2022 Supreme(Gau) 1014

IN THE HIGH COURT OF GAUHATI, (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH), (ITANAGAR BENCH)
A.M. BUJOR BARUA, DEVASHIS BARUAH, JJ.
The State Of AP, Represented by the Secretary (Land Management), Govt. of Arunachal Pradesh and 2 Ors. – Petitioners
Versus
Mihin Laling, S/o. Late Mihin Talang and Anr. – Respondents
WA No.15 Of 2022
Decided On : 12-09-2022

Advocates Appeared:
For the Petitioners: Subu Tapin.
For the Respondents: Marto Kato.

Headnote:

Constitution of India, 1949 - Article 254 - Rehabilitation and Resettlement Act, 2013 - Section 103 - Sadiya Frontier Tract Jhum Land Regulation, 1947 - Section 10 - Land Acquisition Act 1894 - Government of India Act, 1935 - Section 92 - Requisition Compensation - Right to Fair Compensation - Land Acquisition Rehabilitation - Writ appeals involve important questions of law relating to the applicability of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 based upon factual matrix of respective writ petitions – Held, Writ petitioners would be entitled to payment of solatium and interest in respect of acquired land case where award had been passed prior to coming into effect solatium and/or interest case may be would be governed by provisions of relevant law of acquisition that been in force - Appellants authorities under State of Arunachal Pradesh as well NHIDC needful to pay solatium and interest on compensation paid to writ petitioners on value of acquired land as per provisions of relevant law of acquisition - Writ appeals stands disposed of.

JUDGMENT :

[A.M. Bujor Barua, J.]

1. Heard Mr. Kardak Ete, learned Advocate General In-charge for the appellants in WA/15/2022, WA/16/2022, WA/17/2022, WA/22/2022, and WA/23/2022 and Mr. Bhaskar Dutta, learned Senior counsel for the appellants in WA/20/2022 and WA/21/2022. Also heard Mr. Subu Koyang, learned counsel for the writ petitioners, Mr. Marto Kato, learned CGC authorities under the Union of India and Mr. Dugmar Kamduk, learned standing counsel for the Land Management Department to the Government of Arunachal Pradesh.

2. As all the writ appeals involve important questions of law relating to the applicability of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (in short Act of 2013) in the State of Arunachal Pradesh; vis-a-vis the Balipara/ Tirap/Sadiya Frontier Tract Jhum Land Regulation, 1947 (in short Regulations of 1947) based upon the factual matrix of the respective writ petitions, which are also the same and therefore, we take up the factual basis in respect of WA/15/2022 and refer to the materials and documents provided therein.

3. The writ petitioners are all land owners and by a notification No. LM- 14/2014 dated 17.02.2014 the Government of Arunachal Pradesh through the Secretary of the Land Management Department had issued a notification for acquiring the lands mentioned to the Schedule to the said notification for construction of road under Trans Arunachal Highway(in short TAH) from Potin to Bopi (Godak) Via Yazali, Yazuli, Ziro, Boa-shimla, Tamen and Raga. The lands of the writ petitioners were included in the Schedule to the notification for acquisition. The notification for acquisition states that it was issued under Section 10 of the Regulation of 1947.

4. It would be relevant to take note that the Government of Arunachal Pradesh through the Secretary of the Land Management Department had issued a notification No. LM-134/2011 providing for the procedure to be followed in respect of depositing and disbursement of compensation for the acquisition of land for various purposes including the TAH and in the notification itself it has been provided that the procedure prescribed under the Land Acquisition Act 1894 (in short Act of 1894) shall be followed for calculation of the compensation. The procedure prescribed in the notification dated 28.09.2012 for calculation of the compensation is as extracted:-

    1. Land value.

2. Add 12% per annum as interest on land value to be calculated from the date of publication of notification under Section 4(1) of the Land Acquisition Act 1894 to the date of award or the date of section taking possession of lands before declaring the award (by applying clause) whichever is earlier.

3. Add 30% (Lump Sum) solatium on land value.

4. Add cost of standing trees and/or any other assets on the land.

5. Add establishment charges @ 8% on the land value.

6. Add contingency charges @ 2% on the land value.

The notification of 28.09.2012 further provides that 8% establishment charge on the land value as provided in Sl. No. 5 shall be deposited in the treasury under the head of account “0029’’ (Land Revenue) and the 2% contingency charges as provided in Sl. No. 6 shall be deposited in the Joint Account of the Commissioner/ Secretary to the Government of Arunachal Pradesh in the Land Management Department and the Director of Land Management, Government of Arunachal Pradesh. It further provided that the land value in Sl. No. 2 interest of 12%, in Sl. No. 3 a solatium of 30%, and the cost of standing trees and other assets on the land in Sl. No. 4 shall be paid to the land owners.

5. By a subsequent notification No. LM-134/2011 dated 27.02.2016, in supersession of the earlier notification No.LM-134/2011 (Pt) the Governor of Arunachal Pradesh was pleased to prescribe a modified procedure to be followed for all kinds of land acquisition including payment of compensation. The procedure provided in the notification dated 27.02.2016 is as

                    Click Here to Read the rest of this document
                    1
                    2
                    3
                    4
                    5
                    6
                    7
                    8
                    9
                    10
                    11
                    SupremeToday Portrait Ad
                    supreme today icon
                    logo-black

                    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                    Please visit our Training & Support
                    Center or Contact Us for assistance

                    qr

                    Scan Me!

                    India’s Legal research and Law Firm App, Download now!

                    For Daily Legal Updates, Join us on :

                    whatsapp-icon telegram-icon
                    whatsapp-icon Back to top