SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Gau) 2199

IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
DEVASHIS BARUAH, J.
M.S. Latala Construction Co. – Appellant
Versus
The Union of India, Rep. by the General Manager Construction, N.F. Railway, Maligaon – Respondent
W.P. (C) No. 6396 of 2025
Decided On : 12-11-2025

Advocates Appeared:
For the Appellant : M. Sharma
For the Respondent: H. Gupta

The court emphasized that interim relief for disputes under arbitration must be sought through the Arbitration and Conciliation Act rather than through a writ petition.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 9 and 17 - Standard General Conditions of Contract - Clause 62 and Clause 64 - Termination of contract - Petition filed to challenge termination notice and seek interim reliefs pending arbitration - The court ruled that the petitioner must pursue remedies under Sections 9 and 17 before appropriate forum, emphasizing that the writ petition is not a suitable avenue for such disputes. (Paras 3, 6, 7, 8)

(B) Jurisdiction of High Court - The court held that it would refrain from exercising jurisdiction when arbitration proceedings have been initiated by the petitioner and any interim relief should be sought within that context. (Para 8)

Facts of the case:
The petitioner challenges the termination notice for inadequate performance, claiming inability to supply due to Supreme Court orders, and seeks relief against termination, refund of deposits, and continuation of work. (Paras 2, 4, 5)

Findings of Court:
The instant writ petition is dismissed, but the petitioner retains the right to approach for interim directions during arbitration proceedings. (Paras 8, 9)

Issues: The primary issue is whether the court should intervene in a matter already designated for resolution through arbitration, specifically concerning interim reliefs and contract rescission. (Para 7)

Ratio Decidendi: The court emphasized that the appropriate recourse for interim relief lies within the Arbitration and Conciliation Act, and not through the High Court, in light of ongoing arbitration proceedings. (Para 8)

Result: Writ petition stands dismissed.

Table of Content
1. challenge to termination notice and request for interim relief. (Para 2 , 4)
2. petitioner's assertion of lawful grounds for contract performance. (Para 5 , 6)
3. jurisdiction concerns and relevance of arbitration pathways. (Para 7)
4. court's dismissal of the writ petition without prejudice. (Para 8 , 9 , 10)

JUDGMENT :

DEVASHIS BARUAH, J.

1. Heard Ms. M. Sharma, the learned counsel appearing on behalf of the Petitioner and Mr. H. Gupta, the learned CGC appearing on behalf of the Respondent Nos. 1 and 2.

2. The present petition is filed challenging the termination notice dated 04/05.09.2025; seeking directions upon the Respondents to refund the Earnest Money Deposit, the Security Deposit as well as the Bank Guarantee. Further to that, the Petitioner also sought for a relief that the Respondents be also directed to permit the Petitioner to resume the balance work after the withdrawal of the mining ban in accordance with the binding directions of the Supreme Court.

3. It is also seen that in the instant writ petition, the Petitioner has sought for the certain interim reliefs. The same being relevant are reproduced herein under:

“(i) Stay the operation and implementation of the impugned termination notice dated 04/05.09.2025 issued by the Respondent No.2, i.e. the Senior Divisional Engineer/I, Lumding Division, N.F. Railway, pending conclusion of the arbitration proceedings initiated between the parties.

(ii) Restrain the Respondents from taking any coercive or adverse action against the Petitioner, including but not limited to forfeiture of Earnest Money Deposit (EMD), Security Deposit, or encashment of the Performance/Bank Guarantee.

(iii) Restrain the Respondents from blacklisting or debarring the Petitioner from participating in the balance work or future contracts related to the subject matter of the present dispute, pending final adjudication of this Writ Petition.

(iv) May pass such other or further interim order(s) or direction(s) as this Hon’ble Court may deem fit and proper in the facts and circumstances of the case.”

4. It is relevant to observe that in the impugned termination notice dated 04/05.09.2025, it was mentioned that the Letter of Acceptance was issued on 20.11.2024 with a completion period of 12 months and the performance was found to be wholly inadequate. It was also mentioned that the Petitioner had supplied only 1535 cum of ballast since the last loading done on 28.02.2025 resulting in issuance of 7 days notice and 48 hours notice on 09.07.2025 and 24.07.2025 respectively. Under such circumstances, in exercise of powers under Clause 62 of the Standard General Conditions of the Contract, the contract with the Petitioner was rescinded with the stipulation that the balance work under the contract would be carried out independently without the participation of the Petitioner. Further to that, the Security Deposit would be forfeited and the Performance Guarantee would also be encashed.

5. It is the case of the Petitioner that the Petitioner was not in a position to make the supply in view of certain orders being passed by the Supreme Court and as such, the said termination was not in accordance with law.

6. At this stage, this Court finds it very pertinent to take note of that the power to rescind the contract is provided in Clause 62((2) of the Standard General Conditions of Contract and the termination order appears to be made in pursuance to the power exercised under Clause 62(2) of the said Standard General Conditions of Contract.

7. This Court further finds it relevant to take note of Clause 64 of the Standard General Conditions of Contract which is an Arbitration Clause. The question therefore arises as to whether this Court should at all exercise the jurisdiction that too when the Petitioner had itself approached for initiation of arbitration proceedings and more particularly when the interim relief so sought for is specific that these interim directions were to be passed during the pendency of the

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top