THE GAUHATI HIGH COURT, (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
DEVASHIS BARUAH, J.
M. S. Arya Erectors India Pvt. Ltd., Represented By Its Managing Director, Mr. Anil Kumar Sarma – Petitioner
Versus
The State Environmental Impact Assessment Authority SEIAA, Represented Member Secretary And Ors. – Respondents
WP(C) No.715 of 2026
Decided On : 11-02-2026
| Table of Content |
|---|
| 1. petitioner's legal representation and ongoing review application. (Para 1 , 8) |
| 2. court's perspective on jurisdiction and appropriate remedy. (Para 2 , 7 , 9) |
| 3. petitioner's grievance regarding unconsidered representation. (Para 3 , 4 , 5 , 6) |
| 4. writ petition dismissed with leave to seek remedies. (Para 10) |
JUDGMENT :
DEVASHIS BARUAH, J.
Heard Mr. S. Dutta, the learned Senior Counsel assisted by Mr. A. Biswas, the learned counsel appearing on behalf of the petitioner. Mr. S. Baruah, the learned counsel appears on behalf of the respondent No.1; Mr. P. Nayak, the learned counsel appears on behalf of the respondent No.2 and Mr. J. Handique, the learned counsel appears on behalf of the respondent No.3.
2. Taking into account the order which this Court proposes to pass, this Court dispenses with the notice upon the proforma respondent Nos.4 & 5.
3. The grievance of the petitioner herein is that the petitioner had submitted a representation on 27.03.2025, pursuant to the directions issued by the State Environment Impact Assessment Authority, (SEIAA) on 15.02.2025 to duly comply with the said recommendations and the said representation dated 27.03.2025 has not yet been considered. It is under such circumstances, the petitioner being in difficulty, has approached this Court by filing the present writ petition.
4. This Court duly takes note of that on the basis of certain complaints being filed by one Ganesh Das and others, a proceedings was initiated before the National Green Tribunal, Eastern Zone Bench, Kolkata, which was registered as Original Application No.92/2023/EZ whereby the SEIAA along with Assam State Public Pollution Control Board were directed to work out the costs incurred in expansion of the project and determine the environment compensation. Further, the SEIAA was also directed to carry out the remedial measures on damage assessment. Directions were also issued directing the SEIAA to take action against the petitioner for violation of the EC condition by complying with the principles of natural justice.
5. In pursuance thereto, the SEIAA took up the matter and submitted a report on 29.01.2025 thereby giving certain recommendations. In pursuance thereto, on 15.02.2025, the Member Secretary of SEIAA informed the petitioner that the SEIAA unanimously decided to send a copy of the report to the project proponent and the petitioner was further directed to comply with the observations and recommendations of the Committee as suggested in the said report.
6. The petitioner thereupon submitted an application before the Chairman, SEIAA on 27.03.2025 stating the difficulties faced by the petitioner to comply with the directions issued by the order dated 15.02.2025 which the petitioner received on 04.03.2025. The said application of the petitioner, however, has not been considered, and under such circumstances, the petitioner has approached this Court seeking interference with the communication dated 15.02.2025 and other consequential directions.
7. This Court has heard the learned counsels appearing on behalf of the parties and is of the opinion that the matter in question emanates from certain directions passed by the National Green Tribunal from the order dated 12.09.2024 in Original Application No.92/2023/EZ. It is further seen that on the basis of such directions, the SEIAA has made certain recommendations. The communication dated 23.07.2025 issued to the Chairman, SEIAA also shows that the petitioner is though interested in complying with the directions passed in the order dated 15.02.2025, but the petitioner in view of certain difficulties stated therein, the petitioner is not in a position to comply. It is the opinion of this Court that these aspects ought to be agitated by the petitioner before the National Green Tribunal.
8. During the course of the hearing, Mr. S. Baruah the learned counsel who appears on behalf of the respondent No.1 submitted that the petitioner has also filed a review application before the N
A High Court cannot entertain a writ petition on matters already under the jurisdiction of the National Green Tribunal, reinforcing the importance of jurisdictional respect and proper channels for en....
Requirements of prior Environmental Clearance - It is a trite law that a writ cannot be issued on ground of violation of principles of natural justice if only one conclusion is possible in a given si....
National Green Tribunal cannot pass ex-parte orders without following principles of natural justice.
A Writ of Mandamus cannot be issued regarding Environmental Clearances when an alternative remedy is available under the National Green Tribunal Act, and the grounds for revisiting such clearances ar....
The National Green Tribunal must ensure adherence to principles of natural justice by allowing parties to present their objections and arguments, particularly in matters concerning environmental prot....
The National Green Tribunal's jurisdiction under Section 16 permits aggrieved parties to challenge environmental clearances to ensure compliance with ecological protection standards.
The main legal point established in the judgment is the importance of adhering to environmental regulations, the jurisdiction of the NGT, and the limitation period for challenging environmental clear....
Violation of principles of natural justice in the imposition of damages for environmental violations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.