THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) 
DEVASHIS BARUAH, J. 
Rukmin Enterprise, Rep. By its proprietor And Anr. – Petitioner
Versus
The State Of Assam, Rep. By The Commissioner And Secretary to the govt. Of assam and ors. – Respondent
WP(C) 2117 of 2024 
Decided On : 20-04-2026

Advocates Appeared:
For the Petitioners:Mr. D. Baruah, Advocate
For the Respondents: Ms. G. Bora, Standing Counsel

Contractual payments for public works are enforceable upon the state, provided the claimant establishes successful execution and provides documented proof. Authorities must conduct a timely verification of the completed project and evidentiary documents before processing the outstanding financial claims.

Headnote:(A) Writ Jurisdiction - Contractual dispute - Non-payment of dues - Petitioners seeking release of outstanding payment for construction work awarded through a tender process - Court directed respondent authorities to verify fulfillment of work and documentation requirements to determine entitlement to payment - Exercise to be completed within a fixed timeframe. (Paras 2-7)

Facts of the case:
Petitioners performed construction work as awarded under a contract and obtained a completion certificate. Despite submission of bills and representations, the due payment remained outstanding. A petition was filed seeking issuance of necessary directions for the release of payment.

Findings of Court:
The court observed that there was no denial regarding the award and execution of the work. It was held that provided the execution of work and submission of documentation are confirmed, the authorities are obligated to process and clear the outstanding dues.

Issues: Whether the respondent authorities are required to verify the performance of the contract and supporting documentation to process the release of outstanding contractual payments.

Ratio Decidendi: The obligation to honor contractual payments for executed works rests upon the state, contingent upon the successful completion of the work and independent verification of the requisite documentation by the concerned authorities.

Result: Petition disposed of with directions to complete verification and payout procedures within six months.

Table of Content
1. factual overview of contractual obligations and payment disputes. (Para 1 , 2 , 3 , 4)
2. state admission regarding work completion subject to official verification. (Para 5)
3. judicial mandate for verification and timely settlement of contractual dues. (Para 6 , 7)

JUDGMENT :

DEVASHIS BARUAH, J.

Heard Mr. D. Baruah, the learned counsel appearing on behalf of the Petitioners and Ms. G. Borah, the learned Standing counsel appearing on behalf of the Agriculture Department.

2. The instant writ petition has been filed by the Petitioners challenging the non-payment of the contractual bill amounting to Rs. 4,00,000/- for the work awarded to the Petitioners pursuant to the NIT dated 03.12.2021 for Construction of Senior Citizen/Farmer’s waiting room at District Agricultural Office, Kamrup.

3. The case of the Petitioners herein is that pursuant to the NIT dated 03.12.2021, the Petitioners were awarded the contract vide Work Order No. EE/Agri/KD/Guw/Tech-01/2020-21/1683 dated 28.12.2021 for the work in question. It is the further case of the Petitioners that, pursuant to the Work Order dated 28.12.2021, the Petitioners started the construction work with their own resources and finances and duly completed the same in accordance with the prescribed specifications. A completion certificate was also issued by the Respondent Authorities vide certificate dated 03.02.2023.

4. It is the further case of the Petitioners that after completion of the work, the Petitioners had submitted the bills and the Petitioner had also made several representations before the Respondent Authorities from time to time for release of the aforesaid dues, but the Respondent Authorities more particularly, the Respondent No.5 are sitting over the matter. Consequently, finding no other alternatives, the Petitioners have approached this Court by way of the instant writ petition.

5. Ms. G. Bora, the learned Standing Counsel appearing on behalf of the Agriculture Department submitted that there is no denial to the fact that the work in question was issued to the Petitioners. The learned Standing Counsel however, submitted that the entitlement of the Petitioners would depend upon verification to be carried out by the Respondent Authorities.

6. Upon perusal of the materials on record, this Court is of the opinion that if the Petitioners had completed the abovementioned work, the Petitioners would be entitled to the amount. However, for the same, verification on the part of the Respondent Authorities would be required.

7. This Court therefore disposes of the instant writ petition with the following observations and directions:-

(i) The Respondent Authorities shall verify as to whether the Petitioners had successfully executed the work, i.e. Construction of Senior Citizen/Farmer’s waiting room at District Agricultural Office, Kamrup.

(ii) The Respondent Authorities shall also verify as to whether the Petitioners had submitted the requisite documents which are required for the purpose of releasing the amount due as claimed by the Petitioners.

(iii) The Respondent Authorities shall also verify the entitlement of the Petitioners to the dues, and if upon verification in the manner stated above, it is found that the Petitioners are entitled to any such amount, the Respondent Authorities shall pay the same to the petitioners.

(iv) The above exercise be completed within a period of 6 (six) months from the date a certified copy of the instant order is served upon the Respondent No.2, i.e. the Director of Agriculture, Office of the Directorate of Agriculture, Assam, Khanapara.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top