SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Gau) 1461

IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
KALYAN RAI SURANA, J.
Sri Rajdhani Industries Prop. Sri Manish Agarwal – Appellant
Versus
Assam Power Distribution Co. Ltd. and 2 Ors. – Respondents
WP(C) 2057 of 2017
Decided on : 19-01-2023

Advocates:
Advocate Appeared:
For the Appellant : MR.S K KEJRIWAL
For the Respondent: MR. P N GOSWAMI

IMPORTANT POINT
The appellate authority under Section 127 of the Electricity Act, 2003 cannot enhance an assessment bill without a cross-appeal and must adhere to principles of natural justice, including providing notice of new evidence to the parties involved.

Headnote:

ELECTRICITY - APPEAL AGAINST ASSESSMENT BILL - Electricity Act, 2003, Section 127; Electricity Supply Code and Related Matters Regulation, 2004, Clause 4.2.2.4 - The court examined the appellate authority's decision under Section 127 of the Electricity Act, 2003, which allows for appropriate orders in cases of electricity theft or malpractice. The court found that the appellate authority exceeded its jurisdiction by enhancing the assessment bill without a cross-appeal from the APDCL and without proper notice to the petitioner. The court highlighted the lack of evidence proving the meter was tampered with or incorrect, rendering the reliance on Clause 4.2.2.4 of the 2004 Regulation inappropriate. The decision emphasized the need for adherence to principles of natural justice and proper procedural compliance.

Fact of the Case:

The petitioner challenged the appellate order and revised assessment bill issued by the Assam Power Distribution Co. Ltd. (APDCL) after an inspection revealed a broken seal on the electricity meter, leading to allegations of meter tampering and a provisional bill of Rs. 5,02,925. The appellate authority later ordered a fresh assessment bill based on consumption patterns, which the petitioner contested as arbitrary and without proper legal basis.

Finding of the Court:

The court found that the appellate authority acted beyond its jurisdiction by enhancing the assessment bill without a cross-appeal and without providing the petitioner notice of the new evidence relied upon. The court ruled that the appellate order lacked a basis for the application of Clause 4.2.2.4 of the 2004 Regulation, as there was no evidence that the meter was incorrect or stopped.

Issues: Whether the appellate authority's order to withdraw the final assessment bill and prepare a new one under Clause 4.2.2.4 of the 2004 Regulation was legally valid and whether the petitioner was afforded due process.

Ratio Decidendi: The court held that the appellate authority exceeded its jurisdiction by enhancing the assessment bill without a cross-appeal and failed to provide the petitioner with notice regarding the new evidence. The lack of evidence proving the meter's tampering or malfunction rendered the reliance on Clause 4.2.2.4 inappropriate, violating principles of natural justice.

Final Decision: The court quashed the appellate order dated 15.02.2017 and the revised assessment bill dated 18.03.2017, restoring the appeal to the appellate authority for a fresh decision in accordance with the law.

JUDGMENT :

Heard Mr. S.K. Kejriwal, learned counsel for the petitioner as well as Mr. K.P. Pathak, learned standing counsel for the APDCL, representing respondent nos.1 and 2. None appears on call for the respondent no.3.

2. The appellate order dated 15.02.2017, passed by the prescribed Appellate Authority constituted under Section 127 of the Electricity Act, 2003 as well as the revised assessment bill dated 18.03.2017, issued by the Assam Power Distribution Co. Ltd. (APDCL for short) have been assailed in this writ petition filed under Article 226 of the Constitution of India.

3. The background facts leading to this case is that on 11.04.2016, an inspection team of 8 (eight) APDCL personnel had inspected the electricity metering installation in the premises of the petitioner firm. During such inspection, the APDCL inspection team found that the left side seal of the cabinet box which housed both the LT and CT meter was broken. Accordingly, the said inspection team decided that it was a case of meter tampering. Resultantly, while the electricity power connection of the petitioner was disconnected and a provisional bill for a sum of Rs.5,02,925/- was served on the petitioner. On payment of Rs.2,51,463/- made to the APDCL, the electricity power to the establishment of the petitioner was restored. On assessment bill having been served on the petitioner, the assessment proceeding was taken up and the Area Manger, IRCA, APDCL. The said authority had heard the representative of the petitioner and by an order dated 19.04.2016, the said authority had held that it was a case of interference with the metering installation and accordingly, it was held that the petitioner was not entitled to any relief in respect of the provisional bill and the said provisional bill served on the petitioner was held to be treated as the final assessment bill.

4. Aggrieved by the said assessment order dated 19.04.2016, the petitioner had preferred an appeal under Section 127 of the Electricity Act, 2003. The Appellate authority i.e. the respondent no.3 heard the matter on 13.02.2017 and by the impugned order dated 15.02.2017, accepted the contention of the respondent no.2 that it was a case of malpractice by interfering with the metering system. However, after taking note of the petitioner’s electricity consumption pattern produced by the respondent no.2 at the time of hearing for the period prior to the date of inspection and after replacement of the new meter on 16.04.2016, had arrived at a conclusion that there was a huge loss on account of consumption till the date of inspection due to negligence of the petitioner within its premises. Accordingly, it was ordered that the final assessment bill for Rs.5,02,925/- confirmed by the Area Manager, IRCA on 19.04.2016 was to be withdrawn and a direction was issued for preparing a fresh assessment bill for a period of 12 months as per clause 4.2.2.4 [Electricity Supply Code and Related Matters Regulation, 2004 (1st Amendment) 2007] (hereinafter referred to as 2004 Regulation), with further direction to serve the same to the petitioner for payment after adjustment of payment already made.

5. Having extensively heard the learned counsel for both sides, the basic point of determination which has arisen for adjudication in this case is whether the appellate order directing (i) the APDCL to withdraw the final assessment bill, and (ii) for preparation of a fresh assessment bill as per clause 4.2.2.4 of the 2004 Regulation is liable to be interfered with.

6. It has been forcefully contended by the learned standing counsel for the respondent nos.1 and 2 to the effect that disputed questions of facts has been raised in this writ petition and moreover, it was submitted that under the provision of Sub-section (3) of Section 127 of the Electricity Act, 2003, the appellate authority is vested with the power to pass an “appropriate order”. Therefore, it was submitted that as because under Clause no.4 (xiii) of the “Statement of Obj

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top