THE GAUHATI HIGH COURT, (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
MRIDUL KUMAR KALITA, ANJAN MONI KALITA, JJ.
M/s Sahabuddin Siddique and Anr. – Appellants
Versus
The Union of India, represented by the Secretary, Govt. of India, Ministry of Defence and Ors. – Respondents
WA/32 of 2025
Decided On : 07-05-2026
| Table of Content |
|---|
| 1. summary of factual background and contractual disputes. (Para 1 , 2 , 3) |
| 2. appellants' arguments on lack of privity and disputed liquidated damages. (Para 4 , 5 , 7 , 8 , 10) |
| 3. court's findings on existence of disputed factual questions regarding contractual obligations. (Para 9 , 11 , 12 , 13 , 14) |
| 4. adjudication of breach and liquidated damages requires a competent civil forum. (Para 15 , 16) |
| 5. dismissal of the appeal due to lack of merit. (Para 17) |
JUDGMENT :
Anjan Moni Kalita, J.
Heard Mr. P. J. Saikia, learned Senior Counsel assisted by Ms. M. Nirola, learned counsel for the appellants. Also heard Mr. M. Kato, learned DSGI appearing for the Respondent Nos. 1 to 4 and Ms. P. Pangu, learned Government Advocate appearing for the Respondent No. 5.
2. The instant intra-court appeal has been filed by the Appellants assailing the Judgment and Order dated 04.03.2025, passed by the learned Single Judge in WP(C) No. 186 (AP) of 2024.
3. The facts leading to the filing of the instant writ appeal are briefly summarised herein below:
A. The Appellants and one M/s Velecha Engineering Ltd., had entered into a Memorandum of Understanding (MoU) on 15.06.2021, for submitting a tender for “Construction and Up- gradation of Tato-Mechuka Road (design chainage from Km 23.800 to Km 33.100 and existing chainage from 24.800 to Km 36.000 (PKG-II) in the State of Arunachal Pradesh” (herein after referred to as ‘Contract Work’). As per the said MoU, the tender is to be submitted in the name of the aforesaid M/s Velecha Engineering Ltd., and if the work is awarded to M/s Velecha Engineering Ltd., the Appellants will be entitled to execute the entire work, on back to back basis. In the tender process, M/s Velecha Engineering Ltd., came out as a successful bidder and Letter of Acceptance was issued in favour of M/s Velecha Engineering Ltd. As per the terms of the MoU, the Appellants submitted the Bank Guarantee, for the successful tenderer, i.e., M/s Velecha Engineering Ltd., for a sum of Rs. 2,41,65,000/- (Rupees Two Crores Fourty One Lakhs and Sixty Five Thousands) only for the aforesaid Contract Work. However, the Respondent No. 3, vide it’s letter dated 10.12.2021, approved the Appellants as the sub-contractor only for 49% of the value of the Contract Work, amounting Rs.39,46,95,000/- (Rupees Thirty Nine Crores Fourty Six Lakhs and Ninety Five Thousands) only under the aforesaid M/s Velecha Engineering Ltd. The Appellants started the execution of the work and completed 49% of the Contract Work. However, further progress could not be made due to bad weather condition, heavy rainfall, various travel restrictions etc. and due to rejection of the prayer of the aforesaid M/s Velecha Engineering Ltd., for extension of time, the Appellants apprehended that the authorities may impose liquidated damages on the aforesaid bills, which were yet to be submitted. The Appellants faced with the aforesaid, submitted a representation to the respondent authorities on 07.12.2023, praying for releasing the Bank Guarantee as well as other reliefs and not to impose liquidated damages on the bills. While the aforementioned representation was pending, the respondent authorities terminated the Contract with the aforesaid M/s Velecha Engineering Ltd., vide it’s letter dated 16.12.2023. In view of the aforesaid termination, the Appellants approached this High Court by filing the aforesaid writ petition for release of their dues and other consequential reliefs.
B. The respondent authorities by filing their Affidavit-in-opposition denied the contentions made by the Appellants in the writ petition. The stand taken by the respondent authorities was that the respondent authorities had given the Contract Work to M/s Velecha Engineering Ltd., on 29.06.2021 and on their request for approval of the Appellants as a sub-contractor, to execute 49% value of the Contract Work, as per Clause 4.2 of EPC contract, the same was approved by the authorities, vide it’s letter dated 10
Disputed questions of fact regarding breach of contract, assessment of liquidated damages, and invocation of bank guarantees cannot be adjudicated under writ jurisdiction. Such matters require determ....
An employer cannot unilaterally determine a breach of contract or impose liquidated damages. Such disputes, involving questions of fact and the absence of privity of contract between an employer and ....
The court upheld the validity of contract termination due to non-completion of work, affirming that claims for liquidated damages should be pursued in civil court.
Validity of subcontracting requires prior approval; payment cannot claim without completed work or legal agreement.
Point of law: When the appeal is presented in terms of Section 96 CPC and when this Court is considering this appeal not only as a last Court of fact but also in terms of law, it is open for the appe....
Section 8 of Act is an example of referring parties to arbitration.
Arbitration Award - An Award however can be interfered with if it is found to be vulnerable under any of the grounds in Section 34 including being in contravention with the fundamental policy of Indi....
Section 16 lays down that even interest is payable on amount entitled to by a unit.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.