THE HIGH COURT OF GAUHATI (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
ROBIN PHUKAN, J
M/s Sahabuddin Siddique And Anr - Appellant
Versus
The Union Of India And 6 Ors - Respondent
WP(C) 186 / 2024
Decided On : 04-03-2025
(A) Contract Law - Contract termination - Performance guarantees - Liquidated damages - Petitioners sought relief for pending bills and release of bank guarantees after contract termination due to non-completion of work. The court found the termination was not arbitrary and upheld the contract terms. (Paras 3 , 18 )
(B) Joint verification - The court directed the respondent authorities to release pending bills based on joint verification with the petitioners, while compensation claims were relegated to civil court. (Paras 18 )
Facts of the case:
The petitioners were subcontractors for road construction in Arunachal Pradesh, facing deductions and termination due to non-completion attributable to external factors. (Paras 3 , 4 )
Findings of Court:
The court ruled the termination and bank guarantee forfeiture were justified, while directing release of pending bills based on joint verification. (Paras 18 )
Issues: Main issues included the validity of contract termination, entitlement to pending payments, and the nature of liquidated damages. (Paras 18 )
Ratio Decidendi: The court emphasized that contract terms were binding, and failure to meet milestones justified termination; compensation claims should be pursued in civil court. (Paras 18 )
Result: Petition partly allowed; pending bills to be released, other claims to civil court.
JUDGMENT :
ROBIN PHUKAN, J.
Heard Mr. P.J. Saikia, learned Senior Counsel, assisted by Ms. M. Nirola, learned counsel for the petitioners. Also heard Mr. M. Kato, learned Dy.S.G.I. for the respondent Nos. 1, 2, 3 and 4 and heard Ms. S. Basar, learned Government Advocate, for the respondent No. 5.
2. In this petition, the petitioners M/s Sahabuddin Siddique and Sri Sahabuddin Siddique, have prayed for following reliefs:
(i) To direct the respondent authorities to release all the pending bills for the works executed by the petitioners, after carrying out a joint verification by the BRO authority and the petitioners, and pay the bill amount directly to the bank account of the petitioners, without imposing any liquidated damages, compensation etc.
(ii) To direct the respondent authorities to refund/releasethe withheld amount of Rs. 4,47,32,154/-, being deducted for liquidated damages including other deductions.
(iii) To direct the respondent No. 3 to refund the amount of Rs. 2,41,65,000/- covered by the Bank Guarantee No. 6343NDDG00019222 and Bank Guarantee No. 6343NDDG00007722, in connection with the aforementioned project.
(iv) To direct the respondent No. 3 to issue work completion certificate to the petitioners for the said project to the extent of 49% of accessible available scope of work executed by the petitioners.
3. The background facts, leading to filing of the present petition, are briefly stated as under:
“The petitioner No. 1, M/s Sahabuddin Siddique had been approved as subcontractor under the respondent No. 6, Valecha Engineering Ltd. (VEL), by the respondent No. 3, vide its letter dated 10.12.2021, to the extent of 49% value of contract work for a sum of Rs. 39,46,95,000/-, for ‘Construction and Upgradation of Tato-Mechuka Road (design chainage from km 23.800 to km 33.100 and existing chainage from km 24.800 to km 36.000)(PKG-II) in the State of Arunachal Pradesh’. The petitioners had submitted bank guarantee for a sum of Rs. 2,41,65,000/- for the aforementioned project as per Memorandum of Understanding (MoU), dated 15.06.2021, executed between the respondent No. 6 and the petitioner No. 1. Thereafter, the petitioners had started execution of the work, being approved as subcontractor. But, the work could not be completed in time due to bad weather condition, heavy rainfall, various travel restrictions etc. Thereafter, the respondent authorities in the BRO, had illegally deducted various amounts of money from the bills already submitted before them as deductions and compensations for reasons solely attributable to the respondent No. 6. But, despite all the aforesaid problems, the petitioners had carried out and completed 49% of the work. Thereafter, on 07.12.2023, the petitioners filed a representation before the respondent authorities to issue completion certificate, and also to release bank guarantee and to release the liquidated damages deducted by the respondent authorities as well as the amounts withheld by the respondent No. 6, and further requested to settle the pending bills for the work executed by the petitioners without imposing any liquidated damage. However, nothing has been done by the respondent authorities on account of termination of the contract with the respondent No. 6. Being aggrieved, the petitioners have approached this Court.”
4. The respondent Nos. 1 to 4 have filed their affidavit-in-opposition denying the averments made in the petition. It is stated that the work for construction and upgradation of Tato-Mechuka Road (design chainage from km 23.800 to km 33.100 and existing chainage from km 24.800 to km 36.000) to 2 lane with hard shoulders, under project Brahmank in the State of Arunachal Pradesh, on Engineering Procedure and Construction (EPC) Mode, was awarded to the respondent No. 6, being the L1 bidder, and that the respondent Nos. 1 to 4 are not aware of any Memorandum of Understanding between the petitioners and the respondent No. 6, and the petitioners were approved as subcontracto
The court upheld the validity of contract termination due to non-completion of work, affirming that claims for liquidated damages should be pursued in civil court.
Disputed questions of fact regarding breach of contract, assessment of liquidated damages, and invocation of bank guarantees cannot be adjudicated under writ jurisdiction. Such matters require determ....
An employer cannot unilaterally determine a breach of contract or impose liquidated damages. Such disputes, involving questions of fact and the absence of privity of contract between an employer and ....
The court established that claims for payment under a subcontract must be pursued through appropriate civil channels, particularly when they involve disputed facts and contractual obligations.
Arbitral awards are not subject to interference unless they exhibit patent illegality; the interpretation of contractual obligations falls within the jurisdiction of the Arbitral Tribunal.
Point of Law : Arbitral Tribunal had erred in concluding that the petitioner had abandoned the works, is also unpersuasive. The finding that the petitioner had abandoned the works is a finding of fac....
A party failing to comply with contractual terms may be subject to termination even if claiming force majeure circumstances.
Bank guarantees can be invoked only if the invocation itself is legal, and the party seeking injunction must show that allowing encashment would result in irretrievable harm or injustice.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.