SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Gau) 693

THE GAUHATI HIGH COURT, (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
MRIDUL KUMAR KALITA, ANJAN MONI KALITA, JJ.
M/s Sahabuddin Siddique and Anr. – Appellants
Versus
The Union of India, represented by the Secretary, Govt. of India, Ministry of Defence and Ors. – Respondents 
WA/32 of 2025
Decided On : 07-05-2026

Advocates Appeared:
For the Appellants : P.J. Saikia
For the Respondents: Marto Kato.

Disputed questions of fact regarding breach of contract, assessment of liquidated damages, and invocation of bank guarantees cannot be adjudicated under writ jurisdiction. Such matters require determination by a competent civil court or arbitral tribunal, as a party cannot be the sole arbiter of its own breach.

Headnote:(A) Indian Contract Act, 1872 - Sections 73 and 74 - Breach of contract - Liquidated damages - Compensation - Adjudication of disputed questions of fact - Writ jurisdiction - Scope and ambit - A contract cannot provide that one party will be the arbiter to decide whether it committed a breach or the other party committed a breach - Such questions can only be decided by an adjudicatory forum, i.e., a Court or an Arbitral Tribunal - Primary responsibility of the employer is to fix liability against the contractor on the basis of facts that the contractor has breached the contract by delaying performance - Unless such breach is established, the question of imposition of compensation does not arise. (Paras 15, 16)

(B) Writ Jurisdiction - Disputed questions of fact - Invocation of bank guarantee and deduction of liquidated damages - Where there is a dispute regarding the percentage of work completed and the liability for breach, the writ court is not the appropriate forum for adjudication - Parties relegated to seek redress in an appropriate civil court or arbitration. (Paras 14, 16)

Facts of the case:
The appellants, acting as sub-contractors for a road construction project, challenged the termination of the contract and the subsequent invocation of a bank guarantee and deduction of liquidated damages by the authorities. The appellants contended that they were not parties to the main contract and that the deductions were unjustified as they had completed their portion of the work.

Findings of Court:
The court observed that the dispute involved complex questions of fact regarding the percentage of work completed and the validity of the liquidated damages, which could not be resolved in writ proceedings. The court emphasized that the determination of breach and the assessment of damages require an adjudicatory process that cannot be performed by the party alleging the breach.

Issues: Whether the writ court can adjudicate upon the validity of liquidated damages and the invocation of a bank guarantee in the absence of privity of contract and in the presence of disputed factual claims.

Ratio Decidendi: The court held that the determination of breach of contract and the assessment of damages under the relevant sections of the Contract Act require an adjudicatory process that cannot be performed by the party alleging the breach. Consequently, such disputes must be resolved by a civil court or an arbitral tribunal.

Result: Appeal dismissed.

Table of Content
1. summary of factual background and contractual disputes. (Para 1 , 2 , 3)
2. appellants' arguments on lack of privity and disputed liquidated damages. (Para 4 , 5 , 7 , 8 , 10)
3. court's findings on existence of disputed factual questions regarding contractual obligations. (Para 9 , 11 , 12 , 13 , 14)
4. adjudication of breach and liquidated damages requires a competent civil forum. (Para 15 , 16)
5. dismissal of the appeal due to lack of merit. (Para 17)

JUDGMENT :

Anjan Moni Kalita, J.

Heard Mr. P. J. Saikia, learned Senior Counsel assisted by Ms. M. Nirola, learned counsel for the appellants. Also heard Mr. M. Kato, learned DSGI appearing for the Respondent Nos. 1 to 4 and Ms. P. Pangu, learned Government Advocate appearing for the Respondent No. 5.

2. The instant intra-court appeal has been filed by the Appellants assailing the Judgment and Order dated 04.03.2025, passed by the learned Single Judge in WP(C) No. 186 (AP) of 2024.

3. The facts leading to the filing of the instant writ appeal are briefly summarised herein below:

A. The Appellants and one M/s Velecha Engineering Ltd., had entered into a Memorandum of Understanding (MoU) on 15.06.2021, for submitting a tender for “Construction and Up- gradation of Tato-Mechuka Road (design chainage from Km 23.800 to Km 33.100 and existing chainage from 24.800 to Km 36.000 (PKG-II) in the State of Arunachal Pradesh” (herein after referred to as ‘Contract Work’). As per the said MoU, the tender is to be submitted in the name of the aforesaid M/s Velecha Engineering Ltd., and if the work is awarded to M/s Velecha Engineering Ltd., the Appellants will be entitled to execute the entire work, on back to back basis. In the tender process, M/s Velecha Engineering Ltd., came out as a successful bidder and Letter of Acceptance was issued in favour of M/s Velecha Engineering Ltd. As per the terms of the MoU, the Appellants submitted the Bank Guarantee, for the successful tenderer, i.e., M/s Velecha Engineering Ltd., for a sum of Rs. 2,41,65,000/- (Rupees Two Crores Fourty One Lakhs and Sixty Five Thousands) only for the aforesaid Contract Work. However, the Respondent No. 3, vide it’s letter dated 10.12.2021, approved the Appellants as the sub-contractor only for 49% of the value of the Contract Work, amounting Rs.39,46,95,000/- (Rupees Thirty Nine Crores Fourty Six Lakhs and Ninety Five Thousands) only under the aforesaid M/s Velecha Engineering Ltd. The Appellants started the execution of the work and completed 49% of the Contract Work. However, further progress could not be made due to bad weather condition, heavy rainfall, various travel restrictions etc. and due to rejection of the prayer of the aforesaid M/s Velecha Engineering Ltd., for extension of time, the Appellants apprehended that the authorities may impose liquidated damages on the aforesaid bills, which were yet to be submitted. The Appellants faced with the aforesaid, submitted a representation to the respondent authorities on 07.12.2023, praying for releasing the Bank Guarantee as well as other reliefs and not to impose liquidated damages on the bills. While the aforementioned representation was pending, the respondent authorities terminated the Contract with the aforesaid M/s Velecha Engineering Ltd., vide it’s letter dated 16.12.2023. In view of the aforesaid termination, the Appellants approached this High Court by filing the aforesaid writ petition for release of their dues and other consequential reliefs.

B. The respondent authorities by filing their Affidavit-in-opposition denied the contentions made by the Appellants in the writ petition. The stand taken by the respondent authorities was that the respondent authorities had given the Contract Work to M/s Velecha Engineering Ltd., on 29.06.2021 and on their request for approval of the Appellants as a sub-contractor, to execute 49% value of the Contract Work, as per Clause 4.2 of EPC contract, the same was approved by the authorities, vide it’s letter dated 10

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top