have exchanged their affidavits, the same is taken as the leading petition. However, we shall refer to the facts of the other three petitions also, wherever necessary.
3. The case of the petitioners in the leading Writ C No. 2959 of 2020 is that, to acquire land for the Special Railway Project Freight Corridor in district Gautam Budh Nagar in the State of Uttar Pradesh, a notification under Section 20-A of the 1989 Act was issued on 24 August 2009, which was followed by declaration, dated 30 July, 2010, under Section 20-E of the 1989 Act. Pursuant thereto, an award was passed on 30 August 2011, under sub-section (2) of Section 20-F of the 1989 Act, and physical possession of 5.0844 hectare of land falling in village Chamrawali -Boraki was taken. Despite having taken possession of that land, the land was not utilised. Later, in a mala fide manner, on request of Greater Noida Authority (for short GNIDA), the impugned notifications were issued even though, for the purpose of the Special Railway Project, need for land stood satisfied by the earlier acquisition proceeding. Accordingly, by exercising statutory right available under subsection (1) of section 20-D of the 1989 Act, an objection to the notification was taken. But, without addressing the objection as per sub-section (2) of Section 20-D of the 1989 Act, straight away the impugned declaration under sub-section (1) of Section 20-E of the 1989 Act was made by making an incorrect declaration that no objection was taken under sub-section (1) of Section 20-D of the 1989 Act. Similar, is the case of the petitioners in Writ C Nos. 42537 of 2019 and 42577 of 2019 though their pleadings are not as elaborate as is in the lead petition i.e. Writ C No. 2959 of 2020.
4. In the leading petition i.e. Writ C No. 2959 of 2020, several counter-affidavits have been filed. It would be useful to refer, in brief, to the contents of those counter-affidavits. These counter affidavits are as follows:
B.P. Singhal v. Union of India
Dedicated Freight Corridor Corporation of India V. Subodh Singh and others
Gojer Bros. (P) Ltd. v. State of W.B.
Hindustan Petroleum Corporation Ltd. v. Darius Shapur Chennai and others
Kalpana Mehta v. Union of India and others
Kalinga Mining Corporation v. Union of India
K.T. Plantation (P) Ltd. v. State of Karnataka
Kesar Enterprises Ltd. v. State of U.P and others
Manohar Joshi v. State of Maharastra
Nand Kishore Gupta v. State of U.P. and others
Savitri Devi vs. State of U.P.
State of Tamil Nadu vs. Vasanthi Veerasekaran
Surinder Brar V. Union of India
State of West Bengal v. Debasish Mukherjee and others
Swadeshi Cotton Mills v. Union of India
Point of Law : If any person referred to in sub-section (1) of Section 64 has built a house on any land referred to in Section 63 of this Code, not being land reserved for any public purpose, and suc....
The main legal point established in the judgment is the importance of complying with the specified time frame for filing objections under the National Highways Act and the court's emphasis on the pub....
Procedural compliance under the Railways Act is essential for valid land acquisition for public purpose projects.
The issuance of notifications under the Railways Act must adhere to statutory requirements of consultation and competent authority endorsement to ensure compliance with natural justice.
The acquisition process must comply with statutory provisions of timely final notification and personal hearing, failure of which undermines legal validity.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.